Content
IN THE HIGH COURT OF MALAYA AT SHAH ALAM, SELANGOR DARUL EHSAN ORIGINATING SUMMONS NO: BA-24C-65-10/2022 BETWEEN TCS CONSTRUCTION SDN BHD (Company No.: 466772-H) AND KTCC MALL SDN BHD (Company No.: 964184-K) HEARD TOGETHER IN THE HIGH COURT OF MALAYA AT SHAH ALAM, SELANGOR DARUL EHSAN ORIGINATING SUMMONS NO: BA-24C-7-01/2023 BETWEEN KTCC MALL SDN BHD (Company No.: 964184-K) AND TCS CONSTRUCTION SDN BHD NT (Company No.: 466772-H) JUDGMENT A. INTRODUCTION [1] These are actions which had originated from an Adjudication Decision dated 13.9.2022 (AD) made by the appointed adjudicator, Ms. Karen Ng Gek Suan. The AD was in favour of the TCS Construction Sdn Bhd (TCS) being the sub-contractor against the main sub-contractor, MPM Project Management Sdn. Bhd. (MPM). Since MPM did not pay the adjudication amount to TCS in accordance to the AD, TCS made a written request to KTCC Mall Sdn Bhd (KTCC) on 21.9.2022 for the Adjudication Amount to be paid pursuant to Section 30 of Construction Industry Payment Adjudication Act 2012 (Section 30 CIPAA 2012). [2] As a consequence to the AD, both TCS and KTCC had filed their respective Originating Summons: i. TCS has filed OS no. BA-24C-65-10/2022 (Suit 65) against KTCC pursuant to Section 30 of CIPAA 2012 for direct payment of the Adjudication Sum as per the AD; and ii. KTCC on the other hand had filed OS no. BA-24C-7-01/2023 (Suit 7) against TCS for declarations that KTCC has no obligation to pay the Adjudicated Sum pursuant to Section 30 CIPAA 2012, based on a letter of undertaking dated 19.9.2018 and that the notice dated 21.9.2022 issued by TCS pursuant to Section 30 CIPAA is defective. [3] Both parties had filed their respective affidavits and submissions for both the OSs. By an Order dated 11.1.2023, Suit 7 was transferred from Kuala Terengganu to Shah Alam and has been ordered to be heard together with Suit 65 which had been filed by TCS at the Shah Alam High Court. Since the grounds for both applications overlap one another it was agreed for both the suits to be heard and decided together. In this respect, I decided on Suit 65 and then followed by Suit 7. B. BRIEF BACKGROUND [4] KTCC appointed MPM as the main contractor for the construction of a construction project known as Bercampur Di atas Lot Pt 4191, Kawasan KTCC, Muara Selatan Bandar Kuala Terengganu, Daerah Kuala Lumpur Yang Terdiri Daripada: 1 Blok Podium Pusat Membeli Belah Di Tingkat Basemen 1, 2, 3 & 4 Berserta Tempat Letak Kereta Do (the Project) for an original contract sum of RM101,000,000.00. [5] MPM had appointed TCS by way of a Letter of Acceptance dated 19.9.2018 as one of its subcontractors for superstructure works (from ground floor and above excluding prestressing work) and some architect works at the Project. [6] Due to non-payment of the outstanding sums for works done under the contract to TCS by MPM, TCS had commenced and succeeded at an Adjudication Proceeding where TCS was awarded via the AD among others a sum of RM6,141,557.77 and interests of 5% per annum calculated from RM6,141,557.77 to be calculated from the date due of payment of revised Progress Claim No. 17 i.e on 4.7.2020 until the date of full payment. [7] MPM has failed to comply with the AD and as such, TCS had exercised its right under CIPAA 2012 by making a written request to KTCC being the principal to MPM pursuant to Section 30(1) CIPAA 2012 in order to recover the adjudication sum as per the AD. [8] In the Section 30(1) notice, TCS also relied on a Letter of Undertaking dated 19.9.2018 issued by KTCC to TCS in relation to the Project (the said LU) which reads: bove-mentioned sub-contract works that were awarded by MPM, we KTCC Mall Sdn Bhd, the Owner of the above mentioned project, hereby undertake to settle on behalf of MPM th outstanding amount in the event MPM defaults in settling the outstanding amount sue to you in (sic) within 14 days from the date of receiving of your [9] KTCC had by way of a reply letter dated 5.10.2022 to the request letter made by TCS intimated that there are no monies due or payable to MPM as all payments have been made to MPM. KTCC had also served a written notice to MPM pursuant to Section 30(2) CIPAA 2012. [10] MPM was wound-up by the court on 28.2.2022 and as such, it is KTCC due to the winding-up of MPM, submitting to TCS claims will contravene the pari passu rule of the Insolvency Law. As such, any sum payable to TCS should be through the liquidator in accordance to the list of registered creditors of MPM. C. [11] pay the adjudication amount to TCS and as such, TCS exercised its concurrent right to make a written request to KTCC being the principal to MPM for a direct payment pursuant to Section 30 CIPAA 2012. [12] Although KTCC had declared that through this case that the Certificate for Practical Completion (CPC) for the Project had been Project was not issued. [13] This is because MPM had taken the position that TCS and 2 other M&E sub-contractors (Eakonmech and Andeli) have failed to complete their works and as such had failed and or refused to issue a CPC to TCS. MPM had also imposed LAD which had continued to run pass 23.1.2020 till to date. Therefore, the issuance of CPC declared by KTCC is very questionable. [14] According to KTCC all monies due to MPM under the contract between them has been paid and that MPM in fact owes KTCC a sum of RM7,950,000.00 being Liquidated Ascertained Damages (LAD). [15] According to TCS, ents, it seems like KTCC had paid to MPM amounts which included payments for works which were to be carried out by TCS but these payments were done prior to TCS doing the said works. Therefore, such statements and evidences by KTCC cannot be true. [16] Be that as it may, since i there is no issuance of the Certificate of Making Good Defects (CMGD) at the time the written request was made to KTCC by TCS, therefore, even if MPM has received full payment of the contract sum, there should at least be the balance of the Retention Sum and or the Performance Bond which are yet to be released to MPM. [17] The said Letter of Undertaking which was given by KTCC to TCS is unconditional. Therefore, KTCC cannot now place conditions to the said undertaking i.e that it is only obliged to pay undisputed sums under the contract. D. [18] KTCC s to TCS s pursuant to Section 30(1) CIPAA 2012 are on the following reasons: i. TCS did not allow for the lapse of the fourteen (14) days given for MPM to pay the Adjudication Amount in accordance to the AD before making its written request for direct payment from KTCC; ii. There are no monies due or payable by KTCC to MPM at the en request due to the following reasons: