Schedule
Schedule 4 of the Agreement. The relevant meaning and definition of the terms in Section 2.1 of the Agreement are as follows: (i) “Deliverables” mean the Equipment and/or Software including all or any IT design document/infrastructure to be supplied or delivered by Meridian to EXIM Bank from time to time in modular form in accordance with each required Modules and/or as described/specified in Schedule 2; (ii) “Charges” mean the charges for the provision of the Deliverables as set out in Schedule 4; and (iii) The “Contract Sum” means RM10,793,000.00, being the price of the Deliverables inclusive of 6% service tax. S/N brP2bvEvYU2TnkpwAs3A 28. The Defendant has paid a total of RM 2,163,230.00 to Meridian for all work successfully completed and signed off by the Defendant prior to the termination of the Agreement. 29. All of these payments were made in accordance with Sections 9.1.1 and 9.1.2 of the Agreement which, among others, require EXIM Bank to pay the Charges to Meridian upon receipt of a duly signed progressive Certificate of Acceptance and based on the payment milestones set out in Schedule 4 of the Agreement as follows: Work Completed and Signed Off Item and Agreed Amount in Schedule 4 Invoice Issued by Meridian Amount Paid by EXIM - Item A (1) – Upon Signing of Agreement (RM393,750.00) Invoice No. 0000613 dated 21.3.2019 (B2, p. 169) RM393,750.00 Completion of Requirement Study Item A (2) – Completion of Requirement Study (RM1,230,480.00) Invoice No. 0000614 dated 8.7.2019 (B2, p.168) RM1,230,480.00 Delivery of Third-Party Hardware / Software Item B (1) – Upon Delivery (RM161,700.00) Invoice No. 0000618 dated 30.9.2019 (B2, p. 167) RM161,700.00 Installation of Third-Party Hardware / Software Item B (2) – Upon Installation Sign-Off (RM377,300.00) Invoice No. 0000619 dated 14.10.2019 (B2, p. 166) RM377,300.00 Total RM2,163,230.00 S/N brP2bvEvYU2TnkpwAs3A 30. The Court is of the considered view that the weekly reports reflect actual progress as the Agreement required the Plaintiff to provide weekly and monthly reports throughout the duration of the Project as provided in Section 10.2.6 and Section 11.1.25 of the Agreement (B2 p. 27 & 30) as follows: “10.2.6 prepare and submit monthly project status reports to the Bank’s Project Manager; 11.1.25 the supplier shall provide or otherwise submit periodic progress report every two (2) weeks and monthly reports on or before the 5th of each of the following month or as and when required by the Bank following the implementation/roll-out of the Islamic Banking System under the Deliverables.” 31. The Project was governed by a committee known as the IT Steering Committee under the Project Management Office”. This Committee was the highest-level body overseeing the Project. The Steering Committee itself referred to the Plaintiff’s weekly progress reports. DW1 admitted that the Steering Committee refer to the weekly reports submitted by the Plaintiff. (Notes of Evidence pp. 286 & 287). The Plaintiff refers to the statement of PW2 (Notes of Evidence p. 89) as follows: “HA: Adakah Encik Shaharuddin tahu apakah dokumen yang digunakan atau dibuat rujukan oleh committee ini? S/N brP2bvEvYU2TnkpwAs3A PW2: Saya… Sekiranya dokumen itu dating daripada kami dan hanya saya percaya datangnya daripada weekly report yang kita hantar kerana tiada dokumen lain yang kami hantar sebagai progress report. Effect of Termination of Agreement 32. The Defendant had unilaterally terminated the Agreement for the Project by letter dated 2.12.2019 (B2 p. 155). The termination of the Project prevented the Plaintiff from proceeding with the system walkthrough and user acceptance testing. The system walkthrough was postponed with the note “Postponed until further notice from PMO.” (B2 p. 404) The Plaintiff submits (para. 61) that it was due to the postponement that the Plaintiff was unable to obtain the Certificates of Completion for the work completed. (see Evidence of PW2 in the Notes of Evidence p. 146) Whether the termination of the Agreement by the Defendant is valid based on Section 16.3 of the Agreement? 33. The Defendant had breached the Supply and Service Level Agreement dated 19.3.2019 by issuing a Termination Notice dated 2.12.2019. The Defendant unilaterally and wrongfully terminated the Agreement without obtaining the Plaintiff’s prior consent regarding Section 16.3 of the Agreement pertains to a termination by mutual agreement and that no reason was S/N brP2bvEvYU2TnkpwAs3A given. (paras. 85 & 86 Plaintiff’s submission). Section 16.3 clearly contains the sub-heading “Mutual Termination by Notice” indicating that any termination under this Clause (section) must be based on mutual consent. 34. Sections 16.1 and 16.2 of the Agreement expressly list the specific grounds and/or circumstances under which either party may terminate the Agreement. The Court is inclined to agree with the submissions of the Plaintiff that if Clause 16.3 were to be interpreted as allowing either party to issue a termination notice without providing any reason and without mutual consent, it would render Section 16.1 of the Agreement nugatory and without legal effect. 35. Needless to say, the provision in respect of “Termination” (Article XVI) Section 16 (Events of Termination) in Section 16.1.2.1 and Section 16.3 (Mutual termination by notice) prescribe different procedures for termination and cannot operate concurrently in the same set of circumstances. 36. Specifically, if Section 16.3 is interpreted as allowing unilateral termination without cause and without affording any opportunity for remedy, it would, in effect, negate the entire purpose and effect of Section 16.1.2.1, which provides a remedy period for the defaulting party. As a result, the protection afforded by Section S/N brP2bvEvYU2TnkpwAs3A 16.1.2.1 to the alleged breaching party would become entirely meaningless. 37. The sub heading in the said Agreement may not be considered a provision in itself. However, the sub heading can assist the Court in assessing and determining the true interpretation or actual intention of the provisions within the Agreement. Sanctity of a contract 38. It is trite law that the sanctity of a contract should be preserved. As decided in Tay Yew Chong v. Koh Hooi Siang & Ors [2021] 1 CLJ 221 at p. 233, the Court of Appeal decided as follows: “[33] It is elementary that in construing a contract, the whole contract has to be considered with reference to its object and the whole of its term (see Chitty on Contracts, vol. 2012, 31 edn. At p. 943) In SPM Membrane Switch Sdn. Bhd.v. Kerajaan Negeri Selangor [2016] 1 CLJ 177, the Federal Court held that the court must approach the interpretation of a contract holistically, no term is to be taken or interpreted in isolation. [34] The court cannot be rewriting the contract for the parties by imposing a term which could not be imported into the contract or go behind the written terms of the contract to introduce or add new terms to it.” S/N brP2bvEvYU2TnkpwAs3A 39. The Court’s role is not to rewrite the Agreement or improve upon its terms to make them fairer or more reasonable. When the terms of the Agreement are clear and unambiguous, the Court is duty bound to give effect to their ordinary meaning and must not impose any implied terms. (see Sumbangan Aneka, supra) 40. The construction of a contract is a question of law for determination by the court and not by the witnesses through their oral evidence. (see NVJ Menon v. The Great Eastern Life Assurance Company Ltd. [2004] 3 CLJ 96 Court of Appeal) 41. In the instant case, based on the construction of the Agreement, I am of the considered view that there lies no ambiguity as to the intention of the parties and that the contractual obligations of the parties were clearly spelt out in the terms and conditions of the Agreement (Section 16.3) in the instant case. It is a fundamental principle of contract law that parties are bound by the terms of the contract to which they have freely agreed, and that it is the contract alone which governs the relationship between the parties. (Tahan Steel Corp., supra) Where the terms of a contract are clear and free from ambiguity, the Court will not impose any implied terms. (see Seven Seas Industries Sdn. Bhd. v. Philips Electronic Supplies (M) Sdn. Bhd. & Anor. [2008] 5 MLJ 157 CA) S/N brP2bvEvYU2TnkpwAs3A Whether the Plaintiff is entitled to claim the remaining contract value of RM8,629,770.00 as compensation due to the termination by the Defendant? 42. The critical issue to be determined is whether the Plaintiff is entitled to claim the remaining payment amounting to RM8,629,770.00 as the Defendant has breached the Agreement by issuing a Termination Notice that lacked mutual consent and was made without providing any reasons. In this respect the Court finds that: (a) there was no breach committed by the Plaintiff throughout the Agreement; (b) there were no complaints raised by the Defendant preceding the Termination of the Agreement regarding the Plaintiff’s work on the project; and (c) the project implementation records (Weekly Status Report) demonstrated that the Plaintiff had performed its obligations satisfactorily without proof of breach of the said Agreement. S/N brP2bvEvYU2TnkpwAs3A 43. Since the unilateral termination dated 2.12.2019 was caused by reasons/actions attributable to the Defendant, did the Defendant commit constructive breach of contract? The Defendant cannot disable itself from performing a contract brought about by its own acts. (see Akitek Tenggara Sdn. Bhd. v. Mid Valley City Sdn. Bhd. [2007] 5 MLJ 697) 44. The Plaintiff submits that they are entitled to the amount claim at RM8,629,770.00 particularly given that 90% of the project work had been completed and the system developed by the Plaintiff was specifically tailored for the Defendant. (see PW2’s evidence in pp. 95 & 96 of the Notes of Evidence). Therefore, the claim of RM8,629,770.00 is disallowed. 45. Be that as it may, the Court hereby allows the calculation for the payment of 90% of the amount outstanding of the project work that completed as claimed by the Plaintiff to be calculated as follows: Contract sum: RM10,793,000.00 90% work done: RM9,713,700.00 minus Amount Paid: RM2,163,230.00 Outstanding Amount Allowed: RM7,550,470.00 S/N brP2bvEvYU2TnkpwAs3A Summary of Court’s analysis. 46. The Court hereby makes the following findings: (a) The termination of the Agreement by the Defendant was wrongful and/or invalid; (b) Payment of RM7,550,470.00 (being 90% of the amount outstanding) to paid to the Plaintiff by the Defendant as compensation; (c) Interest of 5% per annum from the date of judgment until full settlement; (d) Cost of RM30,000.00 to be paid (subject to allocatur) forthwith by the Defendant to the Plaintiff. Conclusion 47. In the circumstances, the Court finds that the Plaintiff has proven their claim on a balance of probabilities. Consequently, the Plaintiff’s claim in the Statement of Claim (Encl. 2) in paragraph 40 is hereby allowed subject to paragraph 46 (a) to (d) above. S/N brP2bvEvYU2TnkpwAs3A Decision 48. Based on the aforesaid reasons, the Plaintiff’s claim against the Defendant is allowed with costs of RM30,000.00 (subject to allocatur). Dated: 10 October 2025 sgd ………………………………………….. (EDDIE YEO SOON CHYE) Judicial Commissioner High Court of Malaya Kuala Lumpur Counsel for the Plaintiff: Dato’ Hazman bin Ahmad & Muhammad Irsyad bin Mohamad Hassan. Messrs. Omar Ismail Hazman & Co. Kuala Lumpur. Counsel for the Defendant: Manshan Singh, Ho Pui Yan & Chong Zheng Yang (PIC) Messrs. Skrine Kuala Lumpur. S/N brP2bvEvYU2TnkpwAs3A