Content
1 IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR IN THE FEDERAL TERRITORY, MALAYSIA SUIT NO. WA-22M-233-04/2019 BEFORE YA KHADIJAH BINTI IDRIS JUDGE BETWEEN KUWAIT FINANCE HOUSE (MALAYSIA) BERHAD … PLAINTIFF
22M-233-04/2019
High Court of Malaysia11 Oct 2019
The written judgment as the court issued it, with the coram, case number, and source links. Every paragraph has its own anchor.
Content
1 IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR IN THE FEDERAL TERRITORY, MALAYSIA SUIT NO. WA-22M-233-04/2019 BEFORE YA KHADIJAH BINTI IDRIS JUDGE BETWEEN KUWAIT FINANCE HOUSE (MALAYSIA) BERHAD … PLAINTIFF
1
WSJ INTERNATIONAL SDN. BHD. (formerly known as Wood Star Jaya Sdn. Bhd.)
2
2.
3
3.
4
4.
5
5.
6
6.
7
7.
8
SELVARAJAN A/L MARUTHAMUTHU ... DEFENDANTS 2 GROUNDS OF JUDGMENT (Enclosure 9) Introduction [1] Kuwait Finance House (Malaysia) Berhad (“Plaintiff”), a licensed Islamic financial institution, filed this civil action claiming from the defendants outstanding sums due under Islamic financing facilities granted by the Plaintiff to the first defendant, WSJ International Sdn Bhd (dahulunya dikenali sebagai Wood Star Jaya Sdn Bhd) (“1st Defendant”). The second to the eighth defendants has all agreed to guarantee the payment of the financing facilities. [2] Vide enclosure 9, the plaintiff applied for summary judgment to be entered against the first, second and the eighth defendants. On 11 October 2019, this court allowed summary judgment to be entered against the said defendants. [3] Vide Notice of Appeal dated 22 October 2019, the 1st Defendant and second defendant appealed against the order for summary judgment dated 11 October 2019. Vide Notice of Appeal dated 1 November 2019 the eighth defendant appealed against the same. 3 Factual Background [4]
Preamble
Pursuant to a letter of offer dated 13 February 2007 and a supplemental letter of offer dated 13 March 2007 (collectively “1st and 2nd Letters of Offer”) the Plaintiff granted to the 1st Defendant the following facilities –
a
a Forex Line Facility of RM 2,000,000.00;
b
a Murabahah Letter of Credit-i Facility of RM 10,000,000.00; and
c
a Murabahah Tawarruq Facility of RM 3,000,000.00. (the above facilities are collectively referred to as “Murabahah Facilities”) subject to the terms and conditions therein. [5]
Preamble
Pursuant to the 1st and 2nd Letters of Offer, the Plaintiff and the 1st Defendant entered into –
a
a Murabahah Letter of Credit Facility Agreement;
b
Murabahah Tawarruq Facility Agreement; and
c
Forex Line Agreement 4 which are all dated 18 May 2007. The above agreements are collectively referred to as “Murabahah Agreements”. [6] Vide Supplemental Letter of Offer dated 26 November 2007 (“3rd Letter of Offer”), the Plaintiff increased the limit of the Murabahah Facilities as follows –
a
the limit of the Murabahah Letter of Credit-i Facility was increased to RM 40,000,00.00;
b
the limit of the Murabahah Tawarruq Facility was increased to RM 9,000,000.00; and
c
the limit of the Forex Line Facility was increased to RM 5,000,000.00. [7] Pursuant thereto, the Plaintiff and the 1st Defendant entered into the following –
a
Supplemental
b
Supplemental Murabahah Tawarruq Facility Agreement; and
c
Supplemental Forex Line Agreement. 5 which are all dated 11 December 2017. The above agreements are collectively referred to as “Supplemental Murabahah Agreements”. [8] The Plaintiff also granted, via letter dated 24 March 2008 (“4th Letter of Offer”) to the 1st Defendant a KFH Wakalah Letter of Credit-i Facility of USD 10,000,000.00 and a KFH Murabahah Tawarruq Working Capital Financing-i Facility of USD 10,000,000.00 subject to the terms and conditions therein. Both the said facilities are collectively referred to as “Murabahah Tawarruq Facility”. [9]
Preamble
Pursuant to the 4th Letter of Offer, the Plaintiff and the 1st Defendant entered into –
a
KFH Wakalah Letter of Credit-i Facility Agreement; and
b
KFH Murabahah Tawarruq Working Capital Financing-i Facility Agreement both of which are dated 10 April 2008. The above agreements are collectively referred to as Murabahah Tawarruq Agreements. The 2nd Defendant had signed the Murabahah Tawarruq Agreements in her capacity as a director of the 1st Defendant. 6 [10] Subsequently pursuant to a letter of offer dated 18 December 2008 (“5th Letter of Offer”) the Plaintiff granted to the 1st Defendant 20 Ijarah Facilities up to the aggregate amount of RM 102,300,000.00, comprising inter alia the following –
a
KFH Ijarah Muntahiah Bitamlik Facility of RM 5,752,188.00 (“Ijarah 2 Facility”);
b
a KFH Ijarah Muntahiah Bitamlik Facility of RM 6,672,538.00 (“Ijarah 3 Facility”);
c
a KFH Ijarah Muntahiah Bitamlik Facility of RM 5,752,188.00 (“Ijarah 8 Facility”);
d
a KFH Ijarah Muntahiah Bitamlik Facility of RM 5,138,621.00 (“Ijarah 13 Facility”);
e
a KFH Ijarah Muntahiah Bitamlik Facility of RM 3,834,792.00 (“Ijarah 14 Facility”); and
f
a KFH Ijarah Muntahiah Bitamlik Facility of RM 3,834,792.00 (“Ijarah 18 Facility”), the above facilities are collectively known as “Ijarah Facilities”. [11] By the 5th Letter of Offer, the Plaintiff and the 1st Defendant entered into an Ijarah Asset Acquisition Financing-i Agreement for each 7 of the Ijarah Facilities, all of which are dated 26 March 2009 (collectively referred to as “Ijarah Agreements”). [12] By a Supplemental Letter of Offer dated 29 April 2014 (“6th Letter of Offer”) issued by the Plaintiff and duly accepted by the 1st Defendant, the Plaintiff further agreed to the 1st Defendant’s request to redeem 10 out of the 20 Ijarah Facilities subject to, inter alia, the execution and perfection of third party 2nd legal charges over 3 vessels to secure the indebtedness under the Murabahah Tawarruq Facility. [13] The 1st Letter of Offer, 2nd Letter of Offer, 3rd Letter of Offer, 4th Letter of Offer, 5th Letter of Offer, 6th Letter of Offer, Murabahah Agreements, Murabahah Tawarruq Agreements and Ijarah Agreements shall hereinafter be referred to collectively as the “Financing Agreements”. [14] The Murabahah Facilities, Murabahah Tawarruq Facility and Ijarah Facilities (collectively “Financing Facilities”) are secured, inter alia, by the second to the eighth defendants in the following manner – 8
a
a Guarantee and Indemnity Agreement dated 18 May 200 provided by Nor Raihan Binti Ahmad Kamarudin (“2nd Defendant”), 3rd and 4th Defendants;
b
a Second Guarantee and Indemnity Agreement dated 11 December 2007 provided by the 2nd Defendant, 3rd and 4th
c
a Third Joint and Several Guarantee dated 10 April 2008 provided by the 2nd Defendant, 3rd and 4th Defendants;
d
a Fourth Joint and Several Guarantee dated 26 March 2009 provided by the 2nd Defendant, 3rd and 4th Defendants. all the above guarantees are collectively referred to “Individual Guarantees”.
e
a Joint and Several Guarantee dated 26 March 2009 provided by the 5th, 6th, 7th Defendants and Selvarajan A/L Maruthamuthu (“8th Defendant’s Guarantee). 9 [15] By the above guarantees, the 2nd Defendants to the 8th Defendants jointly and severally guaranteed to the Plaintiff not merely as sureties but also as principal debtors, for the payment on demand of all monies due and owing by the 1st Defendant to the Plaintiff under the Financing Facilities upon the terms therein contained. [16] In breach of its obligations under the Financing Agreements the 1st Defendant had defaulted in the monthly instalment payments and lease rentals to the Plaintiff bank in respect of the Financing Facilities on the due dates despite reminders. Guaman No. WA-22M-36-03/2016 [17] Pursuant to the 1st Defendant’s breach, on 18 March 2016 the Plaintiff bank instituted a writ action Guaman No. WA-22M-36-03/2016 (“Suit 36”) against inter alia the 1st Defendant to 8th Defendant herein for the payment of the outstanding sums due under the Financing Facilities as at 30 November 2015. [18] By a settlement letter dated 17 May 2016 (“Settlement Letter May 2016”) and settlement letter dated 1 June 2016 (“Settlement Letter June 2016”), the Bank entered into a settlement arrangement with the 1st 10 Defendant (“Settlement Arrangement”) for the full and final settlement of the 1st Defendant’s indebtedness under the Financing Facilities and the 1st Defendant’s guarantors’ indebtedness under their respective guarantees subject to the terms and conditions set out in the Settlement Letter May 2016 and Settlement Letter June 2016 (both are collectively referred to as “Settlement Letters”). [19] Pursuant to the terms of the Settlement Arrangement, it was agreed that the 1st Defendant pay to the Plaintiff bank, inter alia, as follows –
a
the sum of RM 28,000,000.00 (“Settlement Sum”) in 3 tranches, as follows: -
i
the first tranche of RM 16,000,000.00 shall be paid into an account nominated by the Bank (“said Account”) within 21 days from the date of the 1st Defendant’s acceptance of the Settlement Arrangement;
II
(ii) the second tranche of RM 2,000,000.00 shall be paid into the said Account within 60 days from the date of 1st Defendant’s acceptance of the Settlement Arrangement; and 11
III
(iii) the third tranche of RM 10,000,000.00 shall be paid into the said Account from the proceeds of sale of Frenz Hotel owned by one Wood Star Hotel Sdn. Bhd. not later than six (6) months from the date of issuance of the Bank’s undertaking to withdraw its caveat over the said property.
b
in the event of any default of the terms / payments as set out in the Settlement Letters, the Bank reserves the right to treat the Settlement Arrangement as terminated and of no effect, and the Bank shall be at liberty to exercise all of its rights and remedies including its right to continue with legal proceedings against the 1st Defendant and its guarantors to recover in full, the outstanding sums under the Financing Facilities and the said guarantees less such amounts as may have been received prior to the termination of the Settlement
c
time wherever mentioned in the Settlement Letters is of the essence; and 12
d
nothing contained in the Settlement Letters shall be construed as a waiver and / or forbearance on the part of the Bank to exercise any of its rights or remedies vis-a-vis any breach or default by the 1st Defendant and its guarantors, and nothing in the Settlement Letters shall be deemed as releasing or discharging the 1st Defendant and its guarantors’ respective obligations, liabilities and indebtedness to the Bank. [20] Suit 36 was withdrawn with liberty to file afresh and with no order as to costs on 18 July 2016. [21] In breach of the 1st Defendant’s obligations under the Settlement Arrangement, the 1st Defendant had defaulted in making payment of the remaining balance of the Settlement Sum amounting to RM 824,815.21 (“Balance Settlement Sum”). [22] Pursuant to the 1st Defendant’s default –
a
vide letter dated 20 December 2012 to the 1st Defendant, the Plaintiff terminated the Settlement Arrangement and 13 demanded for payment of the total outstanding sums under the Financing Facilities as at 26 November 2018; and
b
vide letter dated 8 January 2019 to the 1st Defendant to the 8th Defendants, the Plaintiff demanded for payment of the total outstanding sums under the Financing Facilities as at 26 November 2018 Contentions of the 1st Defendant and 2nd Defendant [23] The grounds forwarded by the 1st Defendant and 2nd Defendant to resist the summary judgment application may be summarized as follows –
a
the Financing Facilities have been terminated and replaced by the Settlement Arrangement. Under the Settlement Arrangement the 1st Defendant still has time to pay the Balance Settlement Sum given that time is no longer of the essence; 14
b
the former officer of the Bank had represented to D1 that its indebtedness to the Bank under the Financing Facilities would be settled upon payment of the Settlement Sum;
