Power of Attorney: • Power of Attorney dated 19.5.2021 for the title held under PN111756, Lot 126399, Seksyen 3, Bandar Ulu Kelang, Daerah Gombak, Negeri Selangor; • Power of Attorney dated 19.5.2021 for the title held under PN117433, Lot 126407, Seksyen 2, Bandar Ulu Kelang, Daerah Gombak, Negeri Selangor; and • Power of Attorney dated 19.5.2021 for the title held under HS(D) 81831PT 5243 Bandar Ulu Kelang, Daerah Gombak, Selangor. (collectively referred to as "Security Agreements") [8] For the purpose of the Project, the Defendant undertook to guarantee a sum of RM476,000,000.00 (Ringgit Malaysia Four Hundred Seventy-Six Million Only) in the form of Bank Guarantee comprising of the following: • RM108,000,000.00 (Ringgit Malaysia One Hundred and Eight Million Only) Bank Guarantee (1); • RM118,000.000.00 (Ringgit Malaysia One Hundred and Eighteen Million Only) Bank Guarantee (2) ; • RM115,000,000.00 (Ringgit Malaysia One Hundred and Fifteen Million Only) Bank Guarantee (3) and • RM135,000,000.00 (Ringgit Malaysia One Hundred and Thirty-Five Million Only) Bank Guarantee (4). (collectively referred to as "Bank Guarantee") Issuance of the Bank Guarantee • Bank Guarantee (1) to be issued in favour of main contractor to guarantee payment for the construction and completion of Festa Block E of the Project; • Bank Guarantee (2) to be issued in favour of main contractor to guarantee payment for the construction and completion of Festa Block C of the Project; • Bank Guarantee (3) to be issued in favour of main contractor to guarantee payment for the construction and completion of Festa Block A of the Project; and • Bank Guarantee (4) to be issued in favour of main contractor to guarantee payment for the construction and completion of Festa Integrated Podium of the Project. Conditions for Issuance of Bank Guarantee The Bank Guarantee Facilities shall be used solely for issuance of bank guarantee favouring the main contractor in respect to the construction of Festa Blocks E, C, A and Integrated Podium of the Project: • Written request for issuance of the bank guarantee shall be delivered by the Plaintiff to the Defendant not less than seven (7) days banking days before the date on which the guarantee is required to be issued; • The Plaintiff shall provide the Defendant with a duly executed and stamped Letter of Indemnity in favour of the Defendant substantially in form and substance acceptable to the Defendant together with its request and a sample format for the issuance of the bank guarantee. • Issuance of the bank guarantee shall be made upon the Plaintiff achieving total combined sales of RM595,000,000.00 on Blocks E, C and A of the Project. The sales are to be evidenced by way of submission of duly executed and stamped Sales and Purchase Agreement between the Plaintiff and the purchasers of the Project. [9] Bank Guarantee (1), (2) and (3) shall only be called upon receipt and/or comply with the following from the Plaintiff or the respective contractor: • A certified true copy of the Certificate of Practical Completion issued by the Project Consultant/Project Architect prior to the expiry date of each of the respective BG issued. • Any other conditions as deemed necessary by the Defendant. [10] Bank Guarantee (4) shall only be called upon receipt and/or comply with the following from the Plaintiff or the respective contractor: • A certified true copy of the Partial Certificate of Practical Completion issued by the Project Consultant/Project Architect prior to the expiry date of each of the respective BG issued. • The construction progress for Block A, Block C and Block E shall have reached 21st Floor, 171h Floor and 13th Floor respectively as certified by the Project Consultant/Project Architect. • The external works for Road Works, Surface Water Drainage Works and Sewerage Works shall have been completed as certified by the Project Consultant/Project Architect. [11] Bank Guarantee (1) to (4) are payable upon the Certificate of Practical Completion ("CPC") issued to the main contractor. Pursuant to the terms of the Letter of Award dated 31 December 2013 between the main contractor and the Plaintiff, the CPC will only be issued upon the compliance of specifications/approvals by the local authority, construction drawings and contract specification. Security / Supporting Documents • A First Party Second Fixed Charge over two (2) land titles identified as H.S.(D) No. 61423 PT No. 3901 and H.S.(D) No. 58240 PT No. 3304, all situated in Bandar Ulu Kelang, Daerah Gombak, State of Selangor and owned by the Plaintiff. • A third fixed and floating charge over all the present and future fixed and floating assets of the Plaintiff. • A second irrevocable Deed of Assignment over all end-finance proceeds on the proposed Festa Condominium comprising of 1,099 units of condominium to be developed on lands identified as H.S.(D) No. 61423 PT No. 3901 situated in Bandar of Ulu Kelang, Daerah Gombak, State of Selangor and owned by Permodalan Negeri Selangor Berhad. • Joint and Several Guarantee by Dato' Tee Ah Seng (NRIC No. 510124- 10-5833) and Mr Tee Kim Hock (NRIC No. 590806-10-5657). The guarantors shall further undertake to inject the necessary funds in the event of any cost overrun during the implementation of the Project. • Subordination of all shareholders' and directors' advances to the Bank Guarantee facilities. • A first charge on Lot 4450 for development on 1,248 units of condominium (Heros Block), Bandar Ulu Kelang, Daerah Gombak State of Selangor. • A first charge on H.S.