2
JABATAN KERJA RAYA MALAYSIA DEFENDANTS GROUNDS OF DECISION 2 Introduction [1] This is an opposed application to discontinue the suit with liberty to refile. [2] The Plaintiff is a private limited company involved in the construction business. [3] The First Defendant is the Federal Government of Malaysia and the Second Defendant is a department within the Ministry of Works of the First Defendant. Background and Preliminary [4] By a contract no. JKR/IP/CKUB/199/2012 dated 17 December 2012 (“Contract”) that included the PWD 203A standard form of conditions of contract, the Plaintiff was appointed by the Defendants as the completion main contractor to carry out and complete the remaining outstanding works at UiTM Cawangan Selangor Kampus Sungai Buloh-Fakulti Pergigian (‘Project”) that was abandoned by the original main contractor. 3 [5] The carrying out of the works in the Project could not be completed by 11 September 2013 which is the time stipulated in the Contract and the Plaintiff was granted several extension of time pursuant to the Contract by the superintending officer of the Defendants. [6] The works in the project was finally completed on 1 September 2015. [7] As the result of the delayed completion of the works in the Project, the Plaintiff claimed for prolongation loss and expense against the Defendants. [8] However, the Defendants counterclaimed that the Plaintiff contributed to the delayed completion of the Project. Consequently, the Defendants refused to pay the prolongation loss and expense claimed by the Plaintiff and the Defendants deducted liquidated and ascertained damages for late completion for the Plaintiff’s payment. [9] By reason of the disputes and differences that have arisen between the parties including on the final accounts that were issued by the superintending officer of the Defendants, the Plaintiff initiated this suit on 3 April 2019. [10] After the close of pleadings in the suit, I noticed at pre-trial case management that there is an arbitration provision in the Contract which 4 was not adhered to by the parties. Since the disputes and differences substantially encompassed construction final accounting, the parties upon my suggestion consented to have disputes and differences determined via court annexed arbitration pursuant to s. 24A of the Courts of Judicature Act 1964. Accordingly and again with the consent of the parties, I so ordered and have on 30 October 2019 appointed Miss Tan Swee Im as the arbitrator (“Arbitrator”). [11] The commencement of the arbitration hearings have been disrupted by the imposition of the Movement Control Order in March 2020 after the submission of the bundles of documents and witness statements. [12] Subsequently, the Arbitrator on 1 July 2020 directed the Plaintiff to submit a detail list of the loss and expenses claimed to the Defendants which the Plaintiff complied by submitting matrix of its loss and expenses claims involved. Furthermore, the Plaintiff on 2 July 2020 submitted a further witness statement for purposes of the forthcoming re-scheduled hearing. [13] The Defendants on 1 August 2020 replied challenging the Plaintiff’s matrix of loss and expenses claim particularly that they were unsubstantiated with actual documentary evidence. [14] In consequence, the Plaintiff on 17 August 2020 submitted an additional bundle of document comprising the documentary evidence to 5 substantiate its loss and expenses claim but which was strenuously objected by the Defendants. [15] The Plaintiff thereafter on the first day of the scheduled resumed hearing on 19 August 2020 intimated to the Arbitrator that the Plaintiff wishes to withdraw/discontinue the suit with liberty to refile and the Arbitrator accordingly directed that this be made before me. [16] I thereafter met the parties several times to try to get them to compromise and put them back on track to conclude the arbitration including the Plaintiff to pay for any abortive costs of the arbitration hearings. Since the Defendant was adamant that the Plaintiff’s additional bundle of document submitted on 17 August 2020 cannot be utilized in the arbitration, the Plaintiff was constrained to apply to withdraw the suit with liberty to refile. However the Defendants replied that the suit must be withdrawn without liberty to refile. [17] In the circumstances, I therefore directed the Plaintiff to file a formal application for withdrawal of the suit which the Plaintiff complied on 21 April 2021 (“Application”). [18] The affidavits which were filed for purposes of the Application are as follows: 6