After the KMK was cancelled on 8-6-2022, a second KMK was issued on 22.06.2022 with a new time line for the HDD works to commence on 22.06.2022 and complete on 22.07.2022. [27] The Defendant gave the Undertaking on 27-6-2022. Based on the HDD works finally commenced on 4-7-2022 and completed on 30-9-2022. Cabling works which were delayed between 4- 11-2022 and 14-11-2022, were finally completed by TNB by the end of December 2022. Using these dates, the delay periods directly occasioned 5 days (30-5-2022 to 4-7-2022) and 10 days (4-11-2022 to 14-11-2022). [28] with its main contractor, Phase 3 of TMM was supposed to complete by 8-5-2022 before any issue with the HDD works arose, proving that the project was already delayed for reasons unrelated to the Defendant. However, the Plaintiff asserted without a delay analysis on the alleged consequential effects of the 45-day delay such as the encountering of inclement weather, that there was a total of 6-month delay until the Certificate of Compliance and Completion ( ) for Phase 3 of TMM was achieved on 31-3-2023. [29] The Plaintiff therefore attributed the 6-month delay wholly to the claimed the following heads of damage: Description Amount (RM) V.O. claimed by HDD contractor, Novel Utility Sdn Bhd 220,520.00 Losses suffered due the increase in premix prices as per the Variation Orders submitted by premix road Work contractor, Kah Seang Construction 79,073.28 LAD claim by the 2 units of Shoplot 63,956.99 Waiver of late payment charges in respect of the 16 units of property purchased by API Hightech Sdn Bhd 580,983.91 Additional 6 months office overheads/ staff salaries 195,300.00 [30] The nature of these claims being capable of specific quantification, they are special damages that ought to have been particularised and must in any case be specifically proved. Evidence of such damages was nevertheless led at the trial without objection and dealt with in some detail. Apart from the question of proof about the underlying premise for attributing 6 months o considered the recoverability of each head of loss and the proof of quantum offered. Variation Order Novel Utility Sdn Bhd [31] The Plaintiff would have been entitled to recover idling and mobilization/demobilization costs for the incidents on 30-5-2022 and 1-6- 2022 and 2-6-2022, but the proof of loss claimed was questionable. [32] According to the Plaintiff, the contract value for HDD works carried out by Novel Utility Sdn Bhd as the HDD contractor was RM445,200.00 based on the contract between OIB Construction Sdn Bhd and Novel Utility Sdn Bhd and the claims totalling RM220,520.00 represented the value of variation orders caused by the delay. [33] However, this Court noted that contract was not adduced in evidence and there is accordingly no corroborating evidence for what is said to be the original contract sum. The Defendant also highlighted that the TNB approved HDD contractor was Muara Perkasa Sdn Bhd, not Novel Utility Sdn Bhd. [34] In any case The Plaintiff produced progress claim invoices and related documents, but these indicated that the Contract Value including V.O. Work was RM239,100.00 and that RM220,520.00 represented 92.23% of the Contract Value as shown: [35] There is no description of the variation order that the invoice related to. In construction, delays do not ordinarily result in a variation if the same work is required to be done. There were no delay notifications, description of delay costs claims and essentially no supporting documents ordinarily available to support a variation order caused by mobilization and demobilization and idling of machinery due to delays. There was also no evidence of payment of said RM220,520.00 by the Plaintiff to OIB Construction Sdn Bhd. Increase in Premix price Kah Seang Construction [36] The Plaintiff would also have been entitled to recover the additional cost of premix paid for work in December 2022 as opposed to July 2022 if it could be proved that such cost differentials were actually suffered. The proof of loss claimed on this head was however, also questionable. [37] The Plaintiff produced various claims by Kah Seang Construction and in particular, what appears to be progress payment 3/8431 dated 12- 5-2023 by OIB Construction Sdn Bhd to Kah Seang Construction for the sum of RM79,073.28. The Plaintiff claims that this is the additional cost of premix between 2022 and 2023 that OIB Construction Sdn Bhd had to pay and attributed this to the Defendant for the delay in the HDD works because post-HDD and cabling, parts of Jalan MM2 presumably required resurfacing. [38] However, the description of the 12-5-2023 invoice relied on by the Plaintiff Phase 3 progress claim no.3 Infra (External Works)/Road - Premix VO, Supply and install for Road Premix Works for Road Extension The description bore no resemblance to HDD road resurfacing and it was not explained how this proved that premix cost had increased by RM79,073.28 between 2022 and 2023. [39] As with the payment to Novel Utility Sdn Bhd claimed by the Plaintiff, the contract between OIB Construction Sdn Bhd and Kah Seang Construction was not adduced in evidence and contrary to the evidence given by the Plaintiff, the Contract Value including V.O. Work for Kah Supply & Install for Road Premix Works for Road Extension to Neighbourhood Land and RM79,073.28 represented 98.78% of that Contract Value as shown: [40] If the sum RM79,073.28 represented the increase in premix price between 2022 and 2023 that borne by the Plaintiff, this Court would have expected to see clearer documentary evidence. There were no premix quotations, bills of quantities with measurements showing the rates and the quantities for the HDD related road resurfacing work done. There were also no evidence that the sum RM79,073.28 was paid by the Plaintiff to OIB Construction Sdn Bhd. LAD payments to purchasers [41] The Plaintiff computed contractual LAD payable to the purchasers based on the sale and purchase agreements adduced for 2 purchasers on the basis of a 6-month delay. For this head of loss, the quantification is straightforward but there was no proof of payment of any LAD to these purchasers. Waiver of late payment interest [42] According to the Plaintiff and a witness appearing on behalf of API Hightech Sdn Bhd (PW-5), they entered into bulk sale and purchase agreements for the remaining 16 units of shoplots on 28-2-2022, based that it would endeavor to deliver vacant possession by 30-9-2022. [43] Apparently, API Hightech Sdn Bhd did not pay the balance purchase price in response to the delay in delivery of vacant possession and the Plaintiff agreed to waive late payment interest amounting to RM580,983.91 as a set off for compensation said to be payable to API Hightech Sdn Bhd for the delay in delivery of vacant possession. [44] The Defendant argued that the Plaintiff had departed from the terms of the sale and purchase agreements which stipulated for vacant possession to be delivered by 28-2-2024 and not 30-9-2022. There was accordingly no legal basis for API Hightech Sdn Bhd to delay payment of the balance purchase price or claim compensation. Considering all this, this Court finds that this head of damage is not reasonably foreseeable and cannot be recovered. Additional Staff Salaries [45] The Plaintiff claims 6 Months Office Overheads/Staff Salaries amounting to RM195,300.00. The Defendant submitted and the Court agrees that there was no evidence direct or exclusive assignment to the Phase 3 and like the other heads of loss, were not proved to be losses of the Plaintiff since the staff were paid by OIB Construction Sdn Bhd. [46] In the final analysis, the Court was not satisfied with: