Construction Stage (Building Works) February 2025 79) PW 1 after reviewing the Malaysian House Price Index between the 1st quarter of 2020 to the 2nd quarter of 2021, showed a declining trend in the average price showing a -2.7% reduction in the price, and a press release dated 15.9.2021 from the National Property Information Centre stipulated that the property sales trend between the 1st quarter of 2021 showed an increase when compared against similar quarter in 2020; PW 1 then , using the ‘before and after’ method, made a comparison between the Phase 3 FBS (November 2019) and Phase 3 FBS (February 2022) are as follows: No. Key Item Phase 3 FBS (Building Plan approval by November 2019) (RM) Phase 3 FBS Building Plan approval by February 2022) (RM) A Sales Revenue / GDV 383,893,920.00 383,893,920.00 B Project Costs 248,722,156.00 390,904,944.00 C Land Cost 48,600,000.00 48,600,000.00 Development Profit 86,571,764.00 -94,336,675.00 80) PW1 then testifies that the Plaintiff would only be able to collect the full forecasted development “profit” by end February 2025, which is by way of interest earning, i.e., by putting them into a deposit account. 81) Thus, PW1 calculated the Plaintiff’s loss here by assuming the annual simple interest rate of 5% per annum, the interest amount that the Plaintiff may generate from June 2024 to February 2025 (8 months) is RM2,885,725.47. Alternatively, if based on compounded interest rate of 5% per annum, the interest that may be generated is RM2,928,161.49. 82) In response to the Plaintiff’s above estimation of their loss of profit, the Defendant had through their expert DW1 Ir. Ting Chek Choon, produced their own report but I find that the same did not challenge PW1’s method of computation and assessment. 83) I have noted that the Court of Appeal case of Kumpulan Prasarana Rakyat Johor Sdn Bhd v Emercon Bina Sdn Bhd and another appeal [2021] 1 MLJ 629 where it was contended by the Plaintiff that this Court should accept PW1’s assessment of the Plaintiff’s loss of profit if the assessment stood unrebutted and contradicted. 84) However, this Court is to balance this against the principle in Malayan Cement Industries Sdn Bhd v Golden Island Shipping (L) Bhd [2018] 1 CLJ 228 where the Court of Appeal held: “[21] In addition, there is a general duty requiring that reasonable steps to be taken to mitigate losses flowing a breach particularly in the case of anticipatory breach. The party who has failed to mitigate the losses cannot later recover any such loss flowing from his neglect” 85) Be that as it may, I find after due consideration that PW1’s findings are based on an estimated feasibility study and not on actual figures which are backed by any documents provided to PW1 or produced by PW1 in the course of the trial. PW1’s said report in fact expressly states under the heading “Key limitations and Assumptions” that PW1’s report was ‘…solely based on the Feasibility Study…which was prepared by Pesat Bumi Sdn Bhd (“the Plaintiff”) and that there was no real data as to costs information made available by the Plaintiff. 86) A feasibility study is at most an estimate of the figures referred to therein as its purpose is to evaluate the project's potential for success and which is normally prepared for potential investors and lending institutions. There are of course, many factors which may arise which would vary or change the figures subsequently when the Project is kicked off and when the Project is eventually completed due to lack of sales target, escalating construction costs, potential delays and the like. As such this Court cannot consider the feasibility study as a document which proves actual profit. 87) In the circumstances the evidence of PW1 is with the greatest of respect not of guidance to this Court and I rely on Sime UEP Properties Sdn Bhd v Woon Nyoke Lin [2002] 3 CLJ 719 where the Court of Appeal held: “…in order to succeed in claims for damages for loss of profit one must establish the actual losses one would have suffered as a result of the breach. A projection as in this case is not sufficient to establish the would-be losses of profit. A venture into a business would not necessarily mean that one can make a profit out of it because there are instances where people suffer losses. Not all businesses end up with profit. It is clear to us that the Respondent failed to establish the expected