Sekali lagi ingin kami tegaskan bahawa keputusan/persetujuan bersama yang dicapai semasa Mesyuarat tersebut adalah muktamad dan pembayaran ke atas tuntutan-tuntutan berkenaan akan diproses dan dibuat mengikut keputusan ini. 25 [22] The Defendant submits the fact that the Plaintiff insisted to make payment of the Debt Demanded regardless of the Defendant’s position and that the corresponding work amounting to RM4,574,479.00 has been paid effectively in November 2014 is consistent with clause 54(b) of the Contract. Therefore the balance in the sum of the Debt Demanded become due and payable to the Defendant. Findings of the court [23] As decided by the Federal Court in the case of Foo See Moi, letters written without prejudice are inadmissible in evidence of the negotiations attempted and where the negotiations conducted lead to a settlement the letters become admissible in evidence of the terms of the agreement. [24] As to the factors which need to be taken into consideration when determining whether a letter is issued with prejudice or otherwise the court in Indran a/l N Jeganathan v Nithiyani a/p K Kulaveerasingam [2011] 7 MLJ 237 referred to a Hong Kong case of Re Jinro (HK) Ltd [2002] 4 HKC 90 and said – 26 [30] In Re Jinro (HK) Ltd [2002] 4 HKC 90 the judge held that it was not necessary for a 'without prejudice' stamp to be expressly applied to the negotiations if it was clear from the surrounding circumstances that the parties were genuinely seeking to compromise the dispute. It was stated in that case that a party claiming without prejudice privilege on communication would have to show that the communication was made legal proceedings in relation to the dispute had commenced or were contemplated: (iii) the communication was made in a genuine attempt to settle the dispute; the communication was made with the intent that if negotiations failed, it could not be disclosed without the parties consent. [25] Applying the law as stated in the above cases to the facts that transpired between the parties I am of the view, based on the reason stated below, the Plaintiff’s Impugned Letter was issued on a without prejudice basis. [26] It is noted that the Impugned Letter was not boldly stamped headed with the phrase “Without Prejudice”. However the application of the rule is not dependent on the use of the said phrase and regards must be given to the circumstances surrounding the issuance of the Impugned Letter, namely, the circumstances which led to the issuance of the said letter and the circumstances that transpired thereafter. [27] The evidence (in particular as set out in the Chronological Table) clearly shows at the time the Impugned Letter was issued the parties 27 were in the midst of a series of discussion as part of their effort to resolve the issue relating to the value of earthworks done by the Defendant. The Impugned Letter was issued almost immediately after the Meeting on 23 September 2014 where both the Plaintiff and Defendant met to discuss the unresolved issue regarding value of additional works done by the Defendant. Importantly discussions were also carried out by both parties by putting forward their case in writing via the numerous letters to justify their position, particularly the quantity, rate and value of works done by the Defendant. The affidavit evidence shows that each of the party refused to accept the other party explanation or justification in relation to the works done by the Defendant. [28] Based on the affidavits of both parties and contents of the letters exchanged between the parties it is my finding that discussions were carried out with the intention of resolving the value of additional earthworks done by the Defendant under the Project to enable the Final Certificate be issued so as to enable payment to be made to the Defendant. Having considered the affidavit evidence adduced I am of the view that the parties had failed to reach a settlement in respect of the value of additional earthworks done which made the issuance of the Final Certificate impossible. I shall state my reasons below. 28 [29] Considering the evidence in its totality I do not agree with the Defendant’s contentions that the Plaintiff’s letter stated at paragraph 21 above shows the Plaintiff’s confirmation and acknowledgement of the Debt Demanded. [30] If one were to only refer to the said selected passages of the Plaintiff’s letter as highlighted by the Defendant (see paragraph 21 above) it would appear that an agreement was reached because the above passages seems to indicate the Plaintiff’s position as such. However it must be borne in mind the statements made by the Plaintiff in the letters highlighted by the Defendant was part and parcel of an ongoing exercise between the Plaintiff and the Defendant to resolve the dispute in respect of the value of earthwork done by the Defendant. As such it is not right to only focus on the Plaintiff’s position as the negotiation/discussion exercise was a two way interaction between the parties. Obviously the Defendant’s position and response to the unresolved issue and the statement made by the Plaintiff in the above passages must be equally considered in order to determine whether there was indeed an agreement reached between the parties. In other words, it must be determined whether there was a meeting of mind between the Plaintiff and the Defendant in relation to the unresolved issue and the Demanded Debt (RM6,313,596.40) as the sum due and 29 payable by the Plaintiff to the Defendant under the Contract. If there is such an agreement then the preliminary objection raised by the Plaintiff in respect of the admissibility of the Without Prejudice Letter must fail. [31] In the Plaintiff’s letter dated 23 September 2014, no doubt the Plaintiff had outlined in a table the details of works done, claim made by the Defendant for the additional works done and what appears to be the agreement reached between the parties in respect of the additional works done. It was also stated in the letter that that payment will be made by the Plaintiff based on the agreement at the Meeting. However the amount of payment to be made or agreed by both parties was not stated in the said letter. [32] Notwithstanding that, the Defendant replied via letter dated 24 September 2014 disputing the Plaintiff’s letter dated 23 September Defendant set out the said differences. The Defendant then set out in detail their computation of the earthworks done in a table and state the value of additional earthworks done as RM17,240,285.00 which is payable to the Defendant. 30 [33] The Impugned Letter was issued in response to the Defendant’s letter dated 24 September 2014 in which the Defendant claimed the sum RM17,240,285.00 is payable. The Impugned Letter is the Plaintiff’s denial in respect of the Defendant’s claim of RM17,240,285.00. Instead the Plaintiff’s calculation of the total value for earthworks done as itemised at paragraph 3 is RM6,313,526.40 and at paragraph 5 is RM4,574,479.00. This made up a total of RM10,888,005.40. It is to be noted the details (includes units, rate and quantity) of the additional earthworks done at the said paragraph 3 where the total value is RM6,313,526.40 is made on a without prejudice basis. The sum RM6,313.526.40 is the sum demanded from the Plaintiff in the Statutory Notice (Demanded Debt). [34] The Defendant subsequently via letter dated 3 October 2014 insisted the sum RM10,888,005.40 is a mistake and that the sum ought to be RM17,240,285.00. By the last paragraph of the 3 October 2014 letter, again the Defendant acknowledged that both parties has different position/views in construing the earthworks done. Pursuant to that the Defendant proposed a meeting be held so that the Plaintiff in its capacity as the Superintending Officer of the Project to decide whether to confirm, revoke or vary the Plaintiff’s own decision. It is pertinent to note the words in the last paragraph where the Defendant said as follows - 31 Oleh kerana terdapat perbezaan dalam menterjemahkan kerja-kerja berkaitan di antara kita, mungkin kerana salah faham dan/atau salah andai, saya ingin mencadangkan supaya satu mesyuarat semula dapat diadakan untuk menyelesaikan perkara-perkara yang berbangkit dan memohon keputusan muktamad tuan sebagai Pegawai Penguasa samada mengesahkan, membatalkan atau mengubah (confirm, reverse or vary) keputusan-keputusan tuan dan/atau pegawai-pegawai tuan untuk tindakan lanjut pihak kami. [35] This is followed by the Plaintiff’s letter dated 20 October 2014 where the Plaintiff replied it has no objection for a meeting as proposed by the Defendant so as to enable parties to discuss further. The Plaintiff however reiterated that the Plaintiff’s position in its letter dated 23 September 2014 and the Impugned Letter remains. [36] At this juncture it is to be noted that in so far as the Plaintiff is concerned the value of additional earthworks is RM10,888,005.40