Content
1 IN THE COURT OF APPEAL, MALAYSIA AT PUTRAJAYA (APPELLATE JURISDICTION) SIVIL APPEAL NO: W-02(NCVC)(W)-1567-07/2018 BETWEEN MERIDIAN CONTRACTS SDN BHD … APPELLANT (No. Syarikat: 530788-P) AND BAUER (M) SDN BHD … RESPONDENT (No. Syarikat: 121194-X) In the Matter of High Court of Malaya at Kuala Lumpur Civil Suit No: WA-22NCVC-458-07/2018 Between Meridian Contracts Sdn Bhd … Appellant (No. Syarikat: 530788-P) And Bauer (M) Sdn Bhd … Respondent (No. Syarikat: 121194-X) 2 CORAM: MOHAMAD ZABIDIN MOHD DIAH, JCA HADHARIAH SYED ISMAIL, JCA AHMAD NASFY YASIN, JCA GROUNDS OF JUDGMENT INTRODUCTION [1] This is an appeal by the Appellant, the Plaintiff in the court below against the decision of the learned High Court Judge in dismissing the Appellant’s claim after trial. [2] We have read the written submission and heard counsels for both parties. [3] Having considered the materials placed before us in the records of appeal, we are satisfied that there are merits in the appeal. We accordingly and unanimously allowed the appeal. The following are our grounds in arriving at that decision. BACKGROUND FACTS [4] The dispute between the parties arose from facts that occurred commonly in construction contracts. It occurred in the following way. The Respondent was appointed by Embassy Court Sdn. Bhd. on 12.07.2005 to carry out and complete the piling and substructure works for a condominium project located on part of Lot 305, Section 63, Lorong 3 Kuda, Off Jalan Tun Razak, Kuala Lumpur. The value of this project was stated to be RM31,226,056.14. The Respondent, subsequently on 30.08.2015, appointed the Appellant to carry out the piling works. The value of the sub-contract between the Appellant and the Respondent is stated as RM10,041,468.61. [5] Embassy Court Sdn. Bhd. then failed to make payment of monies due and owing to the Respondent and this resulted in the Respondent terminating the contract with Embassy Court Sdn. Bhd. on 20.01.2007. The Respondent, subsequently proceeded to issue notice to the Appellant informing the latter of the determination of the sub-contract work. That notice dated 20.01.2007, contained, among others, the following: - “We refer to the above sub-contract and the meeting held in our office today when we informed you that we have today exercised our right under the main contract to terminate our employment under the contract following a breach by the employer in failing to pay amounts due under interim payment certificates. Pursuant to Clause 29 of the sub-contract your employment under the sub-contract is automatically determined as a consequence of our employment being terminated under the main contract.” [6] The Appellant, aggrieved with the non-payment of what it alleged as the amount due under the sub-contract work, filed a claim against the Respondent, vide Kuala Lumpur High Court No. S-22-530-2009 claiming their entitlement for the works done up to termination. That proceeding, was however stayed pending arbitration proceeding between Embassy Court Sdn. Bhd. and the Respondent. 4 [7] Subsequently, the Respondent succeeded in the arbitration proceeding and was awarded a sum RM18,718,966.28 on 03.12.2012. [8] Premised on the arbitration award, the Appellant and the Respondent negotiated and agreed that the Appellant will be paid a sum of RM6,121,660.34 and a Compromise Agreement dated 15.02.2012 was signed. The parties then signed a Settlement Agreement on 03.07.2012 on similar terms as the Compromise Agreement. [9] Subsequently, Embassy Court Sdn. Bhd. and its holding company, Magna Prima Berhad and Respondent entered into a consent judgment, and it was agreed that a sum of RM16,000,000.00 was payable to the Respondent by Embassy Court Sdn. Bhd. This, in effect, reduced the sum payable to the Respondent under the arbitration award. It must be mentioned too that in the consent judgment the agreed sum was to be paid by instalment. [10] The Appellant therefore claimed a sum of RM5,232,000.00