The evidence in this case showed that the IKBN project was completed on 28 February 2015, which meant that the plaintiff was not out of time when it commenced this action in June 2018. [20] Hence, the learned trial judge concluded that there was conditionality to the repayment of the loan and that it was to be repaid upon demand after completion of the IKBN Project. The IKBN Project was completed on 28.2.2015. This action was filed on 6.6.2018. Thus, the 9 claim was filed well within the 6 years limitation period prescribed in section 6(1)(a) of the Limitation Act 1953. The law on appellate intervention on findings of fact [21] The law on appellate intervention in respect findings of facts made by a trial court is well settled. We are reminded of the general rule that an appellate court should be slow to interfere with the findings of fact of a trial court unless the findings were arrived at with no or insufficient judicial appreciation of the evidence before it to render such findings plainly wrong; or the findings were the result of a misdirection by the trial court on the applicable law or there was a wrong application of the law to the facts; or the findings were of a kind which a reasonable court similarly circumstanced, which had properly directed itself and asked the right questions, would not have arrived at (see: China Airlines Ltd. v. Maltran Air Corp Sdn Bhd. & Another Appeal [1996] 3 CLJ 163 (FC); Lee Ing Chin @ Lee Teck Seng & Ors v. Gan Yook Chin & Anor [2003] 2 CLJ 19; [2003] 2 MLJ 97 (CA); Gan Yook Chin (P) & Anor v. Lee Ing Chin @ Lee Teck Seng & Ors [2004] 4 CLJ 309; [2005] 2 MLJ 1 (FC); Sivalingam Periasamy & Anor v. Periasamy & Anor [1996] 4 CLJ 545). 10 Submissions of appellant’s counsel [22] Learned counsel for the appellant submitted that the learned trial judge had failed to fully appreciate the evidence and that the factual findings went against the documentary evidence and admission of PW3 that the loan was unconditional. We find this contention to be bereft of any merit. PW3 testified as follows in his Witness Statement: What was the term of repayment of the RM2.5 million loan? When the 2nd Defendant approached me to lend him the money of RM2.5 million on or about 19.12.2007, he personally informed me that the monies were used to finance the IKBN Project and request me not to demand for repayment of the RM2.5 million loan when the IKBN Project is on-going until and unless full completion of the said project of which the Plaintiff also has participated in the supply business as well. Are you saying that the repayment of RM2.5 million loan was conditioned? Yes, it is a conditional loan tied with IKBN Project. The loan of RM2.5 million is pay back on condition that the IKBN Project is fully completed and contract money is fully received from KBS. [23] This evidence was challenged by counsel for the appellant in cross-examination, but PW3 stood firm and remained unshaken. The following part of the cross-examination is relevant: And the response to that today, their response to that today is that they don’t owe you the 2.5 million anymore, do you agree? No I don’t agree. 11 I am putting it to you that they have stated that because Khazanah Jaya’s position is that the recovery of the loan is now statute barred agree. No I don’t agree. DK: I am not asking you whether it is statute barred or not I am asking you they have always told you that it is statute barred. Well he told me that way. I don’t agree. But you do agree he told you that? Yeah I agree he told me that. But what he said I do not agree. [24] And in re-examination PW3 stated: Everything is based on oral, so when BK Tan need to borrow the money we get him the money. So orally he should pay me back when I want the money back but every time when I chase for the money he will say the project is not completed, so project is not completed so the condition is okay, let the project completed, you should pay us back the money. After that also never pay the money that is why we sue them. That is the main reason. [25] Learned counsel for the appellant submits that there were several oral demands for repayment of the loan in late 2012 and 2013, and this suggests that the repayment was not conditioned upon completion of the IKBN Project. Though there were such oral demands, PW3 explained that when those demands were made the appellant had stated that they would repay the loan upon completion of the IKBN Project, and the respondent had agreed to that. The respondent then waited until after completion of the IKBN Project to demand payment. 12 [26] In fact, we find that this evidence supports the respondent’s contention that the repayment was to be made after completion of the IKBN Project. PW3 had stated in his testimony that after completion of the IKBN Project in 2015, he had on various occasions orally demanded repayment of the loan and the 2nd defendant had always given some promise of repayment that never materialized. The following excerpt from PW3’s Witness Statement is pertinent to the issue: Upon completion of the IKBN Project, does the Plaintiff demand for repayment of the RM2.5 million loan from the Defendants? Upon completion of the IKBN Project in 2015, I had on numerous occasions orally demanded from the 2nd Defendant to repay the RM2.5 million. But every time the 2nd Defendant requested the Plaintiff to wait and if the Plaintiff really wanted the loan of RM2.5 million repaid quickly he can offer the Plaintiff some property in Bandar Seri Gemilang at Lahad Datu, Sabah or lands from China projects could be transferred to the Plaintiff as repayment of the loan. However, what he promised was never materialized. It is just to induce me to delay pursuing back the loan. [27] The evidence shows that from 2013 till the completion of the project there were no written demands made, until the issuance of the 1st Written Demand on 16.8.2017, and the Statutory Notice dated 6.9.2017. There was no response from the appellant to the 1st Written Demand, however, the appellant disputed the Statutory Notice. [28] Learned counsel for the appellant further submits that the first time that respondent raised the issue of the repayment of the loan being 13 conditional on the completion of the IKBN Project was in the Reply to Defence. Counsel submitted that the respondent had an earlier opportunity to raise this namely in an application for a Fortuna Injunction made by the appellant to restrain the respondent from filing a winding-up Petition, but did not do so. Thus, the appellant contended that this issue was an afterthought to save the respondent’s claim from statutory time-bar. [29] We find that there is no substance to this contention. The respondent had issued the 1st Written Demand and the Statutory Notice demanding repayment of the loan. When the appellant disputed the loan on the basis of limitation in the Fortuna Injunction application, the respondent made a call not to proceed with winding-up but instead chose to have the matter resolved by way of the civil action. This was a prudent course to take as first obtaining a judgment on their claim would be the better option than proceeding with winding-up in the face of a disputed debt. Thus, the lack of averment by the respondent during the Fortuna Injunction proceedings as to when the loan was to be repaid, was not indicative whether the loan was an unconditional demand loan. The court would have to look at the evidence in its entirety before concluding whether the loan was unconditional as contended by the appellant. 14 [30] Applying the legal principle governing the burden of proof in a civil claim, we are in agreement with the learned trial judge that based on the facts and circumstances of the present case, the respondent had sufficiently discharged its evidential burden to establish a prima facie case that the loan of RM2.5 million made to the appellant was for the purpose of funding the IKBN Project, and that it was repayable upon demand after completion of the project. Having established that, the evidential burden had shifted to the appellant to lead, by admissible evidence based on their pleaded case, that there were no such condition for repayment of the loan and that the loan was repayable upon demand simpliciter. We further agree with the learned trial judge that the appellant had failed to discharge that evidential burden. See: Wong Hon Leong David v. Noorazman Bin Adnan [1995] 4 CLJ 155; [1995] 3 MLJ 283 and in Tan Aik Teck v. Tang Soon Chye [2007] 5 CLJ 441; [2007] 6 MLJ 102. [31] A similar issue to whether a claim for repayment of a friendly loan was statute barred by limitation came up for consideration in Kam Seng Realty Sdn Bhd v Dato Tai Fatt Yew & Anor [2012] 7 MLJ 825, where Mohamad Ariff J (as he then was) held: [39] The issue on limitation revolves around the question whether there were agreed terms of repayment, and if they were no such terms, when the limitation period can be said to run. The minutes of the board of directors meeting referred to earlier, merely refers to 'upon such terms and conditions mutually agreed by 15 both parties thereat'. What these terms and conditions are cannot be gathered from the minutes themselves. Mr Jayakumar, counsel for the first defendant, refers to the common law rule that stipulates where there is no fixed date for repayment of the loan, the period of limitation runs from the earliest time at which an action could be brought'. See the observations of the Federal Court in Nadefinco Ltd v Kevin Corporation Sdn Bhd [1978] 2 MLJ 59 and the reference to the English case of Reeves v Butcher [1891] 2 QB 509, where Lindley LJ was quoted as stating, 'the right to bring an action may arise on … this event; but it has always been held that the statute runs from the earliest time at which an action could be brought.' See also the decision of the Singapore High Court in Tay Ivy v Tay Joyce [1992] 1 SLR 893 when it is stated that in the case of a loan simpliciter, as a loan repayable from the date of advance, limitation runs from the date of advance. On the evidence, as seen earlier, the date of advance of this particular friendly loan is 14 January 2004. The writ is issued on 24 March 2010. With the limitation period of six years stipulated under s 6(1) of our Limitation Act 1953, if time is taken to run from the date of the advance, the plaintiff's claim will be time-barred. The issue then turns very much on whether they were in fact terms of repayment agreed between the parties. This again is a matter of evidence. [32] Similarly, in the present case, the learned judge had construed the evidence as a whole before coming to the conclusion that the claim was not time-barred. We do not find that there was any lack of appreciation of the evidence by the learned trial judge. We agree with the submissions of learned counsel for the respondent that the learned trial judge had considered the totality of the evidence, the inherent probability of the case, and had drawn the proper inferences from the evidence. There was full and mature consideration of the evidence and there was proper application of the law to the established facts of the case. The learned 16 trial judge had neither misdirected himself on any point of law nor applied any wrong principles of law to warrant appellate intervention. 2nd Issue - The pleadings point [33] The appellant contends that in the Statement of Claim, the cause of action is premised upon an unconditional interest free loan repayable upon demand, and that there is no mention in the Statement of Claim: