that the Final Award is in conflict with the public policy of Malaysia because it was given in breach of rules of natural justice both during the Arbitral proceeding and/or in connection with making of the Final Award in, inter alia, the following respects:- a) there were ex parte communications that took place between the Defendant and the Arbitrator in close proximity with and prior to the issuance of the Final Award; b) the appointed Secretary of the Arbitrator acted beyond the administrative scope and/or role that was consented to by the parties; c) there were further irregularities in the conduct of the arbitration proceedings including, inter alia, distasteful remark issued by the Arbitrator; d) the Arbitrator awarded interest on several of the Defendant’s claim without sufficient legal justification and/or basis to wit, there was no explanation on the nature of the interest imposed, the basis of the S/N K7w0BfBrJUOxcbcfcJYumg imposition of the interest and the basis upon which specific dates were taken to be the commencement date for the calculation of such interest without inviting the parties to address these issues; e) the Arbitrator further took into consideration entirely irrelevant matters in making his decision including evidence that was only tendered by the Defendant after the close of evidence during submission stage; f) the Arbitrator also failed to consider arguments that were raised by the Plaintiff throughout the Final Award; and g) the Arbitrator, on his own frolic, changed the completion date of the construction contract between the parties without giving the parties the opportunity to object or address the same. ii. these matters clearly had a material impact and/or causative effect in the Learned Arbitrator’s decision-making process which resulted in the Learned Arbitrator dismissing the Plaintiff’s counterclaim and allowing the Defendant’s claim. iii. the Learned Arbitrator had failed to properly assess the available evidence; S/N K7w0BfBrJUOxcbcfcJYumg iv. the Plaintiff has met the statutory requirements under Sections 37(1)(a) and (b), Sections 37(2)(b)(i) and 37(2)(b)(ii), 37(6) and Section 50 of the Arbitration Act 2005 as well as Orders 5, 7, 28, 69 and 92 Rule 4 of the Rules of Court 2012. [3] There is also before this Court an application by the Plaintiff under enclosure 2 that the enforcement of the Award be stayed pending determination and disposal of Enclosure 1. Brief Factual Background [4] Briefly, MRCB Builders Sdn Bhd, the Plaintif, appointed the Defendant, AFS Engineering Sdn Bhd, for the design, supply, delivery, installation, upgrading, testing and commissioning of the Public Address System (“PA System”) at the National Sports Complex at Bukit Jalil, Kuala Lumpur (“the Works”). [5] During the Defects Liability Period, the Defendant failed, refused and/or neglected to rectify defects that were identified by the Plaintiff. [6] As a result, the Plaintiff terminated the contract with the Defendant on 11.2.2020 and made a call on the Defendant’s Performance Bond on 19.2.2020. [7] The Defendant attempted to injunct the Plaintiff’s call on the Performance Bond. However, the Defendant was unsuccessful in the first instance at the Hight Court and on appeal at the Court of Appeal, the Court of Appeal found that the call on the Performance Bond was S/N K7w0BfBrJUOxcbcfcJYumg not unconscionable. On 6.7.2020, the sums under the Performance Bond were disbursed to the Plaintiff. [8] The Defendant then commenced arbitration against the Plaintiff. In turn, the Plaintiff mounted a counterclaim against the Defendant. [9] On 14.12.2024, the Arbitrator allowed the Defendant’s claim and dismissed the Plaintiff’s counterclaim against the Defendant. Hence, the Defendant filed the Setting Aside Application and the Stay Application herein. [10] At the arbitration proceedings, the Defendant claimed for the following reliefs:-