(iv) Parties had to furnish their respective sureties to guarantee performance of their obligations. [16] To protect its interest in Lot 3 and 4, the Plaintiff lodged a private caveat. Litigation pertaining to the removal of the caveat has since ended. The Court of Appeal allowed the caveat to remain until the conclusion of the present suit. [17] Subsequent to the execution of the 2nd JVA, events transpired which led to the present dispute. Apart from the earthworks which were carried out, the development of the said land did not proceed further. The factories were not constructed. The reason as to the Plaintiff’s failure to construct is the crux of the present dispute. The Plaintiff’s case [18] The Plaintiff contends that the Defendant’s conduct prevented it from proceeding with its performance of the contract. [19] Mr Lee Kok Tian (PW1), a director of the Plaintiff testified that after the building plan was approved on 17.9.2015, DW3 (a director of the Defendant) proposed to delay commencing with further development of the said land for one year as he was unable to finance the construction costs. The Plaintiff was further informed that the Defendant planned to either sell its entitlement namely Lot 1 and 2, or to apply for financing. [20] By the time the Plaintiff received the instruction to delay construction, it had already appointed Pangkat Beruntung Sdn S/N cjcUpVhlIkmEANBG0qLxng Bhd. (“Pangkat Beruntung”), to manage the development project. By a letter of appointment dated 3.4.2014, Pangkat Beruntung was appointed the project consultant for the construction of four units of three storey semi-detached office factory. It was to be responsible for applying, submitting, and securing all relevant approvals, permits, licences from the authorities. Its team comprised a planner, architect, civil, structural, mechanical and electrical engineer as well as a quantity surveyor. However, in view of the Defendant’s instruction to delay commencing with construction, it had no choice but to instruct Pangkat Beruntung to halt the carrying out of further works. [21] Sometime in 2016, DW3 informed PW1 that he would use his company Foamcrete Cornice Sdn Bhd (“Foamcrete”) to apply for financing from Maybank. PW1 then reminded DW3 that the agreed one year delay to commence construction was expiring soon and it was necessary to finalize the commencement date for construction. This was to primarily avoid costs escalation arising from further delay. [22] Both parties then agreed to meet on 11.8.2017 to discuss and finalize the commencement date for construction. At the meeting, both PW1 and Pangkat Beruntung’s representative, Mr Chua Teck Choon (PW2) and DW3 were present. Both PW1 and PW2 proposed to erect a fence surrounding the project site to facilitate further preliminaries works as all the requisite approvals had been obtained. The proposal was refused by DW3. S/N cjcUpVhlIkmEANBG0qLxng [23] Instead, a few days later, DW3 by his letter dated 15.8.2017, instructed the Plaintiff not to commence construction on PT 86 and PT 87 (Lot 2 and 1 respectively). These lots were provided as the Defendant’s entitlement under the 2nd JVA. [24] A week later, on 22.8.2017, DW3 attached Maybank’s letter to Foamcrete informing that it could not accept the Plaintiff as its appointed contractor to undertake the construction. PW1 expressed surprise at the information as it was never the contractor for the project. At all material times, it acted as the developer. It would then in turn appoint its own contractors. The Plaintiff had, by then, appointed United Asia Development Sdn Bhd for the preliminary and earth works and was in the process of appointing a contractor specifically for the construction of the factory buildings. PW1 then requested DW3 to clarify with Maybank as to its role. However, the latter flatly refused to do so. [25] By a letter dated 27.9.2017, the Defendant notified the Plaintiff that as it had yet to commence construction works, it offered to sell PT 84 and PT 85 to the Plaintiff for RM 1,400,000.00 subject to the fulfillment of certain conditions. Upon the acceptance of the Plaintiff to the offer, all prior agreements entered into shall be considered terminated. [26] Parties then instructed their respective solicitors to communicate further on the terms to be agreed upon. Unfortunately, the offer by Defendant for the Plaintiff to purchase PT 84 and PT 85 did not materialize as parties could not agree to the detailed terms and conditions. S/N cjcUpVhlIkmEANBG0qLxng [27] The delay in commencing construction meant that some of the prior approvals had to be renewed, leading to costs escalation. The Plaintiff regarded the series of conduct on the part of DW3 as evincing an intention not to proceed with the development of the said land as earlier agreed. [28] As the Plaintiff was left with no other option in the matter, it then instructed its solicitor to terminate the joint venture agreements. By its solicitor’s letter of 2.1.2018, the Defendant was informed that its acts in preventing the Plaintiff from commencing construction amounted to a serious breach of the agreements entered into. Consequent thereto, the Plaintiff exercised its rights of termination under the agreements. [29] The Plaintiff claims that Defendant’s intention in not wanting to proceed with the agreements entered into came to light subsequently when it discovered the Defendant to have engaged with a third party, one Tu Leong Chay (DW2) to develop the said land. [30] DW2 is known to PW1. In a chance meeting, DW2 enquired from PW1 regarding the caveat entered into by the Plaintiff as well as the lots which were the subject matter of the agreements. PW1 was surprised at the enquiries as DW2 was a stranger to the agreements. It then suspected the Defendant to have entered into discussions to develop the said land. [31] The Plaintiff’s position in this suit is that it had performed its obligations under the JVA, Supplementary JVA and 2nd JVA by S/N cjcUpVhlIkmEANBG0qLxng obtaining the requisite approvals, including carrying out preliminary works. It was at all material times, ready to commence construction. The Defendant was the party obstructing it from proceeding with the construction by refusing to finalise the Commencement Date for construction and instead attributing it to Maybank’s refusal to provide financing as it could not agree with the Plaintiff as the contractor for the project. Finally, the Defendant’s counterclaim that the Plaintiff was in breach because it failed to commence construction is unfounded and wholly without basis. [32] In the result, the Defendant’s breach had caused the Plaintiff to suffer various losses. It had incurred much expense in the preliminary works undertaken. Thereupon it claims the following reliefs in this action:-