86.2 Cross-examination of DW-1: OK And then further to that your second claim is RM672,306. This is for the period between 01/04/2019 to 31/06/2019. The can be captured in paragraph 83, betul? ZAS Yes. OK OK. And this is according to you is as a result of a delay and agreement by, and the agreement between the parties captured in Supplementary Agreement No 4 dated 05/09/2019, betul? ZAS Yes. [53] We have perused the LHJ's grounds of judgment on this issue. It is clear that the LHJ failed to take into account that the period claimed under LAD Claim 3 being identical to the period for LAD Claim 2; a fact admitted by the Respondent's own witness, who confirmed that LAD Claim 2 covered the period from 1 April 2019 to 31 August 2019. By allowing LAD Claim 3 for the same period, we are of the view that the LHJ fell into error by permitting double recovery. [54] On the question of waiver in respect of LAD Claim 1, we have considered the LHJ's findings on this issue and do not find them to be plainly wrong. The LHJ arrived at his decision by taking into account the plain and obvious language of the letter dated 26 November 2018, which stipulates that SSM is entitled to impose LAD from the 3rd Extended Completion Date (i.e. from 1 April 2019 onwards) if the project is not completed by 31 March 2019. [55] We also address the Appellant's contention that the Respondent contributed to the delays, which was framed around five broad instances. We are mindful of the LHJ's findings of fact at paragraph 169 of the grounds of judgment. We agree that the burden was on the Appellant to prove that the Respondent caused or contributed to the delay, and as that burden was not discharged, it was not plainly wrong for the LHJ to arrive at his findings of fact on this point. [56] Based on the above, the Appellant succeeds in part on this issue. LAD Claim 3 in the sum of RM499,368.99 should not have been awarded by the High Court. [57] The awards of LAD Claim 1 in the sum of RM797,238.21 and LAD Claim 2 in the sum of RM670,205.74 are upheld. The total LAD award is accordingly reduced from RM1,966,812.94 to RM1,467,443.95. The Concurrent Recovery of Refund and LAD [58] We have considered the submissions of the parties on this point. [59] Based on our finding that the Respondent is not entitled to the refund as it did not elect Option 1 within the requisite period after issuing the Notice of Termination, we find that the LHJ was plainly wrong in allowing the Respondent to recover the refund. The Entitlement to Payment for Work Done [60] As regards the fifth ground of appeal, the Appellant contends that it is entitled to payment for three categories of work done: (A) IRSMI in the sum of RM507,680.00; (B) eBSK Solution Configuration in the sum of RM204,750.00; and (C) Pre-UAT in the sum of RM1,527,000.00. [61] The Respondent submits that the ERP Agreement is a fixed price, milestone-based contract and refers to Clause 14.2(a), which provides that the Respondent shall pay the Appellant in milestone payments in accordance with Schedule E. [62] It was submitted that the Appellant was only entitled to payment upon completing each corresponding milestone. [63] We have considered the LHJ's grounds of judgment from paragraphs 173 to 200, where his Lordship dealt with this issue at length. Based on the evidence, his Lordship was entitled to find that the Appellant was not entitled to these payments. Further, since we have concluded that the Respondent was entitled to terminate the ERP Agreement, the Appellant's claims that it had completed the Infrastructure Readiness and Standard Module Installation, eBSK Solution Configuration, and portions of the pre-UAT tasks signed off by the Respondent are rendered immaterial. [64] In the circumstances, we do not find any merit in the fifth ground of appeal. The Claim for Oracle Licence Fees [65] As regards the sixth ground of appeal, the Appellant claims RM17,633,549.19 for Oracle licence fees incurred in subscribing to Oracle software, relying on Clause 8.8 of the ERP Agreement (read together with Schedule G), under which the Appellant was to acquire and subscribe to the selected third-party software, namely the Oracle Software. [66] The Respondent submits that there was no obligation, express or otherwise, in the ERP Agreement obliging the Appellant to acquire the Oracle software licence fees on SSM's behalf. It was further submitted that the Appellant had incurred these fees on its own volition and the Respondent cannot be made liable for this alleged expenditure. Insofar as SSM's payment obligations are concerned, SSM is only required to make payment in accordance with Schedule E to the ERP Agreement. [67] The Respondent further submits that Clause 13.2.7 expressly provides that the Appellant shall bear all costs relating to third-party software licences, and Clause 14.2(a) provides that the Respondent shall pay the Appellant in milestone payments in accordance with Schedule E, which payments represent the total contract price. [68] The LHJ considered this issue and reached the following conclusions: [136] Clause 8.1 of the ERP Agreement sets out the Scope of Services to be provided by Liberty to SSM. This includes '...(d) to supply, deliver, install, commission of software for implementation of the SSM's Enterprise Resource Planning as specified in the Bill of Material including but not limited to Oracle Cloud Services'. [137] In consideration of Liberty performing its obligations under the ERP Agreement, SSM shall pay a total sum of RM29,800,000.00 to Liberty. This sum was subsequently increased to RM35,530,152.00. The payment was to be made in accordance with Schedule E of the ERP Agreement. This is stated in Clause 14.2 of the ERP Agreement. [138] In respect of the rights to software and the payment for the same, Clause 13 of the ERP Agreement stipulates thus: