Content
1 IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR IN THE STATE OF WILAYAH PERSEKUTUAN, MALAYSIA (CIVIL DIVISION) SUIT NO: WA-22C-23-02/2017 BETWEEN MATRIX CONCEPTS (CENTRAL) SDN BHD (COMPANY NO: 404543-A) … PLAINTIFF AND AR LIM YOKE TIANG (Board of Architects Registration No: A/L 221) [practising as a Professional Architect and Principal under the name of YTT ARCHITECT] ... DEFENDANT THE JUDGMENT OF Y.A. LEE SWEE SENG [1] The Plaintiff is a Developer and had bought a piece of development land in Puchong from IRDK Ventures Sdn Bhd (“IRDK”) together with a condominium project on the said land pursuant to a Sale and Purchase Agreement (“SPA”) dated 21.4.2015. The Defendant is a registered Architect with the Board of Architects of Malaysia. The Defendant had 2 earlier been engaged by IRDK as the Architect for the development land to develop it into a condominium project with car parks and villas for sale to the public (“the Project”). Project [2] The Plaintiff had agreed to continue with the Defendant’s engagement as their Architect for the Project and they issued the Defendant a Letter of Appointment dated 25.5.2015 for his engagement with agreed professional fees and other terms and conditions that will be considered with greater depth in the course of this judgment. [3] Suffice to say by way of introduction that Clause 11 of the Letter of Appointment allowed the Plaintiff to unilaterally terminate their contract with the Defendant by giving a 30-day Notice and 7 days thereafter the Defendant as the Architect is to issue his Letter of Release to the Plaintiff to enable them to proceed with the Project without delay. [4] The same Clause in the contract also mentioned that upon termination the remuneration of the Architect shall be computed without any delay based on the schedule of work in progress at the site. [5] Clause 13 of the Letter of Appointment also provided that upon termination the Architect shall deliver the relevant documents including specifications and computations (“the Documents”) to the Plaintiff as his Client within 14 days. Problem [6] As is not uncommon, problems arose between the parties with respect to the professional fees of the Defendant upon the termination of the Letter of Appointment. The Architect refused to issue the Letter of 3 Release to the Plaintiff on the ground that his balance fees had not been paid. Upon being terminated on 2.11.2016 the Defendant had issued an invoice for RM2,843,342.12 which sum is derived from the fees owing from the previous developer IRDK to the Defendant. There was also another invoice for additional work done for the Plaintiff for the sum of RM342,347.48 after taking into consideration the sum of RM880,000.00 paid by the Plaintiff to the Defendant. [7] It should also be stated here that both the parties had agreed on a total professional fees of RM3,600,000.00 and that the “Agreed Cumulative Work done” as at 20.5.2015 @ 55% stage of payment is RM1,980,000.00 and that after deducting the sum of RM1,100,000.00 paid by the Plaintiff to IRDK for services rendered by the Defendant to IRDK and an agreed one-off Lump Sum Reimbursement of RM300,000.00 there is the balance sum of RM1,250,000.00 due to the Defendant after taking into consideration service tax at 6%. [8] The Plaintiff disputed the sums owing to the Defendant and maintained that no further sums were owing for the Defendant’s fees. The Defendant stood his ground and refused to issue the Letter of Release. The result was an impasse and upon the Defendant threatening to withdraw the approved Drawings and Plans with the local authority, the Plaintiff applied to this Court for an injunction to compel the delivery of the Documents and the issuance of the Letter of Release. [9] Parties could agree on a consent order for the said surrender of documents and the issuance of the Letter of Release on the hearing of the application on 2.3.2017 subject to the deposit of an agreed sum of RM1.6 million on the disputed fees into the joint stakeholders account of both the solicitors for the parties. That was without prejudice to the parties’ rights to 4 claim from each other the damages from the alleged breaches of the contract in the Letter of Appointment. Prayers [10] The Plaintiff filed their Writ and Statement of Claim to claim for damages arising out of the breach of the Letter of Appointment. They claimed for wasted expenditure costs of RM738,205.47 up to 20.2.2017 (the date of the injunction) with a further sum of RM10,698.63 per day from 21.2.2017. [11] The Plaintiff further claimed for loss of profit of RM6,931,506.78 until 20.2.2017 together with a daily loss of RM100,456.72 from 21.2.2017. [12] Not to be outdone the Defendant counterclaimed for RM8,571,060.00 and RM2,843,342.12 plus 6% GST for his professional fees outstanding whilst maintaining that there was no breach of the Letter of Appointment in not issuing the Letter of Release and delivering the Documents to the Plaintiff until the relevant security for his fees is furnished or his fees is paid. Principles Whether there was a breach by the Defendant of the Letter of Appointment dated 25.5.2015 and in particular Clauses 11 and 13 in the Defendant refusing to issue the Letter of Release and deliver the Documents to the Plaintiff [13] Learned counsel for the Plaintiff submitted that the Defendant was in clear breach of the Letter of Appointment when the Defendant refused to issue Letter of Release and to deliver the Documents to the Plaintiff within 5 the stipulated time in accordance with Clauses 11 and 13 of the Letter of Appointment (page 31 CBOD 1). [14] Clauses 11 and 13 of the Letter of Appointment read as follows: “11. TERMINATION OF APPOINTMENT As an additional clause of termination, this appointment may be unilaterally terminated by the Client giving one (1) month written notice. Upon such termination, the Architect shall issue the Letter of Release within seven (7) calendar days to the Client and all other relevant bodies to enable the Client to proceed with the Project without any delay. The remuneration of the Architect upon termination shall be computed without any delay. The remuneration of the Architect upon termination shall be computed based on the schedule of work in-progress at the site. ……….