January 18, 2019 for claim item Nos. 20 and 21. 23 | P a g e [38] Based on the affidavit evidence, I am satisfied that the amounts claimed in claim item Nos. 12, 13, 14, 20 and 21 are not completely new claims but they form part of the interim claims which had previously been submitted by MCE to Puncak Niaga as the value of works completed. It is observed that for claim item No. 14, a sum of RM25,825.20 was certified in IPC No. 32 and paid by Puncak Niaga. [39] MCE has merely rectified the errors in the amounts as stated in interim claim Nos. 29, 30, 38 and 39, in the payment claim. The adjudicator has rightly decided that it is acceptable for MCE to have the errors corrected in the payment claim and the fact that errors were made in the progress claims does not preclude MCE from making a claim under the CIPAA. Progress claims and interim certificates are neither final nor conclusive and the adjudicator has the power to review and revise any certificate issued or to be issued under s 25(m) of the CIPAA and to decide or declare on any matter notwithstanding that a certificate has not been issued under s 25(n) of the CIPAA (see Bina Puri Construction Sdn Bhd v Hing Nyit Enterprise Sdn Bhd [2015] 4 AMR 565). [40] I am thus satisfied that MCE is an "unpaid party" and Puncak Niaga is a "non-paying party" as defined under s 4 of the CIPAA and that the requirements of subsection 5(1) and (2) of the CIPAA as to what constitutes a payment claim have been fulfilled. [41] In the upshot, this court accepts the submissions by MCE that the adjudicator did not act in excess of his jurisdiction when he considered MCE's rectified claims in relation to claim item Nos. 12, 13, 14, 20 and 21 in the adjudication proceedings. Our Decision [49] The question here is whether, the Adjudicator exceeded his jurisdiction for having adjudicated on Mersing’s Payment Claim which included the Rectified Claims. At the outset, we may state that it is our finding that the Payment Claim that was submitted by Mersing is not premature and comes within s.5 (2) CIPAA as it is in respect of claims which are due under a Construction Contract. 24 | P a g e [50] As such, the Adjudicator has the requisite jurisdiction to deal with and determine the claim on its merits. The Rectified Claims were part of the Payment Claim and there are therefore within the jurisdiction of the Adjudicator. [51] Of course, a Payment Claim which is based on claims which are premature and not due (in futuro) are not claims which comply with the definition of Payment Claim per s.5 CIPAA. But that is not the case here. As the High Court observed in Syarikat Bina Darul Aman Bhd (supra), “…Once he has the jurisdiction, it is then within his powers to be exercised at his discretion, to decide on whether the claimant is entitled to the whole or part of its claims based on the evidence adduced.” Consequently, the Adjudicator’s decision relating to the particular claim does not go to the jurisdiction of the Adjudicator but is one which concerns the merits of Mersing’s claim. This involves the exercise of power by the Adjudicator under s.25 (m) and (n) CIPAA by which the Adjudicator may review or revise any certificate to be issued or to decide or declare on any matter notwithstanding no certificate has been issued. Mersing’s progress claim and the interim payment certificates are not final nor conclusive. As such, any error in the progress claims is capable of being rectified by Mersing before the completion of works under the project. The certification process is not at an end and attains finality when the final certificate is issued. 25 | P a g e [52] Therefore, as rightly submitted by Mersing, as these are interim claims, the amount cannot always be a wholly exact exercise as at that stage, there will be an element of assessment of judgement and with that the errors will be subject to adjustment and verification. Here, Mersing made the necessary adjustments and rectified the impugned items and presented it as part of the Payment Claim. We agree that this does not go to the jurisdiction of the Adjudicator. [53] In this regard, if in the ordinary course, the monthly claims which had been submitted by Mersing had been verified and certified by Puncak Niaga per clause 8.1 LOA, then errors may have been picked up by Puncak Niaga. But that did not happen as the monthly claims were just not certified. The employer’s failure or refusal to certify the claim does not take the matter out of the ambit of CIPAA. There is no doubt at all that in the Adjudication Proceedings, the Adjudicator has statutory power under s.25 (m) to “review and revise any certificate issued or to be issued pursuant to a construction work contract, decision, instruction, opinion or valuation of the parties or contract administrator relevant to the dispute” and under s.25 (n) to “decide or declare on any matter notwithstanding no certificate has been issued in respect of the matter”. [54] Hence, despite Puncak Niaga’s non-certification of Mersing’s monthly claims, the Adjudicator is nevertheless statutorily empowered to adjudicate upon the items which make up the Payment Claim. It is for the Adjudicator to decide whether to allow the whole or any part of the amounts stated in the Payment Claim. 26 | P a g e [55] It was contended that on behalf of Puncak Niaga that since Mersing had by-passed the claims submission and verification route via clause 8.1 LOA, there was no amount that was due and Mersing had no cause of action vis-à-vis the impugned items. There is no merit in this argument. In our view, given the circumstances of non-certification and non-payment by Puncak Niaga, the full details of claim have been stipulated in the payment claim, it is clear that Mersing was “unpaid party” and Puncak Niaga a “non-paying party” under CIPAA, entitling Mersing to lodge a Payment Claim under CIPAA, albeit part of it consisted of the Rectified Claim. [56] It is quite obvious that the Rectified Claim relates to work done, for which claims had previously made to Puncak Niaga which were not certified. Thus, when the Rectified claim was made as part of the Payment Claim, they were not new claims but a scaled down version of an earlier claim which contained erroneous figures. Puncak Niaga’s objection is that the impugned items consisted of claim amounts which Mersing had unilaterally “rectified” without any prior reference to Puncak Niaga. The “rectification” of the amounts was due to errors in the amounts previously claimed by Mersing in the monthly claims. These value of the five items is RM93,577.70. [57] In our view, the Rectified Claims were merely a “refinement” of the previously submitted monthly claims. Thus, if it is not a new claim and is merely a refinement of a claim which had previously been submitted to the employer, then it is valid for purposes of adjudication proceedings. See: William Verry (Glazing Systems) Ltd v Furlong Homes Ltd [2005] EWHC 138 (TCC)], and OSC Building Services Ltd v Interior Dimensions Contracts Ltd [2009] EWHC 248 (TCC). 27 | P a g e [58] In the context of the present appeal it is I think relevant to refer to the decision of the English High Court in Witney Town Council v Beam Construction (Cheltenham) Ltd [2011] EWHC 2332 (TCC), [2011] CILL 3090,139 Con.LR 1, [2011] BLR 707, [2011] TCLR 8 (HC) where Akenhead J. said that the refinement of a pre-existing dispute does not take that dispute out of the jurisdiction of the Adjudicator. This is how the Judge put it: