other than the above defects, the other defects and rectification works had been examined by the learned SCj, where both Plaintiff and Defendant had argued regarding the roller shutter, Switch Socket Outlet (SSO) control, Crestron keypads, motorized projector screen, overloading and poor termination of power cables, excessive data cables length, dumpster diving risk, alarm and control system, curtain control system, lighting control system, TV control and AV distribution system, and general cabling work. The High Court’s decision [37] The learned counsel for the Plaintiff has laid out the summary of the evidences in the table format as attached in Appendixes A and B. This Court also finds that the learned SCj did studied the evidences after hearing the trial. [38] LAW OF EVIDENCE: “HE WHO CLAIMS, PROVES”: the fundamental principle of the law of evidence is that the burden of proving a fact is on the person claiming the existence of that said fact, except where it is stipulated by any law that the proof of that fact lies on another person. [39] This evidentiary principle of “he who claims, proves” is entrenched in the Evidence Act 1950. Sections 101, 102 and 103 of the Evidence Act 1950. [40] The Court of Appeal in Poratha Corporation Sdn Bhd v. Technofit Sdn Bhd [2018] AMEJ 0214 [2019] 1 LNS 941; [2020] 1 MLJ 74, reiterated this principle. It held that the party claiming damages bears the burden of proving the fact and the quantum of the damages suffered and that if the claimant only succeeds in proving the fact and not the quantum, it will only be entitled to nominal damages. Y.A Hasnah Hashim JCA (as she then was) in delivering the decision of the Court of Appeal held – “[44] It is trite law that the party claiming damages bears the burden of proving the fact and quantum of damages suffered. [45] The defendant bears the burden of proving both the fact and the amount of damages suffered as a result of the breach by the plaintiff. Special damages unlike general damages must be specifically pleaded and strictly proved, and recoverable only where they can be included in the proper measure of damages …”. [41] In Chang Hang Guan & Ors. v. Perumahan Falim (Penang) Sdn Bhd [1994] 1 CLJ 19, Edgar Joseph Jr held− “When a plaintiff claims damages from a defendant, he has to show that the loss in respect of which he claims damages was caused by the defendant’s wrong and also that the damages are not too remote to be recoverable. Where precise evidence is obtainable, the court naturally expects to have it, where it is not, the court must do the best it can. General difficulty of proof does not dispense with the necessity for proof.”. [42] In arriving to the decision, the delay in finishing and completing the works was proven by the Plaintiff. I agree. This Court should and never will interfere with this finding. [43] Now, to answer whether the findings by the learned SCj that the Defendant is liable and next on the awarding of the damages by the learned SCj is correct? [44] The Defendant in this appeal said that the learned SCj has made an error in finding that the Defendant is liable because the following facts are the Plaintiff’s faults – Dates Incidents 24-10-2016 • the Plaintiff made the payment of 35% down payment based on the BOQ Form. • from 24.10.2016 to the end of March 2017, the brick walls for the Bungalow were still being built and therefore, the Defendant was not able to commence the hacking for wiring works purposes. 10-4-2017 • the Bungalow was not ready for the Appellant to commence the wiring works. • only on 10-4-2017 the hacking works for purposes of wiring at the basement and ground floor was commenced by the Defendant. • 1st floor and 2nd floor of the bungalow was not ready for the Defendant to commence the hacking works for wiring purposes. the electrical contractor was still installing the electrical trunking and riser. The Appellant will only be able to complete the wiring works after the completion of installation of trunking and riser by the electrical contractor. Dates Incidents pursuant to the Plaintiff’s instructions, additional/variation works were required where there were a total of 4 Variation Orders/VO. Further wiring works were required pursuant to the VO. Before early March 2018 • the Bungalow was not ready for the Defendant to commence equipment delivery and installation because the flooring, internal painting, plaster ceiling, windows and doors and other fixtures were still being installed or pending installation. • furthermore, there was a security issue whereby the Bungalow was exposed (there were no doors or gates) hence the equipment could not be delivered for fear of theft and/or damage. between 12-3-2018 and 7-8-2018, the Appellant had delivered and installed the equipment in batches, depending on the readiness of the Bungalow for such delivery and installation. 31-7-2018 at 8.00pm • the Respondent for the first time unilaterally informed the Appellant that he intended to move into the Bungalow by 03.08.2018. The Appellant stressed that at all material times, no such deadline was agreed between the parties. • at all material times, the Respondent was aware that the Smart Home System, including the security system and control system, will not be ready and delivered by 3-8-2018. Dates Incidents 6-8-2018 7-8-2018 Meetings: • during the meeting, Mr. Eric Goh and SD2 then informed the Plaintiff that the Defendant was willing to give the Plaintiff, a goodwill discount of RM20,000.00 or 5% of the total project sum, whichever is higher, which would be offset from the amount due from the Plaintiff after the handover of the Smart Home System. This offer was made on a without prejudice and without admission of liability basis. However, the Plaintiff demanded for more discount. • in another meeting, Mr. Eric Goh thereafter informed the Plaintiff that the Defendant was willing to give the Plaintiff a goodwill discount amounting to 10% of the total project sum which would be offset from the amount due from the Plaintiff after the handover of the Smart Home System. This offer was also made on a without prejudice and without admission of liability basis. However, the Plaintiff disagreed and demanded for more discount. • at about 12.00p.m., SD2 and SD3 were at the Bungalow to inform the Plaintiff that the Defendant was only willing to offer a 10% goodwill discount. Upon being informed of this, the Plaintiff ordered the Defendant’s team to stop all work, pack all tools and leave the bungalow immediately. The Plaintiff had further threatened, among other threats, that the Plaintiff will sabotage the Defendant’s business and trade and that the Plaintiff would Dates Incidents cause the Immigration Department of Malaysia to prevent SD1 from leaving Malaysia. • the Defendant was prevented from performing the Defendant’s obligation under the terms of the BOQ Form and the VO. • as of 7-8-2018, the Defendant was in the final stages of configuration, testing, troubleshooting (if necessary) and commissioning of the Smart Home System. This includes testing all connectivity and performing termination for all of the relevant installed hardware. • however, pursuant to the Plaintiff’s stop work order on 7-8-2018, the Defendant was prevented from completing the said project and have since also not received any consent from the Plaintiff to re-enter the premises to complete the works, with exception to a meeting on 10.08.2018 with Crestron on which day, no consent was given to continue work. 30-8-2018 the Defendant’s solicitors proposed to the Plaintiff a proper handover of the project to a new system integrator since the parties’ relationship broke down, and again there was also no response from the Plaintiff regarding this matter. 28-9-2018 consequent to the delayed construction project, the Defendant estimated that the Smart Home System could only be completed by 28-9-2018. [45] In paragraph 52 of the written submission, the learned counsel for the Defendant submits that – “52. The Appellant (Defendant) has received a total sum of RM423,137.18 from the Respondent (Plaintiff). The actual value of completed works for the Smart Home System, is estimated by the Appellant (Defendant) to be RM395,953.38 which amounts to 89.99% to the total value of contracted works (including Variation Orders). However, the payment terms agreed between the parties are not based on the value of works performed but on milestones achieved. To date, the Appellant (Defendant) has surpassed 95 percent (%) completion of milestones achieved and hence, the Appellant (Defendant) is entitled to retain all amounts previously paid by the Respondent (Plaintiff). The Respondent (Plaintiff) also has not returned to the Appellant (Defendant) any of the alleged defective and unnecessary items and/or materials. This contradicts the facts given by the Respondent (Plaintiff).”. [46] Paragraph 174 to 206 in the learned SCj’s grounds of judgment, he stated the application of the law to the fact. The learned SCj starts its reasons as follows: “174. The law on damages for breach of contract is trite. the law on damages is set out in s. 74 of the Contract Act 1950. Pursuant to the provision, compensation can only be awarded against the guilty party for breach of contract if the loss or damage suffered by the other party satisfies two conditions.