of s 15 CIPAA. 2nd Issue: Whether the Adjudicator acted in breach of the rules if natural justice and/ or failed to act impartially by re-writing the terms of the agreement [35] Without prejudice to the 1st Issue, MBSB contended that the Adjudicator had breached the first pillar or rule of natural justice in that he was bias. It was alleged that the Adjudicator had also failed in his duty to be impartial by rewriting Cause 43.0 of the CoC in favour of Mitrajaya when he imposed a time limit for the SO to provide his S/N xh8T7sFBYkuCRUzm7qyz1w determination on the EoT applications contrary to the agreement of the parties. [36] Specifically, MBSB was disgruntled at the decision in para K: 2c(5)(m) of the AD which reads: “Notwithstanding the foregoing, there appears to be protracted delay on the part of the SO in eliciting additional documents and seeking clarification from the Respondent; this is evident from the fact that the first of several clarifications and additional documents was only submitted by the Respondent on 15 May 2019 (for EOT applications #5 through #9) some 14 months of so after EOT application #5 was submitted and thereafter several more submissions ensued from the Respondent with the last submission being made by the same on 16 Jun 2020. I agree with the Respondent that the first MCO imposed by the Government on 18 Mar 2020 did not have any significant bearing on the SO’s ability to assess the EOT Applications timeously and promptly as these applications were made well before the above the foregoing date. Even if the assessment of the EOTS extended into the MCO period as in this instant case, approval from the local authorities to visit the Project site could S/N xh8T7sFBYkuCRUzm7qyz1w have been sought in order to access site records and other contemporaneous documents stored thereat.” [37] Apart from para (c) in s 24 CIPAA which was alluded to previously, paras (b) and (d) of the same provision provide that an adjudicator shall act independently, impartially and in a timely manner and that there are no circumstances likely to give rise to justifiable doubts as to the adjudicator’s impartiality and independence. [38] For purposes of limb (c) of s 15 CIPAA, MBSB submitted that the applicable test is the “real possibility” test in that a “fair minded and informed observer” would conclude that there is a “real possibility” that the Adjudicator was partial to Mitrajaya and biased against MBSB. It was additionally submitted, on the authority of Itramas Technology Sdn Bhd v. Savelite Engineering Sdn Bhd and other cases [2021] MLJU 1382, that an adjudicator must treat both parties “equally and fairly” and the High Court in that case had set aside the adjudication decision because the adjudicator had breached the duty to be impartial by simply giving one party “an additional day” compared to the other party to respond to the adjudicator’s order. S/N xh8T7sFBYkuCRUzm7qyz1w [39] In the instant case, the complaint is that, despite finding that Mitrajaya had failed to comply with the mandatory requirements under Clause 43.0 CoC, the Adjudicator sought to exonerate Mitrajaya for the same by faulting the SO for the “protracted delay … in eliciting additional documents and seeking clarification” from Mitrajaya although Clause 43.0 does not impose a time limit on the SO. This eventually resulted in a finding that time for Mitrajaya to complete the works had been rendered at large and MBSB therefore could not claim for LAD. [40] The learned counsel for MBSB cited the case of Richallenge Corp Sdn Bhd v. Poteck Enterprise Sdn Bhd [2020] 3 MLJ 704 for the proposition that the Adjudicator cannot rewrite or improve on the terms between the parties “however desirable the improvement might be”. [41] In my considered view, MBSB has not proven that there is a denial of natural justice as the Adjudicator was bias and/ or that he had acted partially to aid Mitrajaya by “re-writing” the terms of the agreement between the parties in respect of the issue on Clause 43.0 of the CoC. S/N xh8T7sFBYkuCRUzm7qyz1w [42] MR. KH Chan had drawn the attention of the Court to the following part of Clause 43.0 CoC where, after the delay events are set out in that Clause, it is stated that – “then the S.O. may if he is of the opinion that the extension of time should be granted, so soon as he is able to estimate the length of delay beyond the date or time aforesaid issue a Certificate of Delay and Extension of Time giving a fair reasonable extension of time for completion of the Works.”. [43] The learned counsel submitted that the words “so soon as” in the above excerpt requires the SO to act forthwith. [44] In the book “The Malaysian PWD Form Of Construction Contract”, Second Edition, Sweet & Maxwell Asia, 2011, Lim Chong Fong J, in discussing Clause 43.0 of the PWD Form of Contract, explicated at p 103 that, in making an objective assessment of the application for EoT, the Officer Named must – “… do this as soon as he is able to estimate the length of the delay and no time limit is specified. S/N xh8T7sFBYkuCRUzm7qyz1w Nonetheless, it is submitted that the views of Roper J in the New Zealand case of Fernbrook Trading Co Ltd v Taggart [1979] 1 NZLR 556 are of assistance. The learned judge said: I think it must be implicit in the normal extension of time clause that the contractor is to be informed of his new completion date as soon as reasonably practicable. …” (emphasis added). [45] Further reference may be made to another textbook, “Construction Law in Malaysia”, Sweet & Maxwell Asia, 2012 by Datuk Sundra Rajoo and Ir Harbans Singh KS, the learned authors opine at p 368, with my added emphasis, that “If no period is expressly provided (see clause 43.1 of the JKR Forms 203 and 203A (Rev 1/2010) and clause 49.1 of the PWD Form DB (Rev 1/2010), then the contract administrator must act within a reasonable time of the contractor’s application (see Lion Engineering Sdn Bhd v Pauchuan Development Sdn Bhd [1997] 4 AMR 3315). …”. S/N xh8T7sFBYkuCRUzm7qyz1w [46] Although MBSB is not wrong in contending that Clause 43.1 CoC is silent as to the time frame within which the SO must provide his determination on Mitrajaya’s EoT applications, I am not convinced that the Adjudicator had given an interpretation of the said Clause in a way which a “fair minded and informed observer” would conclude that there is a “real possibility” that the Adjudicator was partial to Mitrajaya and biased against MBSB. [47] The Adjudicator had considered the submissions made by the parties and made a finding of fact as quoted in para 36 above. [48] In the upshot, it is well within the matters submitted by the parties in the adjudication proceedings for the Adjudicator to investigate as to whether the SO had acted within a reasonable time in assessing and deciding on the applications for EoT. In reality, MBSB is unhappy with the Adjudicator’s analysis and ultimate findings and conclusions, and this discontent is translated into a veiled attempt to set aside the AD on the grounds as stated in para 35 of this judgment. S/N xh8T7sFBYkuCRUzm7qyz1w 3rd Issue: Whether the Adjudicator breached the rules of natural justice and/ or failed to act impartially by allowing Mitrajaya to file a Rejoinder and denying MBSB the opportunity to file a Surrejoinder [49] At the outset, it is observed that in paras 48 to 50 of the AIS and in MBSB’s Written Submission (encl. 28), MBSB first attempts to have the AD set aside pursuant to limb (b) and/ or (c) of s 15 CIPAA as the Adjudicator is alleged to have failed to afford MBSB with the opportunity to file an application for leave to serve a Surrejoinder whereas he had allowed Mitrajaya to serve a Rejoinder without even hearing MBSB regarding this request. However, in the subsequent Written Submission In Reply and Brief Reply (encls. 32 and 37), MBSB seems to focus on the aspect of the purported unequal treatment of the parties and the Adjudicator having acted partially in favor of Mitrajaya i.e. limb (c) of s 15 CIPAA. [50] In the instant case, “a fair minded and informed observer” is said would conclude that there is a “real possibility” that the Adjudicator was partial to Mitrajaya when he – S/N xh8T7sFBYkuCRUzm7qyz1w