Content
1 IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR IN THE STATE OF WILAYAH PERSEKUTUAN, MALAYSIA (CIVIL DIVISION) ORIGINATING SUMMONS NO: WA-24C-98-06/2017 In the matter of Adjudication between PWC Corporation Sdn Bhd and Ireka Engineering & Construction Sdn Bhd under Construction Industry Payment and Adjudication Act 2012 And In the matter of an Adjudication Decision dated 18.5.2017 issued by Steven Seah Shu Keen, Adjudicator And In the matter of Section 28 of the Construction Industry Payment and Adjudication Act 2012 And In the matter of Orders 7 and 28 of the Rules of Court 2012 BETWEEN PWC CORPORATION SDN BHD (Company No: 233329-T) … PLAINTIFF AND 2 IREKA ENGINEERING & CONSTRUCTION SDN BHD (Company No: 381566-U) … DEFENDANT (heard together with) IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR IN THE STATE OF WILAYAH PERSEKUTUAN, MALAYSIA (CIVIL DIVISION) ORIGINATING SUMMONS NO.: WA-24C-124-07/2017 In the matter of the Adjudication Proceedings between PWC Corporation Sdn Bhd as Claimant and Ireka Engineering & Construction Sdn Bhd as Respondent pursuant to the Construction Industry Payment and Adjudication Act 2012 And In the matter of an Adjudication Decision dated 18.5.2017 by the Adjudicator, Steven Seah Shu Keen And In the matter of Section 15 and 16 of the Construction Industry Payment and Adjudication Act 2012 And 3 In the matter of Order 7 of the Rules of Court 2012 BETWEEN IREKA ENGINEERING & CONSTRUCTION SDN BHD … PLAINTIFF (Company No: 381566-U) AND PWC CORPORATION SDN BHD … DEFENDANT (Company No: 233329-T) THE JUDGMENT OF Y.A. LEE SWEE SENG Project [1] Ireka Engineering & Construction Sdn Bhd (“Ireka”) is the Main Contractor for the project known as "Cadangan Pembangunan yang mengandungi 2 Blok Menara Pejabat 17 & 31 Tingkat, 1 Blok Kompleks Membeli Belah 4 Tingkat dengan Kemudahan Rekreasi, di atas Tempat Letak Kenderaan Bawah Tanah dan Ruang Perdagangan 4 Tingkat Di Atas lot PT 17741 (Sebahagian Lot PT 21755) Jalan Kiara, Mont Kiara, Mukim Batu, Kuala Lumpur untuk Tetuan Ireka Land Sdn Bhd" (“Mont Kiara Project”). 4 [2] Ireka appointed PWC Corporation Sdn Bhd (“PWC”) as a subcontractor by a Letter of Award dated 15 September 2009, for the ‘supply and installation of Aluminium Composite panel to isolated columns at basement P1 and podium retail areas Lot PT 17741, Jalan Kiara, Mont Kiara, Mukim Batu, Kuala Lumpur“ (“the Contract"). Problem [3] PWC carried out the works for the said Project. Throughout the said Project, PWC had issued two progress claims and a final progress claim. PWC had duly completed the works as well as the variation order in relation to the said project. The total final amount claimable was for the sum of RM545,170.87. [4] Upon submission of the final claim to Ireka, the parties negotiated on the amount for the total work done. On 8.10.2014, Ireka sent an email to PWC informing PWC that the total amount of work done amounted to RM521,929.67. Subsequently PWC agreed to this sum. [5] However Ireka failed to pay the outstanding sum or RM134,869.25 to PWC. PWC was only paid the sum of RM387,060.42 for the works done and the balance of the sum arising under the Contract for works done was RM134,869.25. 5 Proceeding in Adjudication [6] PWC, as Claimant, commenced Adjudication under the Construction Industry Payment and Adjudication Act 2012 (“CIPAA”), claiming the sum of RM134,869.25 from Ireka who was the Respondent. [7] On 7.12.2016, PWC served a Payment Claim on Ireka by hand. On 22.12.2016, Ireka served its Payment Response on PWC as the Claimant by hand. In its Payment Response Ireka had raised a set-off/counter claim in the sum of RM3,740,790.45 arising from an LAD claim in a Sandakan Project for RM3,723,000.00 and an overpayment in a KL Sentral Project for RM17,790.45. [8] On 18.1.2017, PWC served the Notice of Adjudication on Ireka by hand. [9] In it’s Adjudication Response, Ireka as the Respondent further argued that the Adjudicator purportedly had no jurisdiction to adjudicate the present Adjudication as they are not disputing the amount claimed by the Claimant. [10] Upon considering all cause papers before him, on 18.5.2017, the Adjudicator delivered his decision. [11] The Adjudication Decision given by the Adjudicator is as follows: 6 i) Ireka shall pay to PWC the Adjudicated Amount of RM134,869.25 within seven (7) days from the date of this Adjudication Decision which was on 18.5.2017 ("Adjudicated Amount"); ii) Ireka shall forthwith pay to PWC the full cost and expenses of the Adjudicator in the sum of RM8,900.00 less such portion thereof as has been paid by Ireka; iii) Ireka shall forthwith pay to PWC the full cost of the KLRCA’s fees, taxes and expenses in the sum of RM2,469.80 less such portion thereof as has been paid by Ireka. iv) Ireka shall pay to PWC by way of cash, cheque or banker’s draft. Prayers [12] As there was still no payment forthcoming from Ireka, PWC filed an application to enforce the Adjudication Decision in Originating Summons WA-24C-98-06/2017. [13] Ireka responded with an application to set aside the Adjudication Decision in Originating Summons WA-24C-124-07/2017. [14] The 2 grounds relied on by Ireka in setting aside the Adjudication Decision are that of the Adjudicator having acted in excess of jurisdiction 7 and that there was a breach of natural justice under section 15(b) and (d) of the CIPAA. [15] By consent the 2 applications were heard together as one is the flip side of the other. [16] The parties shall be referred to by their names and sometimes as Claimant and Respondent as they were so referred to in the Adjudication. Principles [17] Section 15 of the CIPAA provides for setting aside of an Adjudication Decision on the limited grounds set out as follows: “Improperly Procured Adjudication Decision An aggrieved party may apply to the High Court to set aside an adjudication decision on one or more of the following grounds: