Term Loan 2 (‘TL’2’) in the sum of RM44,000,000.00. [6] RHB’s offer dated 03.09.2014 was accepted by the Defendant dated 05.09.2014. [7] In accordance with the rate prescribed in the contract, the Defendant owed professional fee to P in the sum of RM2,480,000.00. [8] The Defendant then proceeded to pay P certain commitment and administration fees in accordance with the contract in the sums of RM30,000.00 and RM50,000.00 respectively on different dates. [9] Under the RHB’s letter of offer (‘L/O’) dated 03.09.2014 the drawdown date for the overdraft and TL1 was 6 months from the date of acceptance of the offer while for TL2 the draw down was 15 months from that date. [10] Thereafter, in accordance with the terms of the L/O the Defendant received the first drawdown for the O/D and TL1 in March 2015. However, the Defendant allegedly refused, failed and/or neglected to pay the balance professional fee (‘P/F’) of RM2,400,00.00 in full and on time for P’s services in breach of the terms of the contract. Under Clause 5 of the contract, the manner of payment was by way of deduction of the P/F from Page 6 of 20 the receipt of the 1st drawdown of the loan whereby the Defendant was required to issue a Letter of Instruction (‘L/I’) to RHB to authorise the latter to deduct the fee from the loan and pay the amount directly to P’s account. The Defendant breached the contract by its refusal, failure and/or neglect to issue the L/I upon the 1st drawdown of the O/D and TL-1 facilities. Instead, the Defendant paid small amounts at random without adhering to any schedule and the total amount paid was far short of the amount of P/F due and owing under the contract to P. [11] Due to the inconsistent and unscheduled, short payments of the P/F by the Defendant, both parties executed a letter of settlement dated 19.8.2015, wherein the Defendant agreed to utilise the loans received from RHB to pay the amount due to P in instalments. No date could be fixed for the payment of the 1st instalment by the Defendant, who could only agree to payment “to the soonest”. The Defendant then made the 1st payment of RM100,000.00 only 2 months later. Thereafter, they only paid 5 instalments when demanded by P only and those too in part payments and also at random which were not in compliance with the agreed terms in the above letter of settlement. Page 7 of 20 [12] At that time, the Defendant further failed to honour their obligations to RHB and in utilising the loans received under the O/D and TL-1 facilities also breached the T&C of the loan, particularly in failing to obtain the necessary approval from the local authority before commencing their building project. Although some 2 years had lapsed after the loan approval by RHB on 03.09.2014, the Defendant had failed to do so which resulted in the facility TL-2 having to be held in abeyance by RHB who were dissatisfied with the situation and froze any further drawdown of TL-1. As a result, RHB fixed 4.09.2018 as the 1st drawdown of TL-2 subject to certain conditions being fulfilled by the Defendant. [13] The overall conduct of the Defendant and the relevant documents showed as follows: