WA-24C-191-12/2025 Kand. 21 12/06/2026 10:08:34 IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR IN THE FEDERAL TERRITORY OF WILAYAH PERSEKUTUAN KUALA LUMPUR, MALAYSIA (CONSTRUCTION DIVISION) ORIGINATING SUMMONS NO.: WA-24C-193-12/2025 In the matter of an Adjudication between PLP Electrical Engineering Sdn. Bhd. (Claimant) and Kerjaya Prospek (M) Sdn. Bhd. (Respondent) And In the matter of an Adjudication Decision by Karen Ng Yueh Ying dated 2.10.2025 And In the matter of Section 15 (b) and (d) and Section 16(1)(a) and (b) of the Construction Industry Payment and Adjudication Act 2012 (CIPAA); And In the matter of Order 5, Order 7, Order 28, Order 69(A) Rule 2, Rule 3, Rule 4 and Order 92 Rule 4 of the Rules of Court 2012 BETWEEN KERJAYA PROSPEK (M) SDN BHD (No. Syarikat: 352407-U) ...PLAINTIFF AND PLP ELECTRICAL ENGINEERING SDN BHD (No. Syarikat: 453327-T) ...DEFENDANT (HEARD TOGETHER WITH) IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR IN THE FEDERAL TERRITORIES, MALAYSIA ORIGINATING SUMMONS NO.: WA-24C-191-12/2025 In the Matter of the Enforcement of an Adjudication Decision dated 02.10.2025 by Ms. Karen Ng Yueh Ying under the Construction Industry Payment and Adjudication Act 2012 ("CIPAA") And In the Matter of Order 5, Order 7, Order 28, Order 69A and/or Order 92, rule 4 of the Rules of Court 2012 And In the Matter of Section 28 of CIPAA BETWEEN PLP ELECTRICAL ENGINEERING SDN BHD (No. Syarikat: 453327-T) ...PLAINTIFF AND KERJAYA PROSPEK (M) SDN BHD (No. Syarikat: 352407-U) ...DEFENDANT GROUNDS OF JUDGMENT