(iii) as the date of completion for the said 24F and 25F were recorded by the Defendant as being 8.2.2015, then the same is within the delay entitlement for this Phase [87] With regards the Coring Issue, I hold again as there is no delay analysis provided by the Plaintiff to this Court on the Coring Issue, I am unable to determine if there was indeed a delay in carrying out the works of Phase 1 and part of Phase 2 because the Defendant had split handover of floors which had allegedly resulted in their inability to carry out coring of bathroom floor for plumbing works. LAD [88] The Supreme Court in Thamesa Designs Sdn Bhd (supra) had held in that case that the employer should not be entitled to claim for liquidated damages under the said contract because, by his omission to give possession of the site on time, the time for completion becomes 'at large' and there was no date from which the damages could be assessed. [89] In any event, on a balance of probabilities and taking into account the evidence of CW1 and his conclusion arrived thereto and the Defendant contending that works for floors 26 and 27 were only completed on 3.11.2014 and date of completion for the said 24F and 25F were recorded by the Defendant as being 8.2.2015, there would in my decision be no valid ground for any LAD claim to be made by the Defendant for these floors. [90] For the record, CW1 had also concluded in his report that there is no LAD exposure for both Phase 1 & 2 and this would, with respect, fortify my findings on the LAD issue. [91] From the facts before this Court, I consequently further hold that as this Court has found acts of prevention by the Defendant, the Defendant is not entitled to claim for liquidated damages herein as such acts of prevention invalidates the liquidated damages clause as, at the sake of repetition, the time for completion as per clause 4 of the Contract now becomes at large. [92] I therefore dismiss the Defendant’s claim for liquidated damages and respectfully follow the decision of Tee Geok Hong JC (as he then was) in Sykt Pembinaan Anggerik Sdn Bhd v Malaysia Airports Holdings Bhd [2022] 9 MLJ 391 Tee Geok Hock, JC, on the basis that a party cannot benefit from or take advantage of its own wrong or default. Alleged Delays Affected Due To Third Party Causes i.e. Marble Damage Incident [93] Following from the above, the next question which needs to be answered is whether there were delays caused by third party causes , being the marble damage which was purportedly caused by a third-party ex-worker who trespassed the Defendant’s Hotel and damaged the marble vanity counter and marble window ledges at level 27/F to room Nos. 2707, 2708, 2710, 2711, 2712, 2714 and 2716. [94] The Plaintiff had of course claimed that this third party act of damage to the marble was beyond the Plaintiff’s control. [95] I have since looked at the evidence on this issue of marble damage and find that i. the video recording of the same shows that the Marble Damage Incident took place at approximately around 7.21 a.m. ii. the Plaintiff had in its email dated 4.12.2014 at Bundle C, page 410, PW-1 explained to Leslie Tong that the Plaintiff cannot be held liable for the Marble Damage Incident, as the said third party ex-worker (Trespasser) was not employed under the Plaintiff’s employment however, by Tunas Innovasi Sdn Bhd, the marble installer iii. the Plaintiff had agreed to rectify the damage as seen in its email of 23.11.2014 to the Defendant iv. the Defendant had imposed a period of 10 days LAD on the Plaintiff as a result of the said damage [96] I am unable from the evidence mentioned above to ascertain what were the working hours of the Plaintiff at the site or whether the said Trespasser was wearing any uniform of the Plaintiff or whether he was indeed an ex worker employed by Tunas Innovasi Sdn Bhd, the marble installer. I consequently hold that the Plaintiff has failed to satisfy this Court that the Trespassers entry into the Site was due to a breach of the Defendant’s security. [97] Following from the above, I do however hold that as the damage to the marble was caused by the Trespasser who was an ex-employee of Plaintiff’s sub-contractor Tunas Innovasi Sdn Bhd, the Plaintiff is to be held responsible for and to make good the said damage as per the case of Syarikat Ong Yoke Lin Sdn. Bhd. v Giant Cash & Carry Sdn. Bhd. & Ors [2000] MLJU 519 where Abdul Malik Ishak J ( as he then was) had held “Reverting back to the issue of privity of contract, I need to cite certain passages from a book entitled "Law and Practice of Construction Contract Claims", second edition by Chow Kok Fong where, at page 226, the learned author said: "A subcontract executed between a main contractor and subcontractor cannot give rise to any privity of contract between the subcontractor and employer. This is because subcontracting operates as a subletting of the physical construction of the works only and does not constitute an assignment of rights and liabilities under the main contract. The main contractor thus continues to be responsible to the employer for the whole of the works and to be liable for any defective work, delay or any other default committed by his subcontractors. There have been occasions in the past where it has been contended that this position may not apply to some situations, particularly, where the subcontractors have been nominated by the employer or where the employer (or his architect or engineer) has otherwise intervened in the choice of subcontractors. This view was canvassed largely on the premise that the main contractor, in the placement of nominated subcontracts, acts as an agent for the employer. However, as noted by one leading commentator, such a result can only be produced by 'the most special and unusual facts showing that the employer expressly or by his conduct authorised the main contractor or the architects so to contract... [because it is] ... contrary to the sense of the usual main contract and the most universal practice in the building industry (Hudson, 10th ed (1970) p 742)'." and these passages would certainly fortify the argument that there was an absence of a contractual relationship between the plaintiff and the first defendant. It was a clear-cut case, in the context of the present case, that the privity rule should be vigorously applied to the detriment of the plaintiff.” [98] My decision that the Plaintiff is to be held responsible for and to make good the said damage to the marble is also in accordance with clause 16(h), (l) and (p) of the Contract. Authority for the latter can be found in the text ‘Construction Law’ Volume II, 3rd Edition by Julian Bailey which quoted the case of Wiltshier Construction (Scotland) Ltd v Drumchapel Housing Co-operative Ltd, 2003 SLT 443, 2003 SCLR 188, 2003 Scot (D) 36/1 where the English Court in that case had found that it was permissible to put the entire risks of such matters upon one party. [99] For the record, clause 16(h), (l) and (p) of the Contract provides as follows: [100] I do also find from the facts aforementioned that the damage was agreed to be rectified by the Plaintiff. On this the Plaintiff had submitted that this warrants at least 10 days EOT for 24/F and 25/F as the Plaintiff’s workers were assigned to repair the damage. [101] The Plaintiff had relied on CW-1, who they claim in his Expert Report has found no reasonable grounds to imply liability on the Plaintiff for the delays to 27/F, as the damage was caused by a third-party i.e the Trespasser. I have viewed the said Report by CW 1 and agree with counsel for the Defendant that CW1 did not make an assessment as to who was responsible for the marble damage as he was of the view that this was a matter of fact, of which this Court agrees with CW1 that this is a matter of fact which is to be decided by this Court. [102] Thus on this issue, I am inclined to hold that this incident of marble damage does not set time at large and thus the Defendant is entitled to damages for the damaged marble. Whether there were any delays and disruptions caused due to additional works, variation orders and delays in confirmation and approval of variation orders from the Defendant’s holding company based in Hong Kong; [103] The Plaintiff had also submitted that there were delays and disruptions caused due to additional works, variation orders and delays in confirmation and approval of variation orders from the Defendant’s holding company based in Hong Kong, purportedly due to internal approval process of the Defendant. [104] The Plaintiff had submitted that the Plaintiff had a ‘strict duty’ to obtain approval from the Defendant prior to carrying out any works, and referred to Clause 7 of the Contract. After reading the said Clause 7, as found in Bundle B, Page118C, I find that the same reads as follows: “Any works done prior to the approval of shop drawings / sample will be subjected to the rejection by the DRM” [105] Thus, based on the said Contract I agree that this Clause 7 does indeed require the approval of the Defendant for the shop drawings / sample before the works can commence. [106] From the facts before me, the Defendant had instructed the Plaintiff to submit shop drawings resulting from the issuance of change in plans for Standard Room Nos, 3, 7 and 14 for each Phase, and on 10.08.2014 and 14.8.2014 respectively, the Plaintiff then emailed the Defendant’s Designer based in Hong Kong i.e. Benjamin Tam (“Benjamin”) with the shop drawings for Standard Room, End Suites 03 and 07 and thereafter for Suite 14 for the Defendant’s approval. [107] As far as the approval for shop drawings, I find from the testimony of DW1 under cross examination that the Defendant had failed to approve the shop drawings on a timely basis by as much as 50 days with no EOT’s given to the Plaintiff, thereby also attributing to the disruption and delays to the Plaintiff’s Works. [108] It would from the documents before me also show thereafter that the Defendant had only about three (3) weeks later i.e 2.9.2014, informed the Plaintiff that Benjamin had signed-off the shop drawings for Standard Rooms, No. 7 and No. 14, save for Standard Room 03 which was still pending as shown in the email at Bundle B, Page 19, Item 3.1. [109] The following evidence was highlighted by the Plaintiff in support of the said additional works referred to above