(iii) The issue in relation to whether the Plaintiff had validly terminated the contract on 28.6.2016 (Issue of termination)?” [33] However, in paragraph 53 of the GOJ, the LJC did not make any ruling on the 2nd termination letter dated 28.6.2016 but instead ruled that the 1st on termination was invalid. Paragraph 53 of the LJC’s GOJ reads as follow: “[53] In our case, it is clear that only the Notice of Default dated 1.02.2016 existed at the time of termination. It is clear that the Notice of Default based on failure to comply with the Notice dated 29.1.2016 no longer exists. Failure to do so causes the 1st termination Notice dated 15.4.2016 to be invalid from the beginning.” [34] Second, the LJC did not make any pronouncement / ruling on the validity of the 2nd termination despite having concluded that 1st termination was invalid. Third, it was never disputed that the Plaintiff’s 1st termination letter dated 15.4.2016 has clearly and explicitly terminated the Defendant’s employment as the main contractor of the Project. It was never the Defendant’s case that it was disputing the validity of the 1st termination. Nowhere in the Defendant’s letter dated 17.4.2016 did the Defendant dispute the 1st termination. In admission of its breaches and the Plaintiff’s entitlement to terminate the PAM contract, the only matter that was raised by the Defendant in its letter was the Defendant’s appeal to the Plaintiff begging the Plaintiff to retract the 1st termination and for a 2nd chance to bring the project to completion (which the Defendant ultimately also failed to do). Fourth, the LJC somehow inexplicably did not give his reasons or explain the underlying ‘reason’ that the validity of the 1st termination remains to be of concern or an issue before him. [35] Hence, the above considered, we have no hesitation to agree with the counsel for the Plaintiff that the validity of the 1st termination in actuality was never an issue to begin with. There is no reason whatsoever for the LJC to harp on the validity of the 1st termination considering the fact that the 1st termination had already been admitted by the Defendant (and had in fact been retracted due to the execution of the CRA). Even if for any reason at all that there were any defects or technicalities in the exercise of the 1st termination by the Plaintiff, the Defendant had not suffered any damages or prejudice considering both the Plaintiff and the Defendant had mutually moved on beyond the 1st termination and later landed on the 2nd termination (which also reflected poorly of the Defendant’s trend and tendency to breach promises or contracts it entered into). [36] Instead the LJC went on at length on how the 1st Termination was invalid as the 1st termination letter was issued based off of a ‘non-existent’ NOD dated 29.1.2016 (of which the Architect had subsequently replaced or superseded with another NOD dated 1.2.2016). [37] The LJC further ruled that as there was no issuance of afresh NOD pursuant Clause 25.2 of the COC, the Plaintiff therefore cannot rely on the NOD dated 1.2.2016 to terminate the Defendant’s contract via the 2nd termination letter dated 28.6.2016. The LJC was under the erroneous assumption that the 2nd termination was exercised pursuant to the terms of the COC (where in actuality, the 2nd termination was exercised pursuant to the mutually agreed CRA which allows the Plaintiff to terminate the contract “bila-bila masa” in the instance the Defendant was in breach of the revised micro schedule) [38] We are regretfully of the view that the LJC was essentially confused in appropriately analyzing and appreciating the distinct and separate complexities of the issues surrounding the 1st termination and 2nd termination. This confusion had led him to misconstrue the true context and content of the 2nd Termination Notice dated 28.6.2016. [39] We must emphasize that it was apparent that the Plaintiff was exercising the new additional right to terminate “at any time” under the CRA due to Defendant’s failure to adhere to the revised micro schedule. This was clearly reflected looking at the contents of the Conditional Reinstatement Agreement (CRA) dated 19.5.2016. The relevant part of the letter states as follows: a. Untuk makluman tuan, Mesyuarat Lembaga Perolehan Bil.5/2016 bertarikh 16 Mei 2016 telah memutuskan Kontrak K/45/2015 bagi Cadangan Membaikpulih Bangunan Infirmary di Jalan Sungai, Pulau Pinang dibenarkan untuk kontraktor menyambung semula dan menyiapkan kerja-kerja pembinaan dengan syarat-syarat berikut: b. Kontraktor hendaklah menyiapkan projek tersebut dalam tempoh 45 hari sehingga 6 Julai 2016; Majlis boleh menamatkan kontrak BILA-BILA MASA sekiranya kontraktor gagal mengikut jadual terperinci harian (daily micro rescheduling) yang ditetapkan; c. Pembayaran penuh hanya akan dibuat apabila projek tersebut selesai. [40] The contents of the CRA are crystal clear. In the CRA, the Plaintiff had explicitly stated that in its Procurement Board Meeting held on 16.5.2016, it was agreed that the Defendant be given another chance to complete the works within the 45 days. It is also clearly stipulated in the CRA that the agreement to allow the Defendant to complete the project with a deadline of 45 days is strictly subject to the stipulated condition that the Defendant must strictly comply with the Revised Micro Schedule, failing which the Plaintiff has every right under para 2 (ii) of the letter to terminate the contract at any time. This departure from the initially prescribed mechanism of termination in the COC was mutually agreed upon by both parties. The Defendant cannot now feign ignorance or confusion that the Plaintiff must still abide by the COC which the Defendant itself had agreed to dispense with. [41] We find that the LJC was plainly wrong in finding the termination of the contract was invalid merely because there was no fresh NOD / CNC being issued under Clauses 25 and 22 of the COC before the 2nd termination letter was issued. We must reiterate that a fresh CNC or NOD is only necessary if the Plaintiff was exercising the right to terminate under the COC. However, in this case the Plaintiff was in fact exercising its additional right to immediate termination under the CRA and not under any provisions of the COC. [42] We are of the view that insisting on a fresh issuance of CNC or NOD would mean the Court is reading additional conditions beyond what was mutually agreed upon under the CRA. In fact, the Conditional Reinstatement was not an EOT that would trigger the cancellation of the CNC under Clause 22.3 of the COC. It would be thoroughly unjust to insist on the Plaintiff to comply with termination procedures under the COC as it would directly run afoul against the express mutual agreement under the CRA that the Plaintiff can terminate the contract “at any time”. Thus, insisting on the termination procedures under the COC (for the 2nd Termination under the CRA) was also akin to unlawfully and unnecessarily improving the Defendant’s bargain in the CRA. Suffice that we refer to the recent decision in the case of Davanam Constructions Sdn Bhd v THP Enstek Development Sdn Bhd (formerly known as TH-NSTC Sdn Bhd) [2024] MLJU 1280: “[115] It was also significantly audacious for the Plaintiff to insist upon this Court to re-write the JVDA so as to improve the bargain the Plaintiff itself had struck upon its own feasibility studies the Plaintiff had conducted well before the JVDA. If this Court were to begin to excuse contracting parties based on the market’s fluctuations, then this Court would have disintegrated the very fabric of good commerce. If that shall be the precedent, then every and all parties to a contract would be allowed to exonerate itself from all blame of contractual breach by assigning blame against the economy or market fluctuations. The immovable rule remains that no parties cannot stand (after a contract) to seek the Court’s assistance to improve the bargain it had agreed to prior. This principle was very recently restated by the Court of Appeal in the case of Orion Choice Sdn Bhd v Bellajade Sdn Bhd [2023] 5 MLJ 437: “Nor can the courts exert unnecessary discretion to deter party autonomy and improve on any party’s bargain in a contract. We can do no better than to refer to the wisdom of the Federal Court in the landmark case of CIMB Bank Bhd v Anthony Lawrence Bourke & Anor [2019] 2 MLJ 1: [26] We agree with the defendant that parties are bound by the terms of the contract which they entered into and that it is the court’s duty to give effect to the clear and plain meaning of the words in the said clause. That is quite trite. [28] It is also trite that an agreement must be construed by the words used in the agreement and the court is not empowered to improve upon the instrument which it is called upon to construct. This we have stated in Berjaya Times Squares Sdn Bhd (formerly known as Berjaya Ditan Sdn Bhd) v M Concept Sdn Bhd [2010] 1 MLJ 597... (Emphasis added.)” [43] It was also patently clear to us that it was erroneous for the LJC to find that the 2nd termination was invalid merely because it was issued before the lapse of 45 days. A plain reading of paragraph 2 (ii) of the CRA sufficiently reveals that the Plaintiff was not bound to wait for the lapsing of the additional 45 days (ending 6.7.2016) to issue the 2nd Termination letter. The additional right to termination was subject to strict adherence of the revised micro schedule and NOT any number of days. As the Defendant began to breach the revised micro schedule even before the lapsing of the 45 days, the Plaintiff was entitled to the 2nd Termination there and then. [44] In view of all the deliberations under this heading, we here answer issue 1 in the negative. The LJC had certainly erred in finding that the Plaintiff’s termination of the PAM contract was invalid. G. ISSUE 2: WHETHER THE LJC WAS CORRECT IN HIS FINDING THAT THE CONDITIONAL REINSTATEMENT AGREEMENT WAS AN EOT, AND THUS, TIME WAS THEREFORE SET AT LARGE. HENCE, THE EOT WOULD HAVE EFFECTIVELY NULLIFIED/ INVALIDATED THE PLAINTIFF’S CLAIM FOR LAD. [45] The LJC had erroneously accepted the Defendant’s submission that the Plaintiff by its CRA had effectively granted the Defendant an ‘EOT’ to finish up the project until 6.7.2016. The LJC had premised his conclusion on the basis that prior to the issuance of the 2nd termination letter on 28.6.2016, the Plaintiff did not issue a fresh CNC and a fresh NOD in accordance to clauses 22 and 25 of the COC respectively. According to the LJC, since the Plaintiff had cancelled the 1st termination via its CRA, all the reasons that had led to the 1st termination are completely null and void. And therefore, the Plaintiff cannot rely on the “sebab-sebab” which were stated on the previously issued CNC / NOD (dated 14.9.2015 and 1.2.2016 respectively). The LJC did not accept the argument by the Plaintiff that the 2nd termination letter was issued based on the conditions stated in the CRA. The LJC was of the view that to terminate the contract, the Plaintiff must comply with the provisions under the COC (see paragraphs 73 and 74 of the GOJ). [46] With due respect to the LJC, he had again misconstrued the COC. The very fact of the matter is; the cancellation of the 1st Termination Notice does not mean the Plaintiff also terminates the CNC. We must emphasize here that the CRA does not erase the factum of delay up to the 1st Termination Notice. The CRA never mentioned of the Plaintiff’s intention to ‘exonerate’ the Defendant from its admitted delays already accrued within the 1st tranche of the LAD period (prior to the 2nd Termination). The granting of additional 45 days way past the original completion date under the CRA by no means was a locus classicus EOT under the PAM contract and the COC. [47] In a typical construction contract (especially a PAM contract), the manner and method for the contractor to request for and obtain an EOT was clearly prescribed under the PAM contract or COC. Should the contractor identify that it might not be able to comply with the originally set deadline, it was incumbent upon the contractor (the Defendant in this case) TO FIRST APPLY FOR EOT. Then, by the Plaintiff’s discretion (and of course fair consideration), THE PLAINTIFF MAY OR MAY NOT GRANT THE DEFENDANT EOT. Should the Plaintiff allow the Defendant’s application for EOT, only then the Plaintiff is disentitled from claiming LAD SPECIFICALLY for the number of days that the Plaintiff allowed for extension. This is the crucial misapprehension that plagued the LJC’s erroneous decision. He had found that time had been set ‘at large’ merely because the Plaintiff had allowed additional 45 days under the CRA for the Defendant to complete the project (of which the Defendant still failed to do so). This was entirely wrong and a misconceived understanding on the mechanism of EOTs. At best, even if the 45 days under the CRA was somehow an EOT (of which it was definitely not an EOT), the Defendant hypothetically might be entitled to absolve delays up to 45 days ONLY and NOT FOR THE ENTIRE DURATION OF DELAY. Thus, if for instance if there was already a delay of 145 days (inclusive of the additional 45 days), the Plaintiff would still be entitled to 100 days’ worth of LAD. What more in this case where the CRA was not even an EOT, the Plaintiff remains entitled to LAD upon the entire breadth and length of the Defendant’s total delays. [48] And we must again reiterate that the CRA only states that the Defendant was conditionally given 45 days to finish up all incomplete works so as to avoid total termination of the contract. It did not set a ‘new completion date’. The Plaintiff was still intent on claiming LAD for the delays post or prior to the initial 1st Termination. [49] The Plaintiff’s entitlement to LAD is specifically provided Clause 22 of the COC. Therefore, this Court must emphasize that Clause 22.1 of the COC is a contractual provision related to liquidated damages which entitles the Plaintiff to recover compensation in the forms of monetary payment triggered by occurrence of specified default or breach by the Defendant (as main contractor) in performing its obligation under the contract. Therefore, Clause 22 of the COC has nothing directly to do with termination of the contract. [50] Now, if there was delay (breach) on the part of the Defendant in carrying out its obligation under the contract, for purpose of claiming LAD, Clause 22 of the COC requires the Plaintiff to issue a CNC. A CNC is invalidated / cancelled only when there was a proper application and granting of EOT under the procedures prescribed under Clause 22.3 of the COC. It was wrong and baseless for the LJC to assume that the CNC was automatically invalidated when the 1st Termination Notice was cancelled. It was also wrong and erroneous for the LJC to find that the CRA was an EOT that triggers the cancellation of the CNC under Clause 22.3 of the COC. [51] Regrettably, we find that the LJC did not appreciate the proper operation of the provisions under the COC, particularly the provision for LAD and the issuance of a CNC (Clause 22 of the COC) and the granting of EOT (Clause 23 of the COC). We must stress that there is a distinct difference between granting EOT (which acquiesces delay and disentitles LAD) under the COC and granting ‘conditional days’ under a totally separate CRA. Now, when EOT is applied for and granted under the COC, then the employer cannot claim for LAD for specifically for the number of days allowed for extension (which does not cover the entire length of delay if the delay ran longer than the extension granted). [52] In the Appeal before us, it must be noted the Defendant had admitted that they indeed did submit a total of 6 applications for EOT and all the applications were rejected by the Architect via his letter dated 11.9.2015. It must also be noted that the rejection was never challenged by the Defendant. It must also be observed that during the subsistence of the CRA, the Defendant by its letter dated 15.6.2016 had re-applied for 6 EOTs to the Architect but was also rejected on the ground that the Defendant’s EOTs applications neither have legal basis nor factual basis. At the trial, the evidence of the Architect (PW 1) in respect of the rejection of the EOTs’ applications again were never challenged by the Defendant. Therefore, the undisputed fact remains that there was no EOT granted by the Plaintiff to the Defendant to negate or disentitle the Plaintiff of its claim for LAD. Most pertinently, the factum that the Defendant proceeded to re-apply for the 6 EOTs clearly proven that the CRA was not an EOT (and thus does not trigger the cancellation of the CNC under clause 22.3 of the COC). If the Defendant genuinely believed that the CRA was an EOT to set time at large, then the Defendant would not have re-applied for the 6 EOTs. [53] Regarding the additional 45 days given to the Defendant by the Plaintiff vide its CRA, it is crystal clear that the additional 45 days were conditionally given under a totally separate contract. Thus, the original completion date and prior period of delay as against the PAM contract remains intact (if the conditions were eventually not met). [54] In fact, since the Defendant had failed to ensure diligent adherence to the revised micro schedule (albeit before the lapsing of the 45 days), the Defendant is not even entitled to the entirety of the conditional benefit of the 45 days that was conditionally granted via the CRA. The 45 days’ benefit is only attainable if and only if the Defendant strictly and diligently adhered to the revised micro schedule (which the Defendant clearly had failed to do so). [55] Succinctly, contrary to the finding of the LJC that the CRA constituted an EOT, even the Defendant itself admitted that the conditional reinstatement was not an EOT considering the fact that the Defendant still re-applied for 6 EOTs after the issuance of the CRA. Thus, the Defendant’s own conduct justifies estoppel to apply to estop the Defendant from contending that the CRA was an EOT (which the CRA certainly was not). [56] Considering the aforementioned deliberations, it is plain and obvious that the CRA was not an EOT. Since the CRA was not an EOT, Clause 22.3 COC was not triggered to invalidate the CNC. Thus, the Appellant remain entitled to both the 1st tranche (accruing at 1st Termination) and 2nd tranche (accruing at 2nd Termination) of LAD. [57] Considering all of the deliberations under this heading, we hereby answer issue 2 in the negative. The LJC had certainly erred in finding that the Conditional Reinstatement Agreement was an EOT. Thus, time was never set at large. Hence, the Plaintiff remains entitled to claim for LAD. H. ISSUE 3: WHETHER ESTOPPEL APPLIES AGAINST THE DEFENDANT CONSIDERING THE DEFENDANT’S OWN DEPARTURE FROM A STRICT AND RIGID CONFORMITY OF THE PAM CONTRACT AND THE COC. [58] In the Appeal before us, we cannot ignore the fact that the Defendant in resisting / negating the Plaintiff’s claim for LAD had tenuously complained that the Plaintiff had failed to comply with the provisions of the COC with regards to the termination of the contract, in particular Clauses 22, 23 and 25 (relating to issuance of CNC and NOD before the Plaintiff can terminate the contract). [59] We are of the view that it no longer lies before the Defendant to complain and insist on strict or rigid conformity or adherence to the COC on the following grounds: