13.3 Time “Time shall be of the essence as regards to the provisions of this Agreement, both as regards the times and periods mentioned herein and regards any times or periods which may, by agreement between the Party, be substituted for them.” ALASAN PENGHAKIMAN NA-22NCVC-54-11/2021 11 [21] Oleh itu, berdasarkan kepada Klausa (1) Perjanjian “SA” tersebut adalah jelas bahawa Pembangunan tersebut mesti disiapkan dalam tempoh lima (5) tahun daripada tarikh Perjanjian “JVA” tersebut iaitu pada atau sebelum 5.6.2012. [22] Fakta berkenaan tempoh untuk menyiapkan Pembangunan tersebut dalam tempoh masa lima (5) tahun telah diakui dan disahkan oleh kedua-dua orang saksi Plaintif iaitu Dato’ Azizul Rahman bin Abd Samad (SP-1) dan Encik Abd Ghafar bin Abd Samat (SP-2) dan juga oleh saksi Defendan sendiri iaitu Dato’ Mohd Azman bin Ahmad (SD-1). [23] Dalam lain perkataan, Pembangunan tersebut harus disiapkan dalam tempoh lima (5) tahun daripada tarikh Perjanjian “JVA” tersebut dimasuki iaitu dari 5.6.2007 sehingga 5.6.2012 dan ianya bukan merupakan suatu isu yang harus dipertikaikan dalam kes ini. [24] Walaubagaimanapun, berdasarkan kepada keterangan-keterangan dan bukti-bukti yang telah dikemukakan kepada Mahkamah adalah jelas terbukti bahawa Defendan bukan sahaja gagal untuk ALASAN PENGHAKIMAN NA-22NCVC-54-11/2021 12 menyiapkan pembinaan tersebut, malahan Defendan langsung tidak ada membina apa-apa struktur di atas hartanah tersebut walaupun setelah Perjanjian “JVA” tersebut telah tamat atau pun telah luput tempohnya pada bulan Jun tahun 2012. [25] Fakta berkenaan dengan kegagalan Defendan untuk membina sebarang struktur di atas hartanah tersebut telah dibuktikan melalui gambar-gambar yang telah diambil oleh Plaintif pada 1.7.2016 sebagaimana yang terdapat dari Mukasurat 111 hingga Mukasurat 120, Trial Documents (Lampiran - 60). [26] Begitu juga, di dalam keterangan yang telah diberikan oleh saksi Defendan sendiri kepada Mahkamah iaitu Dato’ Mohd Azman bin Ahmad (SD-1), SD-1 mengakui dan mengesahkan bahawa tidak ada apa-apa kerja yang telah dijalankan atau yang telah dilaksanakan di atas hartanah tersebut setakat pada tahun 2016. [27] Oleh itu, berdasarkan kepada keterangan dan pengakuan yang diberikan oleh saksi Defendan sendiri, adalah jelas terbukti bahawa Defendan telah gagal untuk menyiapkan Pembangunan tersebut ALASAN PENGHAKIMAN NA-22NCVC-54-11/2021 13 dalam tempoh masa lima (5) tahun daripada tarikh Perjanjian “JVA” tersebut dimasuki. Dalam erti kata yang lain, tingkah laku atau tindak tanduk serta keingkaran Defendan ini adalah boleh dianggap atau pun terjumlah kepada pemecahan atau perlanggaran terhadap perkara asas kepada Perjanjian “JVA” dan Perjanjian “SA” tersebut. [28] Di dalam kes Sik Hong Photo Sdn Bhd lwn Ch’ng Beng Choo [2010] 5 CLJ 427, Mahkamah Rayuan telah memutuskan seperti berikut:- [27] Under the SPA, the defendant has the contractual obligation to perform ie, to transfer the shares to Madam Ng on or before 31 December 1980. The defendant’s non-performance of that obligation struck at the very root, foundation or substratum of the SPA. The transfer of the consideration is a ‘fundamental term’, a breach of which constitutes a fundamental breach, ie, the failure by one party (the defendant) to perform a primary obligation which has the effect of depriving the other party (Madam Ng) of substantially the whole benefit which it was the intention of the parties that she should obtain from the SPA: See Photo Production Ltd v. Securicor Transport Ltd [1980] 2 WLR 283, 294 HL per Lord Diplock. The defendant’s fundamental breach had deprived Madam Ng of the fundamental benefits under the SPA. That ALASAN PENGHAKIMAN NA-22NCVC-54-11/2021 14 fundamental breach entitled the innocent party (Madam Ng) to rescind the contract and to have the parties restored to a position where they will stand as if the contract (the SPA) had never been made ie, the return of the property by way of restitutio in integrum to Madam Ng: (See Berjaya Times Square Sdn. Bhd, supra, at p. 281 B per Gopal Sri Ram FCJ), and, upon her death, to her estate. [29] Seterusnya, di dalam kes Damansara Realty Bhd lwn Bungsar Hill Holdings Sdn Bhd & Anor [2011] 9 CLJ 257, Mahkamah Persekutuan telah memutuskan seperti berikut:- [31] We also agree with the finding of the courts below that the assertion that the plaintiff was entitled to commence development at a time of its choice or at its own leisurely pace and the argument that the plaintiff had the right to a further three years extension upon the expiration of the fifteen years period to be wholly untenable. Indeed, it would be commercially sensible to deduce that the parties had intended for the development process to be completed (or at least substantially completed) by the end of the fifteen years period. Here, nothing to that effect has been done. It is far from completion. In fact, it has not even commenced. And incidentally, it is trite that there is a prima facie acceptance that in commercial contracts, time would be of the essence (see: Bunga Corp v. Tradax Export SA [1981] 2 All ER rule, in our view, applies with even greater force in construction contracts. It can of course, be rebutted if the ALASAN PENGHAKIMAN NA-22NCVC-54-11/2021 15 parties indicate otherwise by words or conduct, but for a starting point it must be assumed that the parties intended for time to be of the essence. It would not make much commercial sense if otherwise. Isu Kedua: Sama ada Defendan telah gagal untuk membayar balasan sebagaimana yang dipersetujui dalam Perjanjian Usaha Sama (“Perjanjian JVA”) dan Perjanjian Tambahan (“Perjanjian SA”) [30] Seterusnya, di bawah Perjanjian “JVA” dan Perjanjian “SA” tersebut, Defendan adalah bertanggungjawab atau berkewajipan untuk membayar kepada Plaintif balasan-balasan seperti berikut:-