c
the Bank’s termination of the Murabahah Facilities is premature because the tenure of the same is until 30 June 2016;
d
the 1st Defendant did not receive the Plaintiff’s demands;
e
as the Bank did not revive the transactions under the Financing Facilities, the Bank is not entitled to further compensation fee from 26 March 2019 onwards;
f
the Bank’s claim is for interest which is forbidden in Islamic banking and the Plaintiff has failed to grant to the 1st Defendant ibra under the Ijarah facilities; and
g
the Bank has overclaimed by RM 10,864,028.64 as the Bank should have been paid USD 4,040,040.04 by Agritrade International Pte. Ltd. instead of RM 16,000,000.00. 15 8th Defendant’s contentions [24] The 8th Defendant basically denies the claim made by the Plaintiff against him. Further arguments may be summarized as follows –
a
the 8th Defendant’s obligation and liability under the 8th Defendant’s Guarantee has been released upon payment made to the Plaintiff of the sum RM 10,000,000.00 from the proceeds of the sale of Frenz Hotel;
b
the Corporate Guarantee provided by Agritrade International Pte Ltd and the 8th Defendant’s Guarantee is for the purpose of securing the 1st Defendant’s indebtedness under the Ijarah Facilities. Since Agritrade International is not named as a party in this instant action, the 8th Defendant ought not to have been named a party;
c
the Plaintiff is estopped from claiming the full outstanding indebtedness under the Financing Facilities as the Settlement Arrangement entered between the Plaintiff and the 1st Defendant had superseded all prior arrangements and the default (if any) by the 1st Defendant at the material time; 16
d
the Plaintiff’s termination of the Settlement Arrangement on 20 December 2018 is unlawful, unreasonable and / or invalid as there has been substantial performance by the 1st
e
any default on the part of the 1st Defendant under the Settlement Arrangement to pay RM 824,815.21 was caused by the Plaintiff’s negligence. The alleged negligence is particularised at paragraph 25 (a) of the 8th Defendant’s Statement of Defence and of significance is the Plaintiff’s release of the charge over the Perak Land without first ensuring that the 1st Defendant has paid all the settlement sum of RM 2 million to the Plaintiff;
f
the 8th Defendant’s obligation and liability under the 8th Defendant’s Guarantee is limited to the Ijarah facilities and does not include the Murabahah and Murabahah Tawarruq
g
the balance under the Settlement Arrangement is RM 767,687.60 and not RM 824,815.21; and 17
h
whether the Bank may file this action when the Bank did not pray for liberty to file afresh under Suit 36. The law [25] Pursuant to Order 14 rules 1 and 2 of the Rules of Court 2012 (“RoC 2012”), in an application for summary judgment, it is incumbent on an applicant seeking the same to prove the following –
a
the statement of claim has been served on the defendant;
b
the defendant has entered appearance; and
c
the applicant has affirmed an affidavit verifying the facts on which the statement of claim is based. The applicant is also required to affirm his belief that the defendant has no defence to the statement of claim. [26] Upon the fulfilment of the above preliminary requirements the burden is on the defendant to prove under Order 14 rules 3 and 4 of the RoC 2012 that there is an issue or question in dispute which ought to be tried (National Company For Foreign Trade v. Kayu Raya Sdn Bhd [1984] 1 CLJ (Rep) 283, [1984] 2 MLJ 300; Cempaka Finance Bhd v. Ho Lai Ying & Anor [2006] 3 CLJ 544, [2006] 2 MLJ 685). An application for 18 summary judgement may also be dismissed by the court if the defendant satisfies the court that there ought for some other reason to be a trial namely there are circumstances that ought to be investigated by the court (United Merchant Finance Bhd v. Majlis Agama Islam Negeri Johor [1999] 2 CLJ 151, [1999] 1 MLJ 657). [27] As what amount to triable issue, the Supreme Court in Bank Negara Malaysia v Mohd Ismail & Ors [1992] 1 MLJ 400; [1992] 2 CLJ Rep 186; [1992] 1 CLJ 653 held – In our view, basic to the application of all those legal propositions, is the requirement under O 14 for the court to be satisfied on affidavit evidence that the defence has not only raised an issue but also that the said issue is triable. The determination of whether an issue is or is not triable must necessarily depend on the facts or the law arising from each case as disclosed in the affidavit evidence before the court… Under an O 14 application, the duty of a judge does not end as soon as a fact is asserted by one party, and denied or disputed by the other in an affidavit. Where such assertion, denial or dispute is equivocal, or lacking in precision or is inconsistent with undisputed contemporary documents or other statements by the same deponent, or is inherently improbable in itself, then the judge has a duty to reject such assertion or denial, thereby rendering the issue not triable. In our opinion, unless this principle is adhered to, a judge is in no position to exercise his discretion judicially in an O 14 application. Thus, apart from identifying the issues of fact or law, the court must go one step further and determine whether they are triable. This principle is sometimes expressed by the statement 19 that a complete defence need not be shown. The defence set up need only show that there is a triable issue. Findings of the court Preliminary requirements [28] There is no dispute that the Plaintiff’s Statement of Claim was served on the 1st Defendant, 2nd Defendant and 8th Defendant. The 1st Defendant and 2nd Defendant had entered their appearances vide Memorandum of Appearance at enclosures 7 and 4 respectively. While the 8th Defendant’s Memorandum of Appearance is at enclosure 5. [29] The Plaintiff has set out in their affidavit in support (enclosure 12) of the summary judgment application adequate facts including the salient terms upon which the Financing Facilities was granted and the relevant contemporaneous documents in relation to the Financing Facilities in particular the Murabahah Facilities, Murabahah Tawarruq Facilities, Ijarah Facilities and the Financing Agreements. With regards to the securities for the Financing Facilities, the 1st Defendant and 2nd Defendant vide the Individual Guarantees and 8th Defendant vide the 8th Defendant’s Guarantee has agreed to jointly and severally guaranteed to the Plaintiff not merely as sureties but also as principal debtors the 20 payment on demand of all monies due and owing by the 1st Defendant to the Plaintiff under the Financing Facilities. [30] The Plaintiff has also deposed that the 1st Defendant, 2nd Defendant and 8th Defendant are justly and truly indebted to the Plaintiff the sums claim as particularised in paragraph 5 of the Plaintiff’s affidavit enclosure 12 and that the said sums is still due and owing. It is further averred by the Plaintiff the 1st Defendant, 2nd Defendant and 8th Defendant has no defence to their claim. [31] Base on the aforesaid, this court finds the Plaintiff has fulfilled the preliminary requirements. Thus the Plaintiff has established a prima facie case in respect of its claim against the 1st Defendant, 2nd Defendant and 8th Defendant. [32] The burden therefore shifts on the said Defendants to prove that there are issue or question in dispute which ought to be tried or there ought for some other reason to be a trial, namely, there are circumstances that ought to be investigated by the court. 21 Purported triable issues raised by the 1st Defendant, 2nd Defendant and 8th Defendant (hereinafter collectively referred to as “the Defendants’) Settlement Arrangement [33] It is a common defence of the Defendants that the Plaintiff is estop from claiming under the Financing Facilities as the said facilities has been terminated and replaced by the Settlement Arrangement. It is further contended by the Defendants that the Plaintiff therefore can only claim the balance outstanding under the Settlement Arrangement and not the outstanding sum under the Financing Facilities. [34] It is not disputed that the Settlement Arrangement was agreed between the Plaintiff and the 1st Defendant as evident from the Settlement Letters. Vide paragraph 2 of Settlement Letter June 2016 it was agreed that the settlement sum of RM 28 million was to be paid in 3 tranches and at the time stated therein. [35] Importantly, the 1st Defendant in its affidavit enclosure 34 did not dispute the Settlement Arrangement. The 1st Defendant also did not dispute that the manner of payment is as agreed in Settlement Letter June 2016 and they have defaulted in complying with the payment 22 arrangement. Thus the 1st Defendant is bound by the terms of the Settlement Letters. [36] Paragraph 2 (h) of the Settlement Letter May 2016 (which is to be read with paragraph 4 of Settlement Letter June 2016) states as follows – h. in the event of any default of the terms / payments as set out in the Settlement Letters, the Bank reserves the right to treat the Settlement Arrangement as terminated and of no effect, and the Bank shall be at liberty to exercise all of its rights and remedies including its right to continue with legal proceedings against you [1st Defendant] and Individual Guarantors …. to recover in full, your outstanding indebtedness under your financing facilities with the bank and the outstanding indebtedness of the abovenamed 2nd to 9th Defendants [in Suit 36] under their respective guarantees (less such amounts as may have been received and retained by the bank pursuant to the settlement arrangement herein prior to the termination of the same) without any further reference to you. [37] In view of the above express provision, the Defendants’ contentions that the Settlement Arrangement has replaced the Financing Facilities and / or the Financing Agreements is untenable. This is especially so when the 1st Defendant has defaulted in complying with the terms of payment. Since there is no allegation of fraud in the execution of the Settlement Letters, the Defendants are therefore bound by the above provision. As there is a default in payment by the 1st Defendant, 23 the Plaintiff has the right to terminate the Settlement Arrangement (which they had done so vide letter dated 20 December 2018 at Exhibit KFH-10 of enclosure 12) and whether the 1st Defendant has substantially performed the Settlement Arrangement is irrelevant. Thus termination of the Settlement Arrangement is lawful and the Plaintiff is entitle to enforce the Financing Agreements in respect of the Financing Facilities. [38] Thus the contentions by the Defendants that they were not notified by the Plaintiff of the Plaintiff’s intention to claim the full outstanding sums under the Financing Facilities and as stated in the Plaintiff’s Statement of Claim is a non-issue. It follows the contentions that the Plaintiff is only entitle to claim the balance settlement sum under the Settlement Arrangement and not the 1st Defendant’s indebtedness under the Financing Facilities is flawed. [39] Due to the termination of the Settlement Arrangement the 1st Defendant’s contentions that they still have time to pay the balance settlement sum of RM 767,687.60 is unfounded. [40] As stated above, the 1st Defendant did not dispute that the terms of the Settlement Arrangement in respect of payment of the Settlement 24 Sum (RM 28 million) was not paid in full. Hence the 1st Defendant cannot rely on the purported representation by the Plaintiff’s officer that the 1st Defendant’s indebtedness under the Financing Facilities would be settled upon payment of the Settlement Sum. As the Settlement Arrangement had been terminated due to default by the 1st Defendant, the 1st Defendant’s indebtedness and that of the 2nd Defendant and 8th Defendant in relation to the Financing Facilities remain unextinguished. In any event it is not the pleaded case of the Defendants that the Settlement Arrangement was concluded premised on the Plaintiff’s misrepresentation as there were no specific particulars of such misrepresentation set out in their pleadings. Financing Facilities / Financing Agreements [41] It is argued by the 2nd Defendant that she did not receive the Plaintiff’s demand in respect of the Financing Facilities. The Plaintiff’s demand were sent via letter dated 8 January 2019 to the 2nd Defendant (Exhibit KFH-11 page 1864 of enclosure 12). As can be seen from the proof of posting, the letters were sent by ordinary post and not registered post. 25 [42] The 2nd Defendant relies on clause 4 of the Individual Guarantees which provides any notice of demand under the guarantee shall be in writing and shall be sufficiently served to the Guarantors if sent by telegram, telex or registered post. If effected by registered post the notice shall be deemed to have been duly served in 3 days of posting.
Preamble
Whereas the Plaintiff relies on clause 22 of the Individual Guarantees which provides the service of any notice and legal process may be given by prepaid registered or ordinary post to 2nd Defendant to her address stated in the said guarantees, and such notice and legal process shall be deemed to have been duly served after the expiration of 3 days from the date it is posted. [43] Since clause 4 is a specific provision in respect of service of notice of demand, clause 4 would prevails over clause 22. Accordingly the notice of demand which was sent to the 2nd Defendant via ordinary post is defective. However it is noted that the notice of demand was also sent to the 2nd Defendant’s solicitor who is the same solicitor defending the 2nd Defendant in this instant action. Although clause 4 do not provide for service to be effected on the 2nd Defendant’s solicitor, authorities has decided that the knowledge of a solicitor is regarded by law as knowledge of the client (T. Sivam Tharamalingam v. Public Bank Bhd [2018] 6 CLJ 1). There is no evidence to show that 2nd Defendant’s 26 solicitor did not receive the said letter of demand or has no knowledge of the same. Therefore it is safe to conclude that the 2nd Defendant has knowledge of the letter of demand. Furthermore, the 2nd Defendant who at all material time is a director of the 1st Defendant who accepted the terms of the Settlement Arrangement on behalf of the 1st Defendant cannot now deny knowledge of the demand made in the said letter. [44] It is also argued by the 2nd Defendant and the 8th Defendant that their liability as guarantor under the Individual Guarantee and the 8th Defendant’s Guarantee respectively is extinguished upon the Plaintiff’s receipt of RM 10 million being payment of the second tranche. This is because paragraph 2 (g) (ii) of the Settlement Letter May 2016 provides the Plaintiff will release the guarantors from all their obligations and liabilities under their respective guarantees upon the Plaintiff’s receipt of the payment of the second tranche. The Plaintiff did not deny having received the said payment. [45] On this issue reference is made to Woolley Development Sdn Bhd v. Tiara Contours Construction Sdn Bhd [2016] 2 CLJ 610 where the Court of Appeal referred to the case Bacom Enterprises Sdn Bhd v. Jong Chuk & Ors [2011] 1 LNS 440; [2011] 5 MLJ 820 which dealt with doctrine of privity of contract and held a person who is not a party to a 27 contract cannot enforce or rely for protection on its provision even if some provision therein was intended to benefit him. The court in Woolley Development said – Two aspects of the Doctrine The doctrine has two aspects. The first aspect is that no one but the parties to the contract is entitled under it. Contracting parties may confer rights and benefits upon a third party in the form of promise to pay, or to perform a service, or a promise not to sue (at all or in circumstances covered by an exclusion or limitation clause). But the third party on whom such right or benefit is conferred by contract can neither sue under it nor can rely on defences based on the contract. The second aspect of the doctrine is that parties to a contract cannot impose liabilities on a third party. A person cannot be subject to the burden of a contract to which he is not a party. It is the counterpart of the proposition that a third party cannot acquire rights under a contract. (emphasis added) [46] Thus the 2nd Defendant and 8th Defendant who are not party to the Settlement Arrangement cannot rely on the Settlement Agreement as their defence against the Plaintiff’s claim. The 2nd Defendant and 8th Defendant are both stranger to the Settlement Arrangement and therefore cannot derive rights under the same for the purpose of avoiding their liability under the Individual Guarantees (Phua Siong Hoe 28 v. RHB Bank Bhd & Anor; Persatuan Pemilik Tanah Taman Pandan (Intervenor) [2001] 6 CLJ 326). [47] It is argued by the 1st Defendant and 2nd Defendant that the Plaintiff has imposed riba which is prohibited under Shariah principles. The purported riba comes in the form of excess amount of lease rental claimed by the Plaintiff under Ijarah in the sum of RM 370,879.78. Such excess lease rental is derived from the difference between the sum claimed by the Plaintiff in 2015 being RM 3,707,826.34 (see letter of demand dated 10 December 2015 to the 1st Defendant at Exhibit KFH-7 and letter of demand dated 4 January 2016 to the 2nd Defendant at Exhibit KFH-8 of enclosure 12) and the sum RM 4,078,706.12 being the indebtedness as at 25 March 2019 as stated in the Plaintiff’s Certificate of Indebtedness (Exhibit KFH-12 of enclosure 12) as well as in the Statement of Claim. [48] However the 1st Defendant and 2nd Defendant overlooked the notification made in both the letters of demand that a compensation fee (al-ta’widh) shall be payable on the outstanding lease rental at the Plaintiff’s prevailing Islamic Money Market Rate from 1 December 2015 until date of full settlement. Thus eventhough the Ijarah Facilities has 29 been cancelled, as long as the outstanding lease rental has not been paid, compensation fee is chargeable. [49] Reference is made to the contractual provisions on compensation fee (at-ta’widh) stipulated in clause 5.6 of the Ijarah Agreements (Exhibit KFH-3 of enclosure 12) where it was agreed by the Plaintiff and 1st Defendant that the Plaintiff shall have the right to be compensated on failure to pay any instalments which continue beyond the maturity date of the Ijarah Facility at the compensation rate of the Plaintiff’s current Islamic Money Market rate on the balance of the lease rental. [50] Imposition of ta’widh is permissible under Shariah principles as a deterrent mechanism against customer who defaulted in discharging their financial obligations under Islamic financing contracts (Bank Islam Malaysia Berhad v. Helcom Engineering Corporation Sdn. Bhd. [2011] 1 LNS 1862; CIMB Islamic Bank Bhd. v. LCL Corporation Bhd & Anor CIMB Islamic Bank Bhd. v. LCL Corporation Bhd & Anor [2011] 7 CLJ 594). [51] With regards to the complaint that the Plaintiff failed to grant ibra, reliance was placed on clause 16, Schedule 1 of the Plaintiff’s Supplementary Letter of Offer dated 29 May 2015. Based on the said 30 clause, ibra is granted where the customer (1st Defendant) request for full settlement of the facility before the end of the Murabahah Period by serving an irrevocable written notice to the Plaintiff 30 days before the proposed settlement date. In this instant case it is not disputed that the 1st Defendant has defaulted under the Settlement Arrangement when they failed to pay the balance settlement sum. Thus the issue of the 1st Defendant not granted ibra does not arise at all. [52] With regards to the contention that the Plaintiff has overclaimed by RM 10,864,028.64 because the 1st Tranche payment under the Settlement Arrangement should have been paid USD 4,040,040.04 instead of RM 16 million, it is to be noted that it was agreed between the Plaintiff and 1st Defendant that the payment of the 2nd Tranche (RM 16 million) shall be made in RM 10 million and not USD 4,040,040.04. As such the issue of Plaintiff overclaiming is devoid of merits. [53] With regards to the sum claim by the Plaintiff, the Plaintiff produced a statement of account for the period 1 December 2015 until 25 March 2019 as Exhibit KFH-16 of enclosure 37 and the Statement of Indebtedness as Exhibit KFH-12 of enclosure 37. Having considered the issues raised by the 1st Defendant and 2nd Defendant on the sum claim by the Plaintiff and the explanation thereto, this court is of the view 31 the issues raised do not show manifest error on the statement of account and the Statement of Indebtedness. Pursuant to clause 30 of the Murabahah Tawarruq Agreement, clause 23.1.14 of the Ijarah Agreements and clause 2 (n) of the Individual Guarantees the amount stated in the Statement of Indebtedness shall be the amount due and owing by the 1st Defendant under the Financing Facilities and 2nd Defendant under the Individual Guarantees. [54] The 8th Defendant argued that the Plaintiff does not have the liberty to file this instant action as the Suit 36 was withdrawn with no liberty to file afresh. However the 8th Defendant did not provide any evidence to support his contentions. As the burden is on the 8th Defendant to do so, nothing turn on this issue. [55] With regards to the 8th Defendant’s argument that the scope of his liability under the 8th Defendant’s Guarantee is only in relation to the Ijarah Facilities and does not cover the Murabahah Facilities and Murabahah Tawarruq Facilities, reference is made to the said guarantee dated 26 March 2009. Pursuant to the terms of the same, the 8th Defendant has agreed to unconditionally and irrevocably guaranteed as principal debtor and not merely as surety the indebtedness of the 1st Defendant under the Ijarah Facilities and the indebtedness of the 1st 32 Defendant which includes all other monies, liabilities and obligations under the Security Documents or such amount thereof or as may be outstanding whether certain or contingent now or thereafter owing as incurred to the Plaintiff from or by the 1st Defendant. [56] Pursuant to the terms of the 8th Defendant’s Guarantee, the 8th Defendant’s liability therein shall subsist whether or not, inter alia, the Plaintiff has a claim against the 1st Defendant or any surety or against any security the Plaintiff may have from or against the 1st Defendant and whether or not the Plaintiff has avail itself of its legal remedies against the 1st Defendant, any surety or any security (clause 2 (e) of the 8th Defendant’s Guarantee). The 8th Defendant has also agreed that the Plaintiff’s right under the said guarantee is in addition to and not in substitution for any other guarantee or security held by the Plaintiff (clause 2 (i) of the 8th Defendant’s Guarantee). Also, under clause 2 (j) of the 8th Defendant’s Guarantee, the Plaintiff is at liberty but not bound to resort to any other means of payment and in any order as the Plaintiff thinks fit without diminishing the liability of the 8th Defendant as a guarantor. Thus the 8th Defendant’s complaint that the Plaintiff failed to realized the security held by the Plaintiff and that the Plaintiff has failed to mitigate its losses is not an issue as the Plaintiff is entitled to pursue 33 this instant action without first realizing the other security (Bank Bumiputera Malaysia Bhd v. Esah Binti Abdul Ghani [1986] 1 MLJ 16). [57] The 8th Defendant’s argument that the Plaintiff was negligent in, inter alia, ensuring that the terms of Settlement Arrangement was fully complied with within the time stipulated therein and the Plaintiff’s failure to realize the securities, this court is of the view such contentions is unfounded and misconceived. Under clause 15.7 of the Murabahah Tawaruq Agreement and clause 4.7 of the Ijarah Facilities, the Plaintiff has the right to exercise all any of the right or remedies whether available under the respective agreements or any other security provided for the Financing Facilities. Furthermore as the relationship between the Plaintiff and the 1st Defendant and the 8th Defendant is premised on a commercial transactions as evident in the Financing Facilities and the 8th Defendant’s Guarantee, the Plaintiff do not owe the 8th Defendant fiduciary duty or duty of care (Hong Leong Bank Bhd v WT Industries Sdn Bhd & Ors (2005) 8 CLJ 239). Conclusion [58] Premised on the aforesaid reasons, this court allowed the Plaintiff’s application for summary judgment and order in terms of 34 enclosure 9 was accordingly granted against the 1st Defendant, 2nd Defendant and 8th Defendant. ( KHADIJAH BINTI IDRIS ) JUDGE HIGH COURT (COMMERCIAL DIVISION) DATED 28 DECEMBER 2019 Counsel: Plaintiff : Tan Gian Chung and together with Caleb Sio Yeang Der of Messrs Shook Lin & Bok Defendants : Aundre Kok Onn of Messrs Onn & Partners (for the 1st and 2nd Defendants) : Sugandra Rao of Messrs Rao & Co. (for the 8th Defendant)
Wrong text, a broken link, out-of-date content, or a removal request — tell us and we'll check it against the official source.