(D) No. 58241 PT No. 3305, Bandar Ulu Kelang, Daerah Gombak, State of Selangor. • A first charge on the land held under HS(D) 71661, PT 4921, Bandar Ulu Kelang, Daerah Gombak, State of Selangor measuring approximately 44,313 square meters. [12] On 31 December 2019, the appointed architect issued the Certificate of Practical Completion ("CPC") to the main contractor. However, the Plaintiff alleged that there were “irregularities” in the manner the CPC was issued on, among others, the following reasons: • There were a substantial number of incomplete and defective works which are not in conformity with the specifications by the local authority, construction drawings and contract specification. • Failure on the part of the main contractor to properly construct expansion joints on Ground Floor to Level 3 resulting in severe ponding issues. • Failure of the main contractor to use materials in compliance to Pengurusan Air Selangor's requirements for all the piping used to receive water meters for the residential units resulting in the Plaintiff having to change all 1,099 units piping to comply with Air Selangor's requirements. • Failure of the main contractor to seal all the voids in the riser rooms. [13] After the CPC was issued by the appointed architect, the main contractor invoked the Bank Guarantee. The Defendant then paid the Bank Guarantee in the sum of RM476,000,000.00 (Ringgit Malaysia Four Hundred Seventy-Six Million Only) to the main contractor through MBSB Bank Berhad. [14] Pursuant to the issuance of the Bank Guarantee by the Defendant, the Defendant then issued a Letter of Offer dated 6 August 2020 for a Term Loan Facility in the sum of RM476,000,000.00 (Ringgit Malaysia Four Hundred Seventy-Six Million Only) for the purpose of reimbursing the Defendant for the amount paid arising from the call of the Bank Guarantee by the main contractor. [15] On 25 September 2023, the Plaintiff received three Letter of Demands from the Defendant's Solicitors, Messrs Shook Lin & Bok demanding RM161,320,568.36, RM35,731,883.07 and RM81,484,072.18 respectively to be paid by 9 October 2023. On 9 October 2023, the Plaintiff issued a letter to the Defendant's Solicitors requesting for an extension of time for the payment of the Loan Facility. [16] On 10 October 2023, the Defendant's Solicitors issued a letter to the Plaintiff stating that the Defendant allowed the extension of time and further requested for settlement proposal by 16 October 2023. [17] On 16 October 2023, the Plaintiff submitted a payment proposal with explanations on the background and issues of the Project that caused the repayment delays. However, the Defendant's Solicitors then issued a letter dated 18 October 2023, to the Plaintiff stating that the Defendant is unable to accede to the Plaintiff's request for deferment of payment of arrears and not agreeable for time to be granted until the middle of 2024. [18] On 1 November 2023, the Plaintiff informed the Defendant's Solicitors by way of a letter dated 1 November 2023, that the Plaintiff and the Defendant were in the midst of negotiation for settlement and will put forth a settlement proposal by 15 December 2023. On 14 November 2023, the Plaintiff proposed for repayment in the sum of RM37,000,000.00 in 2023 and RM500,000,000.00 to be paid in 2024. With this, a total of RM537,000,000.00 will be repaid by the end of 2024. [19] Subsequently, the Defendant's Solicitor issued a Letter of Demand dated 20 November 2023, demanding for the payment of RM936,644,754.19 by 30 November 2023 failing which the Defendant will proceed to immediately take all steps to recover all monies due and owing under the Loan Facility and enforce all Security Agreements. However, the Plaintiff failed to make any payment to the Defendant. [20] On 29 November 2023, the Plaintiff commenced legal proceedings against the Defendant at the High Court of Shah Alam via Suit No. BA- 22NCVC-490- 11/2023 (“the Suit). Concurrently with the filing of the Suit, the Plaintiff sought an interim injunction against the Defendant to inter alia, restrain the Bank from enforcing the security agreements and the security documents related thereto against the Plaintiff and from filing a winding up petition against the Plaintiff. [21] On 30 November 2023, the High Court allowed the Plaintiff’s ex-parte application for an interim injunction. [22] On 26 Mac 2024, after the inter partes hearing, the learned Judicial Commissioner dismissed the Injunction Application with costs of RM5,000.00 to be paid by the Plaintiff to the Defendant. [23] The learned Judicial Commissioner in her judgment inter alia held that the Plaintiff failed to establish a serious issue to be tried, there was no unconscionable conduct on the part of the Defendant in releasing the bank guarantee and the Plaintiff has failed to make full and frank disclosure when the ex-parte interim injunction was obtained by the Plaintiff. [24] Dissatisfied, on 1 April 2024, the Plaintiff filed Notice of Appeal against the said decision. [25] Pending the disposal of this appeal, Plaintiff then filed an application for an Erinford Injunction dated 12 April 2024 in Enclosure 54 at the High Court to preserve the status of this appeal. [26] On or about the same time, the Defendant also filed an application for striking out under Order 18 Rule 19 Rules of Court 2012. [27] On 12 July 2024, the learned Judicial Commissioner granted the Plaintiff’s application for an Erinford Injunction pending the present appeal and directed that the Defendant’s application to strike out the Plaintiff’s action be deferred pending the disposal of the Appeal before this Honourable Court. Summary of The High Court Decision [28] The learned Judicial Commissioner in her judgment held among others as follows: