(iii) The court too had raised an issue as to why MPM, the defendant did not see it fit to lodge a claim for compensation from the owner of the project, Unifortune Holding Sdn Bhd, if at all there has been a delay by the plaintiff to complete its part of the works. Contention of the defendant [9] The defendant stood its ground to state that there was no money owing to the plaintiff based on the aforesaid three factors, namely: defective work; omission of work; and delay. These were woven by the defendant to form an interplay of circumstances which worked against the plaintiff, KKEE. [10] It claimed that the SCJ had erred on the issue as to omission of works. Reference is made to clause 11.1 of the Letter of Award that 8 stated changes in the design amounted to variation. As such, due to the variation, there was no reason for the plaintiff to be entitled to the whole contract sum. [11] Apparently, the defendant had informed the plaintiff of the omission of work, at the time when the final accounts were prepared. However, the plaintiff had requested for a detailed list from the defendant, which resulted in the defendant consulting a third party to prepare a list with reference to the technical report. From here, it was calculated that the omission works costs RM400,000.00 [12] The core of the matter was that the defendant claimed it was entitled to claim for omission of works resulting in cost reduction. The cost of the omission of works amounted to RM386,256.21. The defendant states the SCJ had the incorrect perspective on the shop/built and tender drawings when considering that the actual work done would be different from the initial design or drawing, and that changing the drawing would actually reduce the total contract value. There were also claims made by the defendant that a lump sum contract did not necessarily mean that a contractor would receive the same amount of money on completion of work, as there would be adjustments made such as extra work, fluctuations with sub-contractors etc. 9 [13] The defendant further argued that it was entitled to claim for LAD if the project was delayed as per Clause 9 of the Letter of Award. It went on to say that the project was delayed for a total of 60 days, which amounted to RM154,000.00 or 5% of the contract sum. [14] Added to the conundrum was the defective work in the project. The defendant alleged the plaintiff refused to carry out the repairs that amounted to RM35,000.00. To support this, the defendant affirmed that the plaintiff did not deny these works remain unrectified. [15] On claim for LAD, it defended itself by stating that the SCJ erred as it was the plaintiff that should prove the amount of damage was unreasonable, but it had failed to do so. Conversely, it pointed out that delay had been proven and it was not refuted by the plaintiff as evidenced by its weekly minutes. This according to the defendant, could be considered as breach of contract. [16] Further on the issue of LAD, the defendant submits if a reasonable compensation could be worked out, so that there is no large difference between level of damages as in the contract compared to actual damages suffered. [17] At this stage of the narrative, a poser which has to be cleared is on the issuance of Certificate of Practical Completion which was never given to KKEE. It could be surmised that, probably MPM held on to 10 it to somehow justify the delay, omission and defective work plot. However, the mantle of the case is, MPM, the defendant refused to pay plaintiff the remaining progressive payment of RM107,993.05. albeit many reminders, including a final meeting where both parties met to finalise their accounts and no payment was forthcoming. Principles of law [18] After referring to cases on Building Contract Litigation like, CM Indah Sdn. Bhd. v UB Usahabina Sdn. Bhd (2006) MLJU 426; Ohbayashi-Gumi Ltd v Kian Hong Holdings Pt. Ltd. (1987) 2 MLJ 110; CS International Design Consortium Sdn. Bhd. v HSB Development Sdn. Bhd. (2014) 11 MLJ 751, it is submitted by counsel for defendant that the total value of contract sum has to be reduced when there is omission of works due to alteration of design, and such a reduction is permitted under the contract and the law. [19] Counsel for defendant/appellant had misread those authorities. In those cases, it was decided that in ordinary lump sum contracts (like the present case) the contractor is entitled to be paid the pre-agreed lump sum as and when he substantially complete the works. It was further decided that substantial completion does not necessarily entail the perfect execution of every detail of the works, and if the contractor is guilty of only comparatively minor defects and/or 11 omissions then he is entitled to be paid the lump sum less a set-off in respect of his failings. In fact, this has been advanced by the defendant, that there are in fact omission of works. Surely, this principle of building construction law is subject to law of evidence wherein, the omission of works has to be proven by the defendant on a balance of probabilities. This is so pursuant to section 103 of the Evidence Act 1950 (EA; Act 56) which renders that burden of proof as to any particular fact lies on that person who wishes the court to believe in its existence, unless it is provided by any law that the proof of that fact shall lie on any particular person. In the absence of any such legal provision, the burden of proof in the present case, rests on the defendant to prove there are omission of works decided by the defendant at the outset. As omission of works is pleaded as a counter claim against the plaintiff, the defendant has to prove of its existence on a balance of probabilities, otherwise the law does not entitle the defendant to such a claim. [20] Is there such proof by the defendant? The answer lies in the finding of fact made by the SCJ, who had the advantage of audible evidence from witnesses both for plaintiff and defendant. He had arrived at the finding of fact after carefully combing through oral and documentary evidence proffered in the case. 12 [21] On omission of works, defendant claims that it is entitled to an amount of RM386,256.21. It is premised on clause 20(b) of the Letter of Acceptance between the plaintiff and defendant before the building contract of works commenced. Clause 20(b) is explicit, when it provides – “The Project Manager reserves the right to omit any part of the works and omission will be deducted from your contract accordingly. You shall not be entitled to claim for any loss and expenses as a result of the omission.” [22] With regard to claim for omission of works by the defendant, the following had transpired –