2.3 After the aforesaid determination / termination, the Defendant did not bring any action whatsoever against the Plaintiff for the alleged retention sum amount of RM231,250.00 and the alleged GST amount of RM13,875.00 within the limitation period of 6 years as provided for by the Limitation Act 1953; and it was alleged that the Defendant’s current action, more than 6 years later, is now time-barred and/or statute-barred under Section 6 Limitation Act 1953. Factual Background [3] The Plaintiff is the main Contractor of the Project [4] By way of a Letter of Award dated 28-01-2015, Tunjong Galleria Sdn Bhd (as the Project’s Employer) awarded the Works of the Project to the Plaintiff (as the Main-Contactor); and subsequently, the Project’s Employer and the Plaintiff signed and executed a Formal Contract dated 11-01-2016 incorporating the Agreement and Conditions of PAM [“Pertubuhan Arkitek Malaysia”] Contract 2006 (With Quantities)[“Main-Contract”]. [5] By way of a Letter of Award dated 20-07-2015, the Plaintiff (as the Project’s Main-Contractor) appointed the Defendant as Nominated Sub-Contractor in respect of the “Supply, Installation, Testing and Commissioning of Air-Conditioning & mechanical Ventilation Services” for the Project; and subsequently the Plaintiff and the Defendant signed and executed a formal contract incorporating “Agreement and Conditions of PAM Sub-Contract 2006” [“Sub-Contract”]. [6] On or thereabouts 04-08-2016, the Plaintiff, via its Solicitors, Messrs Andrew – David Wong & Ong’s letter dated 01-08-2016, duly gave a Notice of Default to the Projects’ Employer; and upon the Project Employer’s failure, refusal and/or neglect to rectify the defaults as stated therein, the Plaintiff, via its Solicitors letter dated 23-8-2016, duly gave a Notice of Termination to the Project’s Employer, and determined the Plaintiff’s employment in respect of the Project and/or terminated the Main-Contract between the Plaintiff and the Project Employer. [7] It is alleged that the aforesaid Plaintiff’s determination of their own employment and/or termination of the Main-Contract had forthwith automatically determined the Sub-Contract between the Plaintiff and the Defendant in accordance with Clause 25.2 of the PAM Sub-Contract Conditions in the Sub-Contract. [8] It is further alleged that at all material times, the Defendant was well aware of the aforesaid Plaintiff’s determination of their own employment and/or termination of the Main-Contract vide the Plaintiff’s letter dated 05-09-2016, which the Defendant had acknowledged receipt thereof vide the Defendant’s letter dated 07- 10-2016. [9] On or thereabouts 16-02-2023, the Defendant’s Solicitors served the Plaintiff with a Payment Claim dated 16-02-2023 for a total sum of RM245,125.00 comprising of an alleged retention sum amount of RM231,875.00 and an alleged “Goods and Service Tax” [“GST”] amount of RM13,875.00 in respect of the Sub-Contract for the Project. [10] However, after the aforesaid determination/termination, the Defendant had never brought any action whatsoever against the Plaintiff for the alleged retention sum amount of RM231,250.00 and the alleged GST amount of RM13,875.00 within the limitation period of 6 years as provided for by the Limitation Act 1953. Findings of this Court [11] The Plaintiff had contended that the purported reference of disputes to adjudication vide its Notice of Adjudication dated 3.3.3023 registered under ‘AIAC/D/ADJ-4619-2023’ (Notice of Adjudication) is time barred and/or statute barred under section 6 (1) LA. [12] To the above the Plaintiff submits that the sum of RM245,125 currently claimed by the Plaintiff in the Payment claim dated 16.2.2023 is comprised of the alleged retention sum and the GST of RM13,875 in respect of the Sub Contract. For this I have examined the Notice of Adjudication exhibit LAL 8 in enclosure 3 and confirm that it was expressly stated therein that “The dispute involves the sum of RM245,125 comprising the 6% retention sum of RM231,250 and 6% GST of RM13,875.” [13] From the facts before this Court, the Plaintiff had appeared to determine their employment contract between the Plaintiff and its Employer, Tunjong Galleria Sdn Bhd, on 23.8.2016 as shown in exhibit LAL 3 of enclosure 2, vide their Solicitors, Messrrs Andrew – David Wong & Ong’s letter of even date. [14] It is thus argued by the Plaintiff that due to the aforesaid termination of the Main Contract, the Sub Contract between the Plaintiff and the Defendant was forthwith automatically determined. [15] I have observed that in accordance with clause 25.1 and 25.2 of the PAM Sub Contract Conditions between the Plaintiff and the Defendant at exhibit LAL 2 of enclosure 2, it is provided that: “25.1 If the employment of the Contractor is determined by the employer under clause 25.0 of the Main Contract Conditions, then the employment of the sub contractor under the Sub Contract shall be forthwith automatically determined and the provision of clauses 23.6 and 23.7 of the Sub contract shall apply.