That lateness in the application to amend the pleadings cannot necessarily be compensated by payment of costs. [13] It is established, therefore, that the Federal Court in Hong Leong Finance Berhad v Low Thiam Hoe & Another Appeal had displaced the principles enunciated in Yamaha Motor Co Ltd v Yamaha (M) Sdn Bhd on amendment of pleadings, if such application is made at a later stage of proceedings, making it imperative that the application to amend 28 December 2020 ----------------------------------------------------------------------------------------------------------------------------------------------------- ------------------------------------------------------------------------------------------------------------------- 6 must be made at an early stage of the proceedings; and where the application is made at a later stage, there must be cogent and reasonable explanation for the delay. Contentions, evaluation, and findings Whether the proposed amendments would change the substance and character of the original defence [14] The Defendant’s initial defences were that the certificate of extension of time issued by the engineer was absolute, and that the late delivery was due to delay categorised under force majeure which was beyond the control of the Defendant. These were the same defences raised at the Earlier Suit, hence the stay of the proceedings in this claim, since the decision of the Court of Appeal would have had a bearing on the defences raised in this claim. However, after the Court of Appeal had dismissed the Defendant’s appeal in the Earlier Suit, the application to amend was filed, and the Defendant had raised the following defences: a) That the Plaintiff had no locus standi to commence and maintain the suit; b) That the Plaintiff had failed to pay the quit rent and assessment, maintenance charges, and the deposit for water supply; c) That the Plaintiff’s claim is subject to section 75 of the Contracts Act 1950. 28 December 2020 ----------------------------------------------------------------------------------------------------------------------------------------------------- ------------------------------------------------------------------------------------------------------------------- 7 [15] The learned SCJ took the view that the proposed amendments would change the character and substance of the original Defence. In my view, she was correct in her finding as the defences in the proposed amendments were not pleaded in the original Defence. [16] What is also pertinent to note that the matters raised in the proposed Defence were already available when the original Defence dated 19 December 2017 was filed. Whether the delay was satisfactorily explained [17] The application to amend was filed on 27 September 2019, which was 21 months after the original Defence was filed. From the records and minutes of the court proceedings, this was after 14 case managements held from 5 December 2017 until 11 September 2019. The reason given was that the Defendant had changed solicitors. [18] A perusal of the grounds of judgment indicated that the learned SCJ had taken this into consideration but found it unacceptable as the change of solicitors was done only after the decision of the Court of Appeal in the earlier suit which was unfavourable to the Defendant. I agreed with the learned SCJ, that a change of solicitors cannot be an excuse for delay in filing an application, lest it be a tactic for indolent litigants to justify delay on their part. 28 December 2020 ----------------------------------------------------------------------------------------------------------------------------------------------------- ------------------------------------------------------------------------------------------------------------------- 8 [19] I am mindful that in Order 20 rule 1 of the Rules of Court, it is stated that the ‘Court may at any stage of the proceedings allow the plaintiff to amend his writ, or any party to amend his pleading’, and as such, the Defendant, in relying on the cases of Bumiputra-Commerce Bank Bhd & Ors v Bumi Warna Indah Sdn Bhd [2004] 4 CLJ 825, Abdul Johari bin Abdul Rahman v Lim How Chong & Ors [1997] 1 MLJ 629, Dato’ Tan Heng Chew v Tan Kim Hor and another appeal [2009] 5 MLJ 790, HSB Bank Malaysia Bhd v Macquarie Technologies (M) Sdn Bhd [2004] 4 MLJ 398, Mahan Singh v Government of Malaya [1973] 2 MLJ 14, and Hong Leong Finance Bhd v Low Thiam Hoe and another appeal [2016] 1 MLJ 301, contended that there was no delay to begin with, and that even if there was, that factor alone should have not been a ground for the learned SCJ to dismiss the application to amend. [20] I am unable to agree with the contention of the Defendant, bearing in mind that first and foremost, delay must be looked at contextually and not in isolation. The Defendant argued that the issue of delay did not even arise since the trial dates were not scheduled. However, it must be borne in mind that the application to amend was made only after the Plaintiff had filed its application for summary judgment. [21] It is also pertinent to note that in the cases that the Defendant had relied on, it was stated that delay alone is not a ground to refuse an application for leave to amend, provided no injustice or prejudice is suffered by the opposing party, and that the proposed amendments should not change the nature and character of the defence. 28 December 2020 ----------------------------------------------------------------------------------------------------------------------------------------------------- ------------------------------------------------------------------------------------------------------------------- 9 [22] In this case, the learned SCJ’s decision was not based upon the issue of delay alone. She had specifically stated that the reason for the delay was unacceptable, as change of solicitors could not be an excuse in light of the fact that the Plaintiff had already filed an application for summary judgment, and that a date had been scheduled for its decision. Furthermore, it would be grossly unjust to the Plaintiff if the application to amend was allowed – an injustice which in my view could not have been compensated by costs. [23] In this context, I found instructive and relevant, the case of Ismail bin Ibrahim & Ors v Sum Poh Development Sdn Bhd & Anor [1988] 3 MLJ 348, where an analogy can be drawn, as in that case, although trial dates had not been scheduled, the application to amend was disallowed as the same was found to be an attempt to circumvent the application to strike out the original writ and the statement of claim. [24] The Plaintiff’s submission was that the timing of this application to amend, raised the issue of bona fides or lack thereof, and it was, therefore, a tactical manouevre to resist the application for summary judgment. [25] Where there is delay in making an application to amend, the applicant must ‘place some material and advance some cogent reasons to impel the court to lean on his side’, failing which, the inference is that the “application borders on lack of bona fides”: per Haidar JCA in Taisho Co Sdn Bhd v Pan Global Equities Bhd & Anor [1999] 1 MLJ 3591 adopting the Singapore case of Multi-Pak Singapore Pte Ltd (In receivership) v Intraco Ltd & Ors [1993] 2 SLR 113. 28 December 2020 ----------------------------------------------------------------------------------------------------------------------------------------------------- ------------------------------------------------------------------------------------------------------------------- 10 [26] I found the Defendant’s reason for its delay unconvincing as it did not explain why the averments in the proposed amendments, were not mentioned in the original Defence, bearing in mind that these facts were readily available at the time the original Defence was filed. [27] On this note, reference is again made to Ismail bin Ibrahim & Ors v Sum Poh Development Sdn Bhd & Anor where it was held that the circumstances in which an amendment would not be permitted are: (a) where the facts giving rise to the amendment were known at the time of the original pleading; and (b) where the delay in making the amendment was in connection with some tactical manoeuvre. [28] The same concerns were expressed in Lim Nyang Tak Michael v ACE Technologies Sdn Bhd [1995] 4 MLJ 616, where in dismissing the defendant's application to amend the defence, the Court held that if the defendant truly had a valid defence, it would not have waited, and the fact that it did, raised the inference that the application was a tactical manoeuvre and was done in bad faith to delay the rights of the plaintiff on his claim. [29] Both Ismail bin Ibrahim & Ors v Sum Poh Development Sdn Bhd & Anor and Lim Nyang Tak Michael v ACE Technologies Sdn Bhd [1995] 4 MLJ 616 were approved and adopted by the court in Jupiter Securities Sdn Bhd v Wan Yaakub Bin Abd Rahman [2002] 3 MLJ