The same process went on until the issuance of the 4th FAT dated 29.10.2009 whereby all of the equipment were certified to be in good condition and in accordance with the specifications. [7] However, on 13.1.2010 while undergoing a free-fall training at Zon Guguran Semalu, Kem Trendak, Melaka, the plaintiff discovered that equipment was damaged where stitches on the one side of the pilot chute cap were broken and all seams in the pilot chute cap were loose. The plaintiff, by a letter dated 25.2.2010 had instructed the defendant to remedy the aforesaid damage which the defendant did. By 30.7.2010 all the equipment could then be used for its purpose. [8] A payment of RM1,050,000 was then made on 6.11.2010 by the plaintiff to the defendant after the issuance of the final FAT report. After the payment was made, the Parachute Board of the Malaysian Army, during a meeting held on 26.11.2010 had resolved that the defendant should conduct another test on all the 52 units of the equipment. Subsequently, the plaintiff and defendant had met and it was purportedly agreed that the defendant would refund the plaintiff the sum of RM1,050,000 and the plaintiff agreed to return the equipment to the defendant. 5 [9] The defendant’s position is that it had performed its obligation under the Agreement and this had been made known to the plaintiff on 17.3.2011. [10] The plaintiff in this action is claiming for the refund of the said sum of RM1,050,000 and interest at the rate of 5% per annum from the date of judgment to the date of full realisation. The application under O 14A [11] The application in Encl 10 is supported by the affidavit (“AIS”) of Tifla Hairi Taib (“Tifla”), who is the legal and secretarial manager of the defendant, affirmed on 16.1.2018. The plaintiff then filed an affidavit in reply (“AIR”) affirmed by Mohamad Ridzuan bin Ismail (“Ridzuan”) dated 30.1.2018. Ridzuan is the deputy under-secretary procurement division, Ministry of Defence, Malaysia. [12] In response thereto, Tifla had filed a further affidavit (“FAIS”) dated 19.2.2018. Is there any dispute on the relevant facts? [13] The first thing that this Court has to determine is whether there was a dispute on the relevant facts that would be a hurdle in disposing the matter under O 14A of the ROC. [14] I can only summarise the position as follows. The plaintiff is objecting to the application since the issues raised in the instant 6 suit could not be disposed of by way pleadings and affidavit evidence. [15] The learned Federal Counsel submitted that the action could only be disposed of by way of viva voce evidence, especially so in respect of the acceptance of the equipment, the quality and the extent of the defects. It is also the plaintiff’s case that the defendant had failed to conduct a re-testing of the equipment pursuant to the meeting dated 26.11.2010. In fact, a letter dated 13.12.2010 [Exh MRI-1 of the AIR] the defendant offered to conduct the said re-testing. [16] The defendant’s case is quite straightforward. First, all of the tests required by the Agreement had been conducted and perfected on 15.12.2009 and a final certificate had been issued. Paragraphs 9 and 10 of the statement of claim provides as follows: [9] Plaintif kemudiannya telah mengesahkan semua Payung telah dibuat pembaikan pada 30 Julai 2010 dan boleh digunakan. [10] Pada 6 November 2010, Plaintif telah membuat pembayaran kepada Defendan berjumlah RM1,050,000 selepas dokumen Laporan Final Acceptance Test (FAT) disediakan dan disahkan. From the averments of the plaintiff it is quite clear that the plaintiff had conceded that by 30.7.2010, the defendant had 7 remedied the defects to the extent that it could be used by the plaintiff. This was duly certified, and for this reason, the plaintiff had made payment to the defendant for the contractual sum as referred to in cl 5.1 of the Agreement. [17] In answer to the issuance of the letter dated 13.12.2010 [Exh MRI-1 of AIR], the defendant averred that such an offer was not mandatory and not even provided for in the Agreement. It cannot in anyway bind the defendant. The analysis [18] The Final Certificate which was dated 15.12.2009 [Exh THT-2 of the AIS] and signed by both parties clearly stated as follows: Dengan ini disahkan bahawa BARANG-BARANG seperti yang dinyatakan telah dilaksanakan mengikut SPESIFIKASI KERAJAAN seperti di Jadual kedua kepada kontrak ini dan ia telah diperiksa dan diuji oleh Wakil Kerajaan dan berpuashati dengan ujian yang telah dijalankan. Learned counsel for the defendant submitted that the issuance of the Final Certificate should be read together with cl 37.2 of the Agreement which provides inter alia that the warranty period of the equipment is one year from the date of the Final Certificate. It further provides that the defendant would only be contractually liable to remedy any defects if it occurred within the warranty period. The procedure is that the defendant would have to remedy or replace the defective part of the equipment 8 within 30 days of receipt of the notice of rejection from the plaintiff. [19] Going by the Final Certificate which was dated 15.12.2009, it means the warranty period would have ended on 15.12.2010. If the plaintiff would like to exercise its right under cl 16 in rejecting part of the equipment, what the plaintiff should have done was to serve a Notice of Rejection under cl 16.1 of the Agreement which would give a 30-day notice to the defendant to replace or otherwise remedy the defective part of the equipment. [20] I have gone through the respective pleadings of the parties herein and could not find anything therein that refers to any notice made under cl 16.1 of the Agreement. It should be borne in mind that before even cl 37.2 comes into operation the notice under cl 16.1 must be issued first. It is, if I may, a condition precedent. [21] What that is exhibited in Exh MRI-2 of the AIR is the minutes of the meeting held on 29.11.2010. To me, the minutes of the meeting is irrelevant. Minutes of the meeting including its resolution thereto could not be construed as a Notice of Rejection. What is more important is that the Notice of Rejection should have been issued before the last date of the warranty period within the meaning of cl 16.1 of the Agreement. [22] The same applies to any parts of the defective equipment which need to be remedied or replaced. If there was no such Notice of Rejection issued by the plaintiff, the plaintiff could not rely on cl 9 37.4 of the Agreement which provides for the same warranty period for the defective part of the equipment. [23] In fact, the Agreement is so comprehensive that there is a specific format of the Notice of Rejection as can be seen in