(viii) A First Charge on the land held under H.S.(D) 71661, PT 4921, Bandar Ulu Kelang, Daerah Gombak, State of Selangor measuring approximately 44,313 square meters [7] Under the plaintiff’s request on 5 February 2015, the defendant issued four Bank Guarantees in favour of the beneficiary, amounting to RM108,000,000.00, RM115,000,000.00, RM118,000,000.00, and RM135,000,000.00, totalling RM476,000,000.00. The plaintiff subsequently issued a Letter of Indemnity dated 25 September 2019 in favour of the defendant. [8] Subsequently, MBSB Bank Berhad, the assignee bank of the beneficiary, demanded payment of a guaranteed sum of RM476,000,000.00 as indicated in a letter dated 7 January 2020 (Exhibit SDB-7). Upon receiving the demand letter from MBSB and a certified true copy of the Certificate of Practical Completion (CPC), defendant released the guaranteed sum of RM476,000,000.00 to the beneficiary on 30 January 2020. At that time, the plaintiff did not object to the defendant's release of RM476,000,000.00. [9] After the Bank Guarantee was released, the plaintiff requested the defendant to convert the Bank Guarantee of RM476,000,000.00 into a term loan facility. The defendant issued an Offer Letter dated 6 August 2020, and subsequently, the parties entered into the Facility Agreement. The Term Loan Facility, amounting to RM476,000,000.00, is intended to reimburse the defendant for the amount paid as a result of the beneficiary's call under the Bank Guarantees. [10] The defendant alleges that the plaintiff has defaulted on payments under three Term Loan Facilities totalling RM476,000,000.00, RM104,100,000.00, and RM235,000,000.00, despite reminders issued by the defendant. In a letter of demand dated 25 September 2023, the defendant demanded that the plaintiff pay the outstanding instalment on or before 9 October 2023. [11] In reply to the demand letter, the plaintiff requested the defendant to defer the payment of the annual instalment for the loan facility of RM476,000,000.00. The defendant granted the plaintiff’s request for an extension until 16.10.2023. [12] Rather than making payment to the defendant, the plaintiff submitted the proposed settlement payment and explained the background and issues that contributed to the delay on the part of the plaintiff, as outlined in the letter dated 16 October 2023. [13] However, the defendant refused to accept the proposal. On 25 October 2023, the defendant's solicitors, Messrs Shook Lin & Bok, issued letters to the Plaintiff and the security parties, stating that an event of default had occurred and demanding the plaintiff pay all sums due under the Term Loan Facilities. [14] In a letter dated 1 November 2023, the plaintiff wrote to the defendant’s counsel, informing them that the parties were in the midst of negotiation. On 14 November 2023, the plaintiff proposed to pay the sum of RM37,000,000.00 in 2023 and RM500,000,000.00 in 2024. [15] The plaintiff failed to make any payments to the defendant as proposed. Instead, on 29 November 2023, the plaintiff filed a lawsuit before this Court against the defendant and an application for an injunction order (Enclosure 3) to restrain the defendant from enforcing the loan and security documents against the plaintiff following the default. [16] Under the Statement of Claim, the plaintiff pray for reliefs from this Court are as follows-a) An interim injunction to prohibit the defendant from enforcing all security agreement against the plaintiff including appointing a receiver and manager pursuant to the debentures dated 2.3.2007 and 23.7.2007 or foreclosure of the plaintiff’s property pursuant to the Power Attorney dated 19.5.2021. b) An interim injunction to prohibit the defendant from filing a winding up petition against the plaintiff. c) A permanent injunction to prohibit the defendant from enforcing all the security agreement against the plaintiff but not limited to appoint a receiver and manager pursuant to the debenture or foreclosure the plaintiff and/or filing a winding up petition. d) A declaration that the letter of demand dated 20.11.2023 is exaggerated, premature and was lacking in good faith and thus invalid. e) An order for an account enquiry pursuant to Order 43 Rules of Court 2012 into the amount of RM936,644.754 as demanded by the defendant. f) Costs. g) Special damages for project loss amounting to RM4,606,143,200.00. h) General exemplary damages to be assessed by the Court. i) Interest at the rate of 8% per annum on special damages to be calculated from the date of order. j) Interest at the rate of 8% per annum on general damages to be calculated from the date of order. k) Such further and/or other orders which this Court deems fit and proper to award. [17] On 29 November 2023, the plaintiff obtained an ex parte interim injunction against the defendant. Following the hearing of Enclosure 3 via inter parties on 26 March 2024, this Court dismissed Enclosure 3 with costs. On 15 November 2024, the Court of Appeal upheld the order made by this Court. C. LAW ON STRIKING OUT APPLICATIONS [18] Under Order 18, rule 19(1) of the Rules of Court 2012, the Court may evaluate the evidence and the merits of the case to determine whether this action is likely to fail and must assess whether the claim is clearly unsustainable. [19] In Raja Zainal Abidin bin Raja Haji Tachik & Ors v British-American Life & General Insurance Bhd [1993] 3 MLJ 16, the Supreme Court refers to the case of Tractors Malaysia Bhd v Tio Chee Hing [1975] 2 MLJ 1 and held as follows-In Tractors, the defendants applied to set aside the pleadings there on the grounds that they were frivolous and vexatious. The High Court allowed the application holding that the action was bound to fail. The Privy Council held that the Federal Court was in error for not examining the evidence and deciding as to whether the action there was bound to fail, though the power to dismiss