The Arbitrator referred to the Points of Claim and suggested that the Defendant was relying on implied terms as the basis of its complaint when this was not the Defendant’s pleaded case [45] The Arbitrator identified two fundamental issues, mainly whether there was a breach of the contract and if there was, which party was in default. To the Arbitrator, the issues as suggested by the parties in their respective submissions are ancillary to the fundamental issues. S/N Xdi4ypbnsEGDUtsYlczQTA [46] In relation to the issue as to whether there was a breach of the contract, the Plaintiff averred that the Points of Claim do not specifically refer to any particular breach by the Plaintiff but rather it is broadly alleged that there was substantial delay by the Plaintiff. It was further averred that, in paragraphs 71, 75, 80 and 81 of the Award, the Arbitrator suggested that, although the Defendant did not plead any implied term, the Defendant was nonetheless relying on implied terms as the basis of its complaint. Hence, the Arbitrator had considered issues that were not pleaded by the Defendant in the Points of Claim and had acted in excess of his jurisdiction (see paragraphs 68 and 69, AIS). [47] The Plaintiff asserted that it is wrong for the Arbitrator to assume that such terms are to be implied into the contract without it being pleaded, and no matter how common its usage may be in a particular industry, as there is a process to determine whether a term can be implied into a contract, and this could potentially be a matter of significant dispute. In this regard, the Plaintiff relied on the decision of the Federal Court in See Leong Chye v United Overseas Bank Berhad [2019] 1 MLJ 25 which had elucidated on the types of implied terms in these words: “[74] The law on implied terms has been succinctly summarised in the case of Sababumi (Sandakan) Sdn Bhd v Datuk Yap Pak Leong [1998] 3 MLJ 151 which was also extensively cited in the Court of Appeal judgment. The relevant paragraphs in Sababumi’s case at pp 169 – 170 are reproduced as follows: S/N Xdi4ypbnsEGDUtsYlczQTA Implied terms are of three types. The first and most important type is an implied term which the court infers from evidence that the parties to a contract must have intended to include it in the contract though it has not been expressly set out in the contract. The implied term contended for in this appeal belongs to this type and much more about this later. The second type of implied term is one by operation of law, and not based on the inference just explained. By operation of law, I mean that a large number of specific implied terms have been held in to arise from previous decided cases on certain specific facts. Such ratio decidendi in respect of such decided implied terms are normally adopted by courts in subsequent cases on similar facts as a matter of course without the necessity of any court to decide afresh whether it ought to draw the inference as explained above. Thus, such implied terms come from decided cases exclusively. Thus, in a contract of employment, there is an implied term that the employee will serve his employer faithfully, and not to act against the employer’s interest, and again there is another implied term that the S/N Xdi4ypbnsEGDUtsYlczQTA employer will provide a safe system of work. Many of such decided and specific implied terms have been incorporated into statutes such as the Sale of Goods Act 1957 and others; it is not necessary to discuss it further except to emphasise that such an implied term of this particular type may sometimes be excluded by parties by an agreement to the contrary and more importantly, it is not dependent on the court having to draw an inference explained above. The third kind of an implied term is one that is implied by custom or usage of any market or trade which is reasonable, and again it is not dependent on a court’s inference explained above but by virtue of such a custom or usage from the market or trade. Interestingly, s 92(e) of the Evidence Act 1950 seems to be custom-made to prove logistical support for this particular type of implied term. It will be remembered that s 92(e) aforesaid is one of the exceptions to the rule against evidence to contradict or vary any terms of a written contract. …”. S/N Xdi4ypbnsEGDUtsYlczQTA [48] Mr. Sanjay Mohan submitted for the Plaintiff that in so far as the third category of implied terms is concerned, evidence must be led to establish that usage or custom was such to imply such a term, but this was not done by the Defendant in the arbitration proceedings. [49] It was further submitted that the finding by the Arbitrator on the issue of implied terms has grave consequences as the Arbitrator ultimately went on to find, in paragraph 109 of the Award, that the Plaintiff was in delay and therefore in breach of the contract and the damages sought by the Defendant was then assessed. [50] I shall begin the analysis with the Points of Claim. I find that the Points of Claim, when read in its entirety, shows that the Defendant had pleaded, among others, the Contract between the parties consisting of the LoI, the Work Order, the scope of works and the Commercial T & C; the completion dates for the Works; the delay by the Plaintiff; and the entitlement to recoup costs, expenses and losses and to claim for liquidated damages. [51] Whilst it is true that the words “breach of contract” cannot be found in the Points of Claim, nevertheless the Defendant had pleaded the essential ingredients for the Arbitrator to identify the cause of action, which was essentially for breach of contract. A cause of action is the entire set of facts that gives rise to an enforceable claim (per Esher M.R. in Read v. Brown (1888) 22 Q.B.D. 128 and applied in Bennett v. White [1910] 2 K.B. 643 and referred to in Tuan Haji Ishak Ismail v. S/N Xdi4ypbnsEGDUtsYlczQTA Leong Hup Holdings Berhad & Other Appeals [1996] 1 CLJ 393 at p 409). [52] At the arbitration, the Plaintiff did not make any submission as to the absence of the words “breach of contract” in the Defendant’s pleadings. Instead, in subparagraph 24(b) of the Written Submissions (Post Hearing), the Plaintiff itself suggested that one of the main issues to be tried is “Whether the Claimant breached the terms of the contract between the parties in failing to provide the material and access to site to enable the Respondent to carry out the erection and commissioning works and the consequences of such a failure?”. This was recognised by the Arbitrator in subparagraph 68(b)(ii) of the Award. [53] Moving on to the Points of Defence & Amended Counterclaