If the defendant’s explanation was accepted, it would mean that the defendant was at liberty to file a statement of defence that did not disclose all the facts so that the proceedings could be delayed with an intention to amend the same later for his own personal motive. Further, there was no reasonable ground for the defendant to wait until the last moment before the hearing of the summary judgment application to amend although more than five months had lapsed since the application for summary judgment was served upon him (see pp 271H-272A). (emphasis added) 17 [26] The defendant had based its application on the ground that it had only just found out that the plaintiff's billing for the scaffolding installed was based on cubic meter ("m3") which was not in accordance, so it claims, with industry practice in Malaysia and that the charges are excessive. [27] The defendant further averred in its affidavit in support of the amendment application that it had discovered this information a few days before the commencement of the trial from a witness to be called for the Defence, one Mr Gunalan a/l Thanimalai. However the "Final Revised Quotation" from the plaintiff to the defendant dated 10 June 2014 clearly showed the quotation in cubic meter at page 103 of the Appeal Record ("AR"). Likewise the defendant's Purchase Order dated 11 June 2014 to the plaintiff also referred to the measurement of the scaffolding in terms of cubic meter. The plaintiff's invoices that had been in the possession of the defendant also showed cubic meter and some payments had already been made based on cubic meter. [28] The last case management was on 13 July 2015 and trial was initially fixed on 19 - 20 October 2015 and which taken off because defendant's counsel was taken ill. For the defendant to wait almost 5 months and then 18 to say that they had stumbled upon an important discovery of something amiss in the method of billing is stretching credibility to its limits. The late application with no reasonable explanation smacks of a lack of bona fides in making the application. [29] In Raphael Pura v. Insas Bhd & Anor [2000] 4 CLJ 830 the Court of Appeal underscored the importance of bona fides in applications for the amendment of defence in this wise: “As we are dealing with the application for the amendment of defence, question (1) [whether the application is bona fide] above would be relevant for consideration. This court similarly had considered O 20 r 5 in Taisho Co. Sdn Bhd v. Pan Global Equities Bhd [1999] 1 CLJ 703. In Taisho’s case, the amendments related to the statement of claim. Be that as it may, the question posed in Yamaha would still be equally applicable to the present appeal before us. If the application, on the facts before the learned judge, showed lack of bona fide then he fails in his application altogether.” (emphasis added) 19 [30] In dismissing a similar late application for amendment in the Hong Leong Finance Bhd's case (supra) the Federal Court observed as follows: [25] The Courts in Malaysia have consistently held that where there is a delay in making an amendment application, the onus is on the applicant to furnish a reasonable explanation for such a delay. They seem to have considered this as an additional factor to the Yamaha Motor's rules. The need to show 'some material and advance some cogent reasons' was applied in Taisho Co Sdn Bhd v Pan Global Equities Bhd & Anor [1999] 1 MLJ 359; [1999] 1 CLJ 703, Haidar JCA (as he then was) held: The learned judge intimated that the application was made after the appellant failed on appeal to this court to affirm the judgment entered by it initially. Further, he said that the appellant had knowledge of the 'acknowledgement' as late as April 1987, that is, four years before the action was filed. Furthermore, the application was filed four years after the commencement of this action. We would add further that no reasons were given for the delay in filing the application when the point of admission was obviously available even before 20 filing the proceedings. As rightly opined by the learned JC in Multi-Pak Singapore Pte Ltd and correctly followed by the learned judge, the appellant did not place some material and advance some cogent reasons to impel the court to lean on its side. We would further add that the application borders on lack of bona fides, one of the basic question set out in Yamaha Motor Co Ltd. (emphasis added.) [31] The requirement to advance some material and cogent reasons was likewise followed in the subsequent decisions in the cases of Raphael Pura v Insas Bhd & Anor [2001] 1 MLJ 49; [2000] 4 CLJ 830 and Everise Hectares Sdn Bhd v Citibank Berhad [2010] MLJU 1379 ; [2011] 2 CLJ 25: [26] It is to be stated here the requirement that a cogent explanation for such a delay must be furnished when making a late application to amend would be clearly in line with pre-trial case management procedures (introduced in year 2000). The management of cases by the courts prior to the trial is intended to ensure 'just, expeditious and economical disposal' of an action (see O 34 r 4(1) of the RHC 1980, now O 34 r 1(1) of the RC 2012) and the Practice Direction No 2 of 2014 issued by the Chief Judge of High Court in Malaya). Timely 21 disposal of cases and the limitation of cost are now the primary considerations under the present regime. [27] In our instant case, there had been five case managements since 2011 and there was no indication at all that an amendment application was contemplated by the defendant. The only explanation given by the defendant in his affidavit for the delay was that he had only discovered that these new issues were not pleaded when preparing for trial. Such an explanation in our view surely cannot be acceptable." (emphasis added) [32] Based on this ground of undue delay which has not been reasonably explained, the defendant's late application after trial had commenced should stand dismissed. Whether the late application to amend by the defendant would prejudice the plaintiff [33] The late proposed amendments that made reference to what is industry practice would entail the calling of expert witness to testify. The need to call an expert witness should have been disclosed to th SCJ at the 22 stage of case management for there specific directions that should be given under the Rules of Court 2012 where expert evidence is envisaged, all with a view to securing the just, expeditious and economical disposal of the proceedings. [34] Under O 34 r 2(2)(p), (q) and (r), with respect to the directions that a Judge may make on a Pre-Trial Case Management where expert witnesses may be called, it is provided as follows: "(2) At a pre-trial case management, the Court may consider any matter including the possibility of settlement of all or any of the issues in the action or proceedings and require the parties to furnish the Court with such information as it thinks fit, and the appropriate orders and directions that should be made to secure the just, expeditious and economical disposal of the action or proceedings, including- ...