(C) to claim interest on the unpaid amount under Clause 30.17 Although the express remedies available to the contractor under the PAM Contract 2006 are much wider than most of the contemporary forms used in the country, it nevertheless 55 does not entitle the contractor to slow-down or reduce the rate of executing work (see Kah Seng Construction Sdn Bhd v Selsin Development Sdn Bhd [1997] 1 CLJ Supp 448); he has to suspend the execution of the works completely.”. [68] The Defendant additionally emphasised that the Plaintiff has a duty to proceed with the works diligently under Clause 23.6 read together with Clause 25.1(c) of the Contract. Reliance was placed on the authority of Supamarl Ltd v Federated Homes Lrd [1981] 9 ConLR 25 in submitting that, by slowing down works in express breach of a duty to proceed diligently with works, is a repudiatory breach. [69] In sum, the Defendant takes the position that the Plaintiff cannot rely on late payments to entitle the Plaintiff to slow down the performance of works and claim for EoT. Assuming that the Plaintiff was entitled to EoT, it would only be for the period that it had suspended works between 5.11.2018 and 24.12.2018, but this period was rejected by the Plaintiff itself. 56 [70] The attention of the Court was drawn to the payment record as at 13.11.2019 as tabulated in para 13 of the AIS which shows that payments have been made in respect of Claim Nos. 30 to 45 whilst payment for Claim No. 46 was due only on 8.11.2019 (payment vouchers and bank statements from August 2015 to September 2019 were exhibited). In para 47 of the AIR, the Defendant admitted that the payments were late, however all Certificates Nos. 1 to 45 have since been paid. Thus, the fact that the Defendant has paid all that is due to the Plaintiff up until 11.10.2019 is clearly established but on 15.10.2019, the Plaintiff stopped the works. [71] From a perusal of the numerous correspondence and other documents as exhibited in the affidavits, it is evident that the issues arising as a result of the dispute between the parties, among others, as to whether the fault for the delay in the Project lies with the Plaintiff or the Defendant; the Plaintiff’s entitlement to an EoT; and the validity of the determination of the Plaintiff’s employment by the Defendant (where apart from the issues discussed earlier, the late issuance of the AI and approval of the VO; the determination of P&M as the sub-contractor 57 for the Project; the alleged acts of prevention by the Defendant; change in the format of certification; and the purported failure by the Architect to act fairly and impartially were among the matters raised in the communication between the parties) are highly contested and must be determined in a full trial. In these circumstances, it is not misplaced for the Defendant to rely on the decision of the High Court in Daya CMT (supra) where it was held, inter alia, that: “[69] As can be seen, the Plaintiff's entitlement to extension of time is something for the Plaintiff to prove and not a given as is clear from the qualification in the words "(if any)". In as much as the Plaintiff may put in fresh application for EOT, the Consultants are not required to re-assess it especially if no fresh grounds are canvassed. All that the Consultants have said is that if the application is based on the same reason, then what they have decided stands. There is nothing unconscionable about that. … 58 [72] The Plaintiff by its letter of 8 April 2013 admitted the delay was due to the non-performance of its subcontractor, Million Aim Sdn Bhd and agreed to replace the subcontractor with another. Such disputes on extension of time and the number of days of entitlement are a fertile area of conflict in a construction contract and in the absence of cogent evidence of unconscionability in rejecting the EOT application or in giving less than what is reasonably applied for, this Court would not at this stage conclude that a strong prima facie case of unconscionability has been made out. Whether or not an EOT application should have been granted and if so for how long, would be a matter for trial. At this stage even if an EOT application has not been considered reasonably or has been rejected unreasonably, that does not, in the absence of some egregious element, amount to an unconscionable conduct.”. 59 (emphasis added) [72] Similarly in the case of JK Integrated (supra) the Singapore High Court rejected the application for an injunction because, among others, it was open to the plaintiff in that case to challenge the architect’s decision in arbitration and at best, casting aside the merits of the allegations hurled against the first defendant, all that the plaintiff had shown was that “… there were genuine disputes to be tried as to which party bore the contractual responsibility for the delays.”. [73] During the hearing of the application, Mr. Ekbal Singh submitted that the facts in Daya CMT can be distinguished. When pressed further by the Court, learned counsel was not able to articulate as to the basis for his submission. [74] At the time of writing this judgment, the Court had already allowed the Defendant’s application for a stay of proceedings pending reference of the dispute to arbitration with costs of RM5,000.00 to be paid by the 60 Plaintiff to the Defendant, subject to allocator. This order was made on 29.7.2020. [75] Taking the Plaintiff’s case at its highest, it can certainly be concluded that disputes are aplenty and these tantamount to triable issues which may, in the end, result in a finding of breach of contract by either or both parties. The mere fact that there is a retention sum, does not mean that the call on the PB was unconscionable. Looking at the Plaintiff’s application in its totality, I am unable to conclude that the Plaintiff has provided sufficient evidence to enable the Court to be satisfied that there is a strong, prima facie case of unconscionability to an extent that is sufficient for the Court to be minded to order the injunction as sought. [76] In the absence of unconscionable conduct on the part of the Defendant, this Court would not restrain the call made on the PB as to do so would strip the PB of its efficaciousness and purpose of the insertion of a provision on the PB in the LoA and the Contract in the 61 first place (see Bella Builders Sdn Bhd v. Kerajaan Malaysia & Anor [2017] 1 LNS 558).