that “… the presence of CASES, the state of abandonment of the project, the change of design, the need to carry out strengthening and underpinning works; the Respondent’s argument that on the one hand that there was ‘no handing over vacant possession’, and on the other hand that there was only a ‘partial handing-over of the site’: drawing all these strings together, I am more inclined to believe the Claimant’s argument that there was a delay in the handing over of the vacant possession of the site as opposed to placing the blame entirely on the Claimant and relinquishing the respondent of all blame as to delay.”. [69] The Arbitrator did not rewrite the terms of the Contract as alleged by PSSB, but rather, he made a finding of mixed facts and law (involving the interpretation of the provisions in the LoA) with regards to Vistasik’s pleaded case that PSSB had delayed in handing over vacant possession of the site to Vistasik. [70] In my opinion, PSSB has not discharged the burden of proving Ground 2 whether in terms of the Jurisdiction Point and/ or the Natural Justice Point (for the same reasons as explained in respect of the 1st Ground). 3rd Ground: Jurisdiction Point [subparas 37(1)(a)(iv) and 37(1)(a)(v) AA 2005] and Natural Justice Point [subpara 37(1)(b)(ii) AA 2005] – Whether PSSB had failed or delayed in providing confirmations, drawings, layouts or plans (Ground No. 4 in the Award) [71] On 4.7.2012, Vistasik wrote to the Architect confirming that it was able to complete the whole works by 31.3.2013, which was the completion date granted by EOT-1, provided that the information, drawings and decisions be made available accordingly by the deadline indicated. The letter goes on to list 3 items under “Outstanding information to be confirmed by July 7,2012”, 12 items under “Outstanding construction drawings to be issued by July 15, 2012”, 8 items under “Nomination of sub-contractors by July 31, 2012”, 4 items under “Appointment of suppliers by July 31,2012” and 11 items under “Confirmation for Provisional Sums by July 31, 2012”. As observed by the Arbitrator in para 66 at p 148 of the Award, there is a total of 38 items which required the Architect’s confirmation. [72] Subsequently, Vistasik sent six reminders to the Architect until 12.10.2012 but no replies were received from the Architect. [73] At the arbitration, Vistasik took the position that the issuance of the Default Notice was substantially due to the Architect’s delay in providing the information etc. required by Vistasik to complete the Works. PSSB refuted this allegation. - The Parties’ Contentions [74] The Jurisdiction Point raised by PSSB was that the Award deals with an issue which was not contemplated or within the scope of submission to arbitration because in paras 9 - 19, pp 152 - 161 of the Award, the Arbitrator wrongly considered arguments advanced by PSSB on the issue of delivery of vacant possession of the site in addressing the issue of whether PSSB had failed or delayed in providing confirmation, drawings, layouts or plans. [75] PSSB also claimed that the Arbitrator had disregarded clear evidence elicited under cross-examination and documentary evidence and instead took great pains to look for inconsequential and insignificant evidence to redeem Vistasik’s case. In short, PSSB accused the Arbitrator of bias and this tantamount to a breach of natural justice. [76] By way of retort, Vistasik submitted that the Arbitrator had considered all evidence elicited in the arbitration proceedings and had substantiated his findings with thorough and elaborate reasoning. Mr. J. Chandra argued that PSSB was treating the Setting Aside Application as an appeal and opening issues which have been heard in its finality in the arbitration. - The Findings of the Court [77] The Jurisdiction Point can be dealt with swiftly. A scrutiny of paras 9 - 19 under “Respondent’s arguments” at pp 152 - 161 of the Award shows that these are similar to paras 14 - 28, also under “Respondent’s arguments”, at pp 109 - 113 of the Award relating to “Ground 3 – Employer’s Delay In Handing Over Vacant Possession”. However, in the “Analysis” part of the Award from paras 58 - 119 at pp 146 - 161, delivery of site vacant possession is not mentioned at all. This shows that the Arbitrator did not wrongly consider arguments advanced by PSSB on the issue of delivery of vacant possession of the site when determining Ground No. 4 in the Award as alleged by PSSB. [78] PSSB’s submission on the Natural Justice Point as to the alleged bias on the part of the Arbitrator by citing the example of delay in the painting works can similarly be addressed speedily. [79] Section 20 of the AA 2005 provides that “The parties shall be treated with equality and each party shall be given a fair and reasonable opportunity of presenting that party’s case.”. [80] Based on the Arbitrator’s analysis of the issue, he had meticulously considered the documentary evidence such as the correspondence and Site Meeting Minutes, the oral evidence especially by CW1 and RW3, the Architect’s silence for 6 months in not answering Vistasik’s queries and the fact that the Architect, Ar. Tony Khoo Heng Peng was never offered as a witness despite having filed a Witness Statement (the architect that was called as a witness i.e. RW3 was not a registered architect and claimed to be the “main person assisting the Architect”) before stating that “… apart from the information relating to paint, which I think was delayed by the Claimant, the other items in paragraph (A) were not in fact provided to the Claimant. The cross-examination of the CW-1 or that of the other witnesses do not throw sufficient light for me to come to an opposite conclusion that these confirmations had in fact been granted.” (emphasis added, para 111 at p 159 of the Award; “paragraph (A)” refers to “Outstanding information to be confirmed by July 7,2012” in Vistasik’s letter dated 4.7.2012. See too, para 100 at p 155 of the Award where the Arbitrator referred to Site Meeting Nos. 54 to 61 before he said that “So here is the evidence that Respondent’s counsel was right when he suggested that in so far as painting had been concerned, the Claimant had been guilty of serious delay.”). [81] This was followed with para 119 at p 161 of the Award where the Arbitrator clearly held and decided that “… Ground-4 is proven – save only to the exception that as far as painting work was concerned, the Claimant had been delayed.” (emphasis added). [82] As seen from these excerpts in the Award, the Arbitrator in fact agreed with PSSB that Vistasik was at fault for the delay in the painting works. [83] Furthermore, as will also be apparent in respect of the other grounds of challenge to follow where bias on the part of the arbitral tribunal is raised, PSSB has simply thrown in the argument of bias without citing any case authorities at all as to the legal principles and test to be applied and whether the test has been fulfilled in this case. This Court has observed that applicants desiring to set aside arbitral awards and adjudication decisions often hurl such allegations just because they were not successful in the arbitration or adjudication proceedings. The parties have often been reminded about the seriousness of accusations of this nature and unless these can be substantiated, such contentions should not be easily made. [84] PSSB additionally submitted that the Arbitrator ignored the evidence showing that there were no outstanding information or drawings to enable Vistasik to complete the Works by 30.8.2013 and any such delay was dealt in Vistasik’s application for EoT, namely –