losses as a result if the breach …” 88) I hold that in the overall analysis the Plaintiff had failed to show proof of the actual losses incurred and in the circumstances this Court is unable to compute or award the same. This Court will thus only award nominal damages based on the authority of Popular Industries Limited v Eastern Garment Manufacturing Sdn Bhd [1989] 3 MLJ 360, where Edgar Joseph Jr J (as he then was) had this to say: “In this context, I am reminded of Lord Goddard's dictum in Bonham-Carter v Hyde Park Hotel [1948] WN 89 quoted with approval by Thomson CJ in Lee Sau Kong v Leow Cheng Chiang [1961] MLJ 17, namely, that: [2009] 4 MLJ 610 at 666 The plaintiffs must understand that if they bring actions for damages it is for them to prove their damage; it is not enough to write down the particulars, and so to speak, throw them at the head of the court, saying, 'This is what I have lost, I ask you to give me these damages'. They have to prove it. Accordingly, all I can do is to make an award of nominal damages of US$500 that being the currency of the contract (see Miliangos v George Frank (Textiles) Ltd [1975] QB 487) which I hereby do.” 89) As to what amounts to nominal damages and the nominal damages to be awarded, I refer to and rely on the Court of Appeal authority of Koperasi Kastam Diraja Malaysia Bhd v Yi Go Group Sdn Bhd [2021] 5 MLJ 590 where the said Appellate Court held: “[72] Where there is loss or damage suffered but the party claiming has failed to prove the damages, then only nominal damages would be awarded. [73] The Federal Court in Guan Soon Tin Mining Co v Wong Fook Kum [1969] 1 MLJ 99 at p 100 enunciated this principle as follows: The respondent, as plaintiff, of course had to discharge the burden of proving both the fact and the amount of damages before he could recover. Where he succeeded in proving neither fact nor amount of damage he must lose the action or, if a right was infringed, he would recover only nominal damages. Where he succeeded in proving the fact of damage, but not its amount, he would again be entitled to an award of nominal damages only. This statement of the law is concisely stated in Mayne & McGregor on Damages (12th Ed) para 174 … (Emphasis added.) [74] The learned registrar had awarded RM100,000 as nominal damages. We are rather uncomfortable in calling such a substantial amount as ‘nominal’. Generally, the term ‘nominal’ means minuscule or small in terms of amount or just a token sum. [75] In Beaumont v Greathead (1846) 2 CB 494 at p 449, Maule J described nominal damages as ‘a sum of money that may be spoken of, but that has no existence in point of quantity’. Often nominal damages are referred to as a token sum awarded where the amount could be small or miniscule (see Sapwell v Bass [1910] 2 KB 486). [76] However a sum of RM100,000 as nominal damages for breach of contract is not without precedent as can be seen in the case of Delpuri-Harl Corp JV Sdn Bhd v Perbadanan Kemajuan Negeri Selangor [2015] 2 MLJ 24 where the Court of Appeal explained as follows: [71] As the appellant had failed to elect to claim either for loss of profits or for wasted expenditure only, and the claim being bad for uncertainty in the circumstances, we decided to award the sum of RM100,000 which sum included the sum of RM70,575.45 assessed by DW1, as nominal damages to the appellant. This is on the basis that this court recognises the fact that the appellant did suffer some loss as a result of the wrongful termination. [72] As for nominal damages they are said to be ‘a sum of money that may be spoken of, but that has no existence in point of quantity’ as held by Maule J in Beaumont v Greathead (1846) 2 CB 494 at 499. [73] A token sum is usually awarded for nominal damages and the amount could be small or miniscule. Just like sixpence in Feize v Thompson (1808) 1 Taunt 121; a farthing in Mostyn v Coles (1862) 7 H & N 872 and a shilling in Sapwell v Bass [1910] 2 KB 486. [74] Undoubtedly, the cases cited above were decided in England in yester years. However, today it is not uncommon for nominal damages to be awarded in Malaysia in the thousands of ringgits, depending of course on the circumstances of the case. And in the case ofTahan Steel Corp Sdn Bhd v Bank Islam Malaysia Bhd [2012] 2 MLJ 314 (CA), my learned brother Justice Mohd Hishamudin had occasion to say that the learned trial Judge was correct in awarding nominal damages of RM50,000 in the circumstances of that case. [75] Where it is clear that the appellant had failed to furnish credible evidence to prove the amount of damages it claimed to have suffered but where it is equally clear that the appellant did suffer some loss and damage , then it will be an appropriate case for the court to award nominal general damages (see Lee Sau Kong v Leow Cheng Chiang [1961] 1 MLJ 17 per Thompson CJ).” 90) Taking the cue from the aforesaid case, I am thus awarding the sum of RM100,000.00 as nominal damages to the Plaintiff for breach of contract but this sum is to be reduced by 20%, as per my decision above on liability of the Defendant, making the sum awarded to the Plaintiff as RM 80,000.00 only. I am also awarding 5% interest per annum on this Judgement Sum from the date of filing of this Suit until full settlement, as well as cost to the Plaintiff for their claim. 91) The Plaintiff had also claimed in its Statement of Claim for General Damages to be assessed by this Court, but had not made any submissions to this Court on the same. I am thus not allowing such claim. 92) For the record, the Court has also disregarded prayer a in paragraph 65 of the Plaintiff’s Statement of Claim vis a vis the Letter of Release as it is now academic in view of the Consent Order dated 9.9.2021 recorded before this Court for the said Letter of Release. The Defendant’s Counterclaim 93) In this matter before the Court, the Defendant has also filed a Counterclaim against the Plaintiff for a sum of RM651,449.50 for alleged work done for the Project which is calculated up to 2.8.2019, the breakdown of which is as follows: - Phase 1 (8 units of semi-detached house and 1 unit of bungalow) Progressive Claim No. 1 Stage A – Upon Approval of Layout Plans (5%) Stage B - Upon Approval of Engineering Plan (10%) Stage C – Upon Completion of Tender Drawings (5%) Progressive Claim No. 2 Stage E – Upon Completion and Issuance of Construction Drawings (5%) RM25,079.60 RM6,269.90 Phase 3 (386 units of condominium) Progressive Claim No. 1 Stage A – Upon Approval of Layout Plans (5%) Stage B - Upon Approval of Engineering Plan (10%) Stage C – Upon Completion of Tender Drawings (5%) Stage E – Upon Completion and Issuance of Construction Drawings (5%) Progressive Claim No. 2 Stage E – Upon Completion and Issuance of Construction Drawings (5%) RM496,080.00 RM124,020.00 94) In the trial, PW2, Low Kheng Hua, who is the architect of the Project, had confirmed during examination-in-chief, that the Defendant’s completed works as per the Plaintiff’s instruction were only as follows:- Stage Professional fee Stage Claim Percentage Phase 1 Phase 2 1 Upon Approval of Layout Plans 5% Completed (19.10.2018) -- 2 Upon Approval of Building Plans 10% Completed (12.6.2019) -- 95) The above is corroborated by by DW1 based on the evidence furnished. I therefore hold that such works/services above stated were indeed provided by and completed by the Defendant. 96) The main contention here in the Defendant’s counter claim would be for the works /services upon completion of tender drawings (5%). Here PW2 had testified during examination-in-chief that the approval of the Planning Permission had encountered delay due to compliance of technical requirements and that the Plaintiff had intention to review the components from Condominium to Serviced Apartments, where after the Plaintiff had then requested all Consultants to put on hold all works while pending for them to work with DCA on the new serviced apartment design after the CCM No.21 held on 27.6.2018. 97) It was then alleged that CCM No.22 was then called on 29.7.2019 to resume the works and that there should be no works from any Consultants as per the Plaintiff’s instruction between the period of 27.6.2018 to 29.7.2019. With respect I have, after reading the said documents in toto, agree with the aforesaid Plaintiff’s contention. 98) My said decision above is also in consonant with the evidence at trial that none of the other consultants had actually worked beyond the Planning Permission stage as testified by PW2. 99) It is in evidence that DW2, Sha Chaim Chuan, the Defendant’s Managing Director, had at the trial explained that the drawings submitted for building plan approval are also the drawings for tender purpose and the tender can be called for. This is contrary to the evidence of the Plaintiff via PW 2 who testified that the Defendant should not have produced the Tender Drawings without the approved layout plans and the instruction by the Plaintiff to proceed further as the work programme distributed on 26.10.2017 was no longer relevant as the works were delayed by the approval of layout plans and planning permission. 100) After due consideration of the above contradictory testimonies, and based on the evidence of CCM no. 21 and 22 respectively, I hold that the Defendant should have halted its works / services between the period of 27.6.2018 to 29.7.2019 with regards the drawings submitted for building plan approval for the Phase 3 (386 units of condominium) drawings. I find that the Defendant had failed to prove or show any evidence at the trial that the Plaintiff had instructed them to commence work for the said phase 3 (386 units of condominium). 101) I therefore hold that the Defendant is consequently not entitled to the sum of RM496,080.00 for Progressive Claim No.1 and RM 124,020.00 for Progressive Claim No. 2 in respect of the Phase 3 (386 units of condominium) drawings. 102) As this Court had earlier held that the Defendant was to provide by mutual consent to the Defendant the C&S services only and that the fees payable was only 1.3% of the total construction costs and that only stage 1 and 2 of the Defendant’s professional services were completed and rendered for the Approval of Layout Plans and the Approval of Building Plans respectively for Phase 1 and 2 of the Project and that neither stages thereafter were done by the Defendant and/or were not approved by the Plaintiff’s architect as well that the alleged works carried out for Phase 3 were also not approved by the Architect; I am awarding the Defendant the claims for stage 1 and 2 only i.e. a total of only 15% of the professional works/services which were done and approved for Phase 1 and 2 of the Project. 103) However, I am again unable to quantify the quantum of professional fees, reasonably entitled by the Defendant for services which it has completed in accordance to the said Contract of 7.7.2014 as the same was subject to the Construction Costs of the Project which was based on the Feasibility Studies conducted by the Plaintiff and were, as indicated by me above, not proven to this Court to be the actual figures or amounts for the Project. 104) I am therefore again constrained to only award nominal damages for the services rendered by the Defendant to which I am making the award of RM10,000.00 only to the Defendant with interest at the rate of 5 % per annum on the Judgement Sum until full settlement and party to party costs of the Defendant’s Counter Claim. 105) As I have decided that the Plaintiff had rightfully terminated the Contract, I am disallowing the Defendant’s claim for the disruption fee of RM325,724.75 (inclusive of 6% SST) which the Defendant’s states it is entitled to for the unlawful termination of the Contract. Conclusion and Final Decision 106) In conclusion this Court holds that the Defendant is in breach of the Contract dated 27.3.2017 and the amount assessed by this Court to be paid to Plaintiff by the Defendant is the nominal sum of RM80,000.00 to which I have found that liability is partly attributable to and therefore apportioned to the Plaintiff on a liability of 20% of the said breach. The Court has also awarded interest at the rate of 5 % per annum on the Judgement Sum until full settlement and costs to the Plaintiff for their claim. 107) The Defendant’s Counter Claim for work done or services rendered is only allowed for stages 1 and 2 of the Defendant’s professional services for the Approval of Layout Plans and the Approval of Building Plans respectively for Phase 1 and 2 of the Project only being 15 % of the services rendered only. 108) I have also only awarded nominal damages of RM10,000.00 to the Defendant for their Counter Claim as mentioned above together with interest at the rate of 5 % per annum on the Judgement Sum until full settlement. I have further awarded party to party costs only to the Defendant for their Counter Claim. Dated: 15th day of January 2024 sgd. NADZARIN WOK NORDIN HIGH COURT JUDGE CONSTRUCTION COURT 1 COUNSEL FOR THE PLAINTIFF: Ringo Low Kim Leng and Brandon Lim Zhung (Messrs Ringo Low & Associates] COUNSEL FOR THE DEFENDANT: Alan Lim Wei Lun (Messrs The Law Office of Anil & Tan]