any other letters and/or approval for the extension of time of the said project. Preliminary objection on affidavit in reply filed by counsel for the Defendant to contest enclosure 13 [2] The objection by the Plaintiff is on the basis that the counsel for the Defendant is not privy to all the material facts arising in this application as counsel is never a party involved in the said project, hence is not equipped with the necessary knowledge to depose the affidavit in reply on behalf of the Defendant. [3] This Court, however having perused the said affidavit by the Defendant’s counsel and having observed the averment by the Plaintiff in the affidavit in support of enclosure 13, noted the following: “5. Saya telah dinasihatkan oleh peguamcara Plaintiff berkenaan isu-isu undang-undang dalam Afidavit ini dan sesungguhnya percaya bahawa permohonan ini adalah perlu untuk pelupusan yang adil untuk guaman di hadapan Mahkamah Yang Mulia”. [4] In addition to this, the affidavit in reply by counsel for the Defendant in replying to the particular facts raised in the said affidavit in support by the Plaintiff, paragraph (2) states as follows: “Saya menyatakan bahawa segala kenyataan-kenyataan yang dinyatakan di sini adalah benar dan mengikut pengetahuan saya sendiri dan melalui dokumen-dokumen yang saya mempunyai akses kepadanya melainkan jika dinyatakan sebaliknya”. S/N rfuNYcCMk6M12VUyiabig Page 3 of 12 [5] For this purpose, facts which are more familiar to the Defendant, the averment by counsel in the said affidavit in reply uses such phrases “saya diarah”. This ‘arahan’ must surely come from the Defendant arising from the authorization given by the Defendant to the deponent counsel as contained in paragraph (1) “… saya telah diberi kuasa untuk mengikrarkan Afidavit ini bagi pihak Defendan”. [6] That being the case, the preliminary objection by the Plaintiff is without basis and therefore dismissed by this Court. The hearing of enclosure 13 proceeded until its determination by this Court, with the result that perusal of the cause papers and upon hearing submissions by both parties, enclosure 13 is dismissed with cost. Background facts [7] The Defendant appointed the Plaintiff as subcontractor for the ‘piling, flyover and bridge works pertaining to the project ‘Cadangan Membina Persimpangan Bertingkat di Persimpangan Jalan Dato Onn Utama dan Jalan Bukit Mutiara, Johor Bahru, Johor’ (referred to as ‘the project’). MBJB is the owner of the said project, Selenggara Maju Trading (SMT) is the main contractor appointed by MBJB and GJ Runding is the project consultant appointed by both MBJB and SMT. None of these are named as parties in this proceeding. [8] The Plaintiff in its statement of claim and enclosure 13 contends that the Project was completed on 31.5.2021. Yet, despite works carried out by the Plaintiff with due diligence, reasonable care and skills, there has been a failure on the part of the Defendant pursuant to the terms of the Subcontract, to certify or make payment for Progress Claims No. 17, 18 S/N rfuNYcCMk6M12VUyiabig Page 4 of 12 and 19 to the Plaintiff, with the outstanding sum owing after material deduction is for the sum of RM1,023,453.80. [9] The Plaintiff further contends that there has been failure by the Defendant to issue the Certificate of Practical Completion (“CPC”) and the Certificate of Completion of Making Good Defects (“CMGD”) to the Plaintiff and this caused the Defect Liability Period (“DLP”) which ought to commence on 31.5.2021, could not commence. [10] The Defendant, on the other hand in its statement of defence and affidavit in reply enclosure 15, said based on the Letter of Award between Plaintiff and Defendant, the completion date of the Project should be 30.6.2020 and any failure to comply, liquidated damages based on clause 3 of the Letter of Award, is due to be paid by the Plaintiff. [11] The Defendant further deposed in paragraph 6 and 7 of the Affidavit-in-Reply, that it is the duty of the Plaintiff (based on clause 10 of the Letter of Award), to submit the documents being the ‘As-Built’ drawings and the ‘Certificate of Completion and Compliance’, the documents requested by the Plaintiff in this application. Clause 10 provides as follows: “i. You are to submit completes sets of shop drawings as required in the Sub Contract. ii. You shall submit complete sets “As Build” drawings and/or Operation and Maintenance Manual (O&M) as stated in the subcontract documents before the date of certificate of completion (CPC) if any.” S/N rfuNYcCMk6M12VUyiabig Page 5 of 12 [12] Arising from the failure on the part of the Plaintiff to do so, the Defendant deposed that the Defendant was moved to obtain the ‘As-Built’ drawings from another source. It is only upon submission of the ‘As-Built’ drawings by the Defendant within the extension of time period granted to the Defendant, moved the issuance of the CPC. [13] It is the submission by the Defendant that the Plaintiff is not entitled to other documents not related to the Letter of Award between the Plaintiff and the Defendant. In answer to this, the Plaintiff did not deny the said clause of the Letter of Award when the Plaintiff in paragraph 11 of the affidavit in reply enclosure 24 deposed as follows: “11. Kecuali setakat mana yang konsisten dengan terma-terma Letter of Award tersebut, baki Perenggan 6 dan 7 Afidavit Jawapan tersebut adalah dinafikan…” and proceeded to maintain the importance of the ‘As-Built’ drawings in order to support, not only the Defendant’s counter-claim but also to either support or break the Plaintiff’s claim. [14] In doing so, the Plaintiff did not refute clause 10 but appears to suggest that if the said ‘As-Built’ drawings are still within the possession and control of the Plaintiff, enclosure 13 would not have been filed. The Plaintiff argued further that in the absence of GJ Runding and/or MBJB’s affidavit opposing this application, the said ‘As-Built’ drawings ought to be allowed based on the discovery application by the Plaintiff. This Court is puzzled by this argument as both GJ Runding and MBJB are not named as parties to this suit. To seek for their affidavits opposing or agreeing to enclosure 13 is therefore, absurd. S/N rfuNYcCMk6M12VUyiabig Page 6 of 12 [15] In addition, this Court agrees with the Defendant that based on the statement of claim, the Plaintiff’s stand is that the ‘As-Built’ drawings have been submitted by the Plaintiff. Although the Defendant contends that the submission, if true, ought to have been made on the Defendant’s consultant and not any other party, takes the position, that surely then there must be no necessity to file this application as it is the same document that have been sought by the Plaintiff in this discovery application as can be seen from the wordings of the application reproduced once more as follows: “correspondence between the Plaintiff and GJ Runding and/or GJ Runding and MBJB (Majlis Bandaraya Johor Bahru) on the handing over of the ‘As-Built’ drawings”. [16] Furthermore, from the letters by GJ Runding dated 10.10.2022 and from MBJB dated 28.2.2023, both annexed by the Plaintiff in the affidavit-in-support, GJ Runding and MBJB have no knowledge of the suit between the Plaintiff and the Defendant. These letters are crucial in determining the position of these entities. The contents of these 2 letters extracted and produced as below: “Letter from counsel for Plaintiff dated 3.10.2022 to GJ Runding with heading: “Cadangan Membina Persimpangan Bertingkat Di Persimpangan Jalan Dato Onn Utama dan Jalan Bukit Mutiara, Johor Bahru, Jahor Darul Takzim (“Projek”): “3. …our client’s progress claims for work done …i.e. Progress Claims No. 17, 18 and 19 respectively, have not been certified and our client has not received the Interim Payment Certificates (“IPC”) for the same… S/N rfuNYcCMk6M12VUyiabig