an action summarily was a drastic power. The Privy Council went through the evidence with a fine-toothed and comb and decided to agree with the learned High Court at the first instance and restored the High Court’s decision. In conclusion, with great respect, the learned Judge could have avoided the pitfall as described by the Privy Council in Tractor. The lower court should have scrutinised the evidence in order to decide whether was bound to fail. If so, it would have been found otiose to send the case back to its starting point to start its long and expensive court albeit such a conclusion was reached on an application filed under O.18 r.19. [20] The Supreme Court in Bandar Builder Sdn Bhd v United Malayan Banking Corp Bhd [1993] 2 AMR 1969 held as follows: The principles upon which the court acts in exercising its power under any of the four limbs of O18 r.19(1) RHC are well settled. It is only in plain and obvious cases that recourse should be had to the summary process under this rule (per Lindley MR in Hubbuck & Sons Ltd v Wilkinson, Heywood & Clark Ltd), and this summary procedure can only be adopted when it can be clearly seen that a claim or answer is on the face of it obviously unsustainable (see AG of Duchy of Lancaster v L & NW Rly Co). It cannot be exercised by a minute examination of the documents and facts of the case, in order to see whether the party has a cause of action or a defence (see Wenlock v Moloney & Ors). The authorities further show that if there is a point of law which requires serious discussion and the point set down for argument under O.33 r.3 (which is in part material with our o.33 r.2 of the RHC) (see Hubbuck & Sons Ltd v Wilkinson, Heywood & Clark Ltd). The court must be satisfied that there is no reasonable cause of action or that the claims are frivolous or vexatious or that the defences raised are nit arguable. [21] In the case of Seruan Gemilang Makmur Sdn Bhd v Kerajaan Negeri Pahang Darul Makmur & Anor [2016] 3 CLJ 1, the Federal Court addressed the test for striking out applications, stating that – The basic test for striking out as laid down by the Supreme Court in Bandar Builder (supra) is that the claim on the face of its must be obviously unsustainable. D. SUBMISSION BY THE DEFENDANT [22] The defendant asserted that the plaintiff owed the total sum of RM936,644,754.19 as of 20 October 2023 under the Term Loan Facilities. The plaintiff, having benefited from various facilities provided by the defendant, has defaulted on repaying these facilities. The plaintiff is bound by the terms of the letter of offer and the security documents for the RM476,000,000.00 and is barred from claiming that the defendant charged an excessive interest rate. [23] To prevent the defendant from taking further action under the facilities agreement, the plaintiff initiated this lawsuit. The plaintiff's main contention was that the defendant failed to investigate the alleged irregularities in issuing the certified certificate of practical completion dated 31 December 2019, before making payment under the Bank Guarantee on 30 January 2020. [24] The defendant additionally stated that the issuance of the letter of demand dated 25 October 2023, seeking the recall of the Term Loan Facilities, was carried out in good faith. This action arose from the plaintiff’s default on repayment under the Term Loan Facilities. [25] Accordingly, the defendant asserts that it is entitled to exercise all rights under the security documents to recover all sums owed by the plaintiff related to the Term Loan Facilities. The plaintiff lacks a valid cause of action against the defendant, and the plaintiff’s claim is intended as a tactical maneuver to forestall and delay the defendant’s efforts to recover funds from the plaintiff under the Term Loan Facilities, as well as to evade the plaintiff’s obligations under the loan and security documents. E. SUBMISSION BY THE PLAINTIFF [26] The plaintiff argues that they have a reasonable cause of action against the defendant and bona fide serious issues to be tried, which necessitates the hearing of viva voce evidence. [27] The main issue raised by the plaintiff is that the issuance of the Certificate of Practical Completion (CPC) is irregular, as it was not issued in accordance with the conditions of the construction contract for the project and the guidelines of Pertubuhan Arkitek Malaysia (PAM). The plaintiff relies on the case of Uniphone Telecommunications Bhd v Bridgecon Engineering Sdn Bhd & Anor [2011] 5 MLJ 875, which determined that whether the CPC was validly issued is a triable issue. [28] The plaintiff asserts that the Bank Guarantee should only be called once the CPC is appropriately issued. If the answer is negative, the Bank Guarantee of RM476,000,000.00 should not be invoked, and the defendant should not disburse the entire sum to the main contractor. The defendant should have verified the terms of the CPC issuance before releasing the payment under the Bank Guarantee. [29] The second issue raised by the plaintiff is that the defendant changed the nature of the Bank Guarantee, which has prejudiced the plaintiff's rights. The plaintiff submits that the call on the Bank Guarantee by the main contractor is unconscionable. The Bank Guarantee of RM476,000,000.00 was called upon the issuance of the CPC, and the sum has been released to the main contractor. [30] Furthermore, the plaintiff asserts that the call on the Bank Guarantee by the main contractor is irregular, as there was no joint site inspection or handover of the works to the plaintiff. The plaintiff did not receive any funds from the sum released; instead, the plaintiff incurred a loss from the project and was compelled to pay the Term Loan arising from the unconscionable Bank Guarantee. F. ISSUES TO BE DECIDED [31] Based onsubmissions from both parties, the relevant issues to be decided are as follows: