In the event of the death of the arbitrator or his unwillingness or inability to act, then the Employer and the Contractor upon agreement shall appoint another person to act as the arbitrator, and in the event the Employer and the Contractor failing to agree on the appointment of an arbitrator, an arbitrator shall be appointed by the person named in the Appendix I hereto.” (emphasis added) [24] The Plaintiff submitted that the language used in Condition 63 is clear and unequivocal in its meaning. In the first instance at sub-paragraph (a), that disputes or differences arising between the parties shall be referred to the ER. [25] Thereafter, and in the event the E.R. fails to give a decision or if the Plaintiff is dissatisfied with the decision given by the E.R., the Plaintiff may require that the dispute or difference be referred to arbitration. [26] According to the Plaintiff Contractor, the option is available and open at the instance of the Contractor to proceed to arbitration if the Contractor is minded to. If the Plaintiff intends to refer the matter to arbitration under Condition 63, the Plaintiff would have to comply with the pre-requisite set out under Condition 63 requiring the Plaintiff to refer the dispute to the E.R. first. However, in the event the Plaintiff does refer the dispute to the E.R. first, the Plaintiff is thereafter not compelled to refer the dispute to arbitration, and can still opt to file an action in Court. 12 [27] I do not think the Contractor has the option not to follow the pre-arbitration procedure by referring the dispute to the E.R. but that the Contractor could proceed straight to the Court. To proceed to Court would be to short-circuit and bypass the agreed procedure with respect to arbitration which is in the nature of a precondition to be fulfilled before proceeding with arbitration. [28] I agree that there is a typographical error in the underlined word “any” in the relevant portion of Condition 63 which provides “…then in any such case the Contractor any within forty-five (45) days after the expiration of forty-five (45) days after he had made his request to the E.R….” (emphasis added). The word “any” does not make any sense nor supply any meaning to the sentence. The use of the word “any” is clearly a typographical error and is meant to read “…then in any such case the Contractor may within forty-five (45) days after the expiration of forty-five (45) days after he had made his request to the E.R….” (emphasis added) [29] I agree with learned counsel for the Plaintiff that this is obviously the case as the language employed in Condition 63 is in fact based entirely upon the 1983 version of the JKR Form 203A Standard Form Contract (also known as the PWD Form 203A [Ed 1983]) [apart from the reference to “E.R.” rather than “SO”], where the language utilized in Clause 54 thereof, equivalent to Condition 63 now under consideration, contains the permissive word “may” rather than the word “shall” in sub-clause (c). [30] Learned counsel for the Plaintiff then submitted rather strategically that the use of the word “any” by mistake by the Defendant in drafting Condition 63 ought to be construed against the Defendant, such that the relevant portion of Condition 63 should in fact be read as “…then in any such case the Contractor may within forty-five (45) days after the 13 expiration of forty-five (45) days after he had made his request to the E.R….”. [31] The Plaintiff harnessed the contra proferentum rule of interpretation to help them further. This rule provides that any ambiguity in a document must be construed against the party preparing the document and who seeks to rely upon the terms thereof. See : Stanta Metal Drum Sdn Bhd v Tokio Marine Insurans (Malaysia) Berhad [2012] 2 MLRH 179 (High Court), Hing Auto Sdn Bhd v Unidive Marine Services (M) Sdn Bhd [2015] MLRHU 299 (High Court) and New Ace Digital Print Sdn Bhd & Anor v Public Bank Berhad [2018] 2 MLRA 346 (Court of Appeal). [32] I am not persuaded by learned counsel for the Defendant in the position he had taken that there is no typographical error in Condition 63, and that the word “any” was intended to be used. This position is completely untenable as the Condition makes no sense whatsoever if read with the word “any”. A comparison between Condition 63 and Clause 54 of the 1983 version of the JKR Form 203A Standard Form Contract will immediately confirm that there was indeed a typographical error in copying Clause 54 and that Condition 63 should indeed be read with the word “may”. This is no doubt made more prevalent with the “copy and paste” approach taken in drafting without proper checking with the result that some words had fallen through the cracks and that the substituted word is not the correct word. [33] It cannot be that when the form of English used is almost impeccable in the rest of the Conditions of Contract, the drafter could have introduced a misplaced word “any” that does not fit nor flow in the context and the clause. 14 [34] In this respect I draw comfort from the authoritative text of Keating on Construction Contracts by Stephen Fust and Vivian Ramsey, (8th Edn, Thomson Sweet & Maxwell 2006) and to the following passage: “[2-021] Meaningless words. An apparent agreement containing meaningless words may be treated in one of three ways: the meaningless words may be ignored and the rest of the clause in which they appear enforced; or the clause in which they appear may be struck out but the rest of the agreement enforced; or the whole agreement may exceptionally be vitiated. Which of these may occur depends on the importance which the parties are considered to have attached to the clause and, presumably, on the remaining integrity of the agreement shorn of the meaningless words. If a clause taken literally is almost incomprehensible, the court may be prepared to ‘translate’ it if the parties’ intention is clear, even though this might involve using words not to be found in the contract.” (emphasis added) [35] I agree that “shall” may mean directory and not mandatory as in Condition 63(a), even though Condition 63 utilizes the word “shall” in connection with a reference of the dispute or difference to the E.R. for a decision. The parties may choose to live with the dispute and so in spite of the use of the word “shall” it does not render such a reference mandatory. [36] However if the Contractor chooses to proceed with reference to the E.R. for the resolution of the dispute or difference then contractually parties have agreed to follow the procedure and consequences that have been provided for. [37] It had been remarked that “shall” is the most confusing word in the English language when it comes to drafting as whether or not it is 15 mandatory or merely directory would depend on the context in which it was used. This proposition has the support of many an authority. See: Hee Nyuk Fook v Public Prosecutor [1988] 1 MLRA 482 (Supreme Court), Lim Phin Khian v Kho Su Ming [1995] 2 MLRA 239 (Supreme Court) and Al Emas Sdn Bhd v Pentadbir Tanah Daerah Kuala Muda, Kedah Darul Aman (Unreported) (Court of Appeal). [38] I would conclude that Condition 63 is an Arbitration Agreement binding on the Contractor if they should choose to proceed further after reference to the E.R. with or without a decision from him. The Arbitration that is to commence shall follow the procedure as set out in Conditions (d) to (h) with respect to the appointment of the Arbitrator and the powers given to the Arbitrator. [39] It may be commented that there is no option to the Employer to similarly proceed with arbitration and that is because they have agreed to abide by the decision of the E.R. appointed by them, no matter how unpleasant the decision might be in the meanwhile. [40] Whether or not the Arbitration Agreement has with it an option for the Contractor to choose proceeding in Court rather than before an Arbitrator will be considered next. Whether Condition 63(c) of the Conditions of Contract gives an option to the Contractor to proceed with Arbitration or Litigation should the Contractor chooses to proceed further after a reference to the E.R. [41] As stated, the Plaintiff’s stand is that under Condition 63, if the Plaintiff has referred a dispute to the E.R. and where the E.R. either does not give a decision, or if the Plaintiff is dissatisfied with the decision given, the Plaintiff can elect to proceed with arbitration, in which event the ensuing 16 provisions of Condition 63 will apply. The Plaintiff also has the equally valid option of electing to have the dispute or difference resolved through other means. In the present case, the Plaintiff has elected to have the dispute resolved by the High Court, which the Plaintiff said it is clearly entitled to do, under Condition 63(c). [42] Learned counsel for the Plaintiff cited the case of Lembaga Pelabuhan Kelang v Kuala Dimensi Sdn Bhd and another appeal [2011] 2 MLJ 606 in support of the above proposition. In this case, the Court of Appeal considered a plethora of cases in deciding upon the proper interpretation of an arbitration clause which, similarly to Condition 63 in the present case, that : “Any such dispute or difference which cannot be resolved amicably may be referred to arbitration in accordance with this Agreement.” [43] Low Hop Bing JCA opined on the use of the word “may” in the relevant arbitration clause as follows: “[30] In addition, unlike the peremptory word “shall”, the permissive word “may” used in the arbitration clause ie cl 11.1 of DA1 is capable of readily abandoning the discretion to refer to arbitration, and opting for litigation instead, as expressed and contractually agreed by the parties in the supplemental agreements DA2 and DA3 via the ‘submission to jurisdiction’ clauses….” [44] Learned counsel also sought to persuade the Court by referring to the case of Syarikat Pembinaan Anggerik Sdn Bhd v Malaysia Airports Holdings Berhad [2017] MLJU 2019; [2017] MLRHU 1, where the High Court originally granted a stay to the Defendant/Applicant under Section 10 of the Act, but this decision was reversed on appeal to the Court of Appeal (grounds of decision pending). The basis upon which the High Court 17 decision was reversed is, inter alia, that Condition 53 of the Conditions of Contract in that case (exactly the same as Condition 63 in the case, save for the typographical error in using the word “any”) did not amount to an arbitration agreement and as such, Section 10 had no application to the matter. The approved Court of Appeal Order dated 30 March 2018 was produced. [45] It was argued by the Plaintiff that as it stands therefore, the Court of Appeal has determined that an identical provision, applying the contra proferentum rule (Condition 53 in that case) did not amount to an arbitration agreement, as a result of which the Defendant/Applicant could not apply to stay the same pending a reference to arbitration under Section 10 of the Act. [46] Therefore applying the doctrine of stare decisis, learned counsel for the Plaintiff submitted confidently that this Court ought to arrive at a similar conclusion, as the provision relied upon by the Defendant/Applicant in this case is identical, applying the contra proferentum rule, to that in the Syarikat Pembinaan Anggerik Sdn Bhd case (supra). See: Dalip Bhagwan Singh v PP [1997] 1 MLRA 653. [47] Learned counsel for the Plaintiff then sought to prevail upon its Court to conclude that there is no arbitration agreement as between the Plaintiff and the Defendant contained in the Conditions of Contract, within the meaning of Section 9 of the Act, and that therefore, Section 10 of the Act does not come into operation. [48] As this Court does not have the benefit of the judgment of the Court of Appeal, this Court is not able to conclude as to whether the dismissal of the appeal is on the ground of there being no arbitration agreement or on some other grounds. It is to be noted that other grounds were raised as 18 could be gleaned from the judgment of the High Court in Syarikat Pembinaan Anggerik case (supra) as follows: “[13] On clause 5 providing Supplemental is governed by the laws of Malaysia and parties irrevocably submit to jurisdiction of the courts in Malaysia reinforcing Plaintiff submission it can elect to refer to arbitration or litigation Hamidah Fazilah Sdn Bhd v Universiti Tun Hussein Onn Malaysia [2017] 7 MLJ 274 is instructive. There one issue was whether a clause on governing law and submission to exclusive jurisdiction of courts would negate the arbitration agreement and the court preferred a harmonious interruption in an apparent contradiction at first reading. It was stated at page 291 - “[57] This is clearly a case where a holistic and harmonious approach is to be followed, giving effect to the clear intention of the parties to resolve all matters arising out of or in connection with the contract to arbitration. At the same time parties affirm that where they have to approach the court to aid and assist them in the instances set out above, they would then submit to the exclusive jurisdiction of the Malaysian courts.” Thus clause 5 of Supplemental would not affect the validity of the arbitration agreement contained in clause 53 and clause 4. [14] Plaintiff’s contention that Defendant had by conduct evinced an intention not to be bound by the strict compliance of Main Contract or Supplemental as it failed to comply with clauses 43 and 47 of Main Contract was not proved but only a bare assertion. In any event the agreement in clause 53 and clause 4 are subject to the doctrine of separability which 19 provides for the severability or autonomy of the arbitration agreement. The doctrine of separability treats the arbitration clause and the underlying contract as two distinct contracts.”(emphasis added) [49] The decision in the case of Hamidah Fazilah Sdn Bhd v Universiti Tun Hussein Onn Malaysia (supra) in the High Court was affirmed by the Court of Appeal on 28.2.2017 in Civil Appeal No. W-02(IM)(C)-1597- 08/2016. [50] In fact a similar argument was mounted in this case to buttress the argument that parties had intended the reference to arbitration as optional at the instance of the Contractor. [51] Learned counsel for the Plaintiff submitted that the fact of an option available to the Contractor to proceed either with Arbitration or Litigation can be gathered from some other Conditions in the Contract, for example, Condition 45, which expressly recognizes the right of the Plaintiff to bring a dispute arising between itself and the Defendant, to Court. Condition 45 provides as follows: “No certificate of the E.R. under any provision of this Contract shall be considered as conclusive evidence as to the sufficiency of any work, Equipment, materials or goods to which it relates, nor shall it relieve the Contractor from his liability to amend and make good all defects, imperfections, shrinkages, or any other faults whatsoever as provided by this Contract. In any case, no certificate of the E.R. shall be final and binding in any dispute between the Employer and the Contractor if the dispute is brought whether before an arbitrator or in the Courts” (emphasis added) 20 [52] As pointed out earlier the Employer may proceed to Court because the route of resolving disputes via arbitration is open only to the Contractor and not the Employer. Obviously when there is a Claim by the Employer and a Counterclaim by the Contractor invariably the issue of the finality of E.R. Certificate shall be reopened and reviewed. [53] Conversely the Employer might have no objection to the Contractor proceeding to Court to resolve the disputes or that the Employer have taken further steps in the proceedings in Court such that they have lost their right to apply for a stay of the proceedings under section 10 AA 2005. [54] I do not think one should read Condition 45 so narrowly as to confine it to just one scenario when a few permutations are probable. [55] In Hamidah Fazilah Sdn Bhd v Universiti Tun Hussein Onn Malaysia (supra) the High Court rejected the argument that the arbitration agreement had been negated by the parties’ agreement to submit to the jurisdiction of the Court as follows: [53] I find no contradiction between the applicability of the arbitration clause in the said contract document in cl 67.0 and the cl 70.0 in relation to the submission of parties to the jurisdiction of the High Court. [54] As we are all aware, when it comes to certain reliefs in aid of arbitration and more so when it comes to setting aside and enforcement of an arbitral award, the parties seeking such reliefs would still have to come to the relevant court for assistance. To avoid bickering over what law to apply and which court to apply for such reliefs, parties have addressed this issue at the outset in governing law clause. As both the parties are incorporated in Malaysia and carrying out their business here and as the project is here, it makes 21 every sense for the laws of Malaysia to apply. Parties have agreed to submit to the exclusive jurisdiction of the courts of Malaysia where there is a need to come to the Malaysian courts to apply for interim measures such as an injunction for instance under s 11 of the Arbitration Act 2005 or for setting aside the award under s 37 or to refer a question of law under s 42 or under s 38 for enforcement of the arbitral award. [55] Section 11 of the Arbitration Act 2005 reads as follows: 11 Arbitration Agreement and Interim Measures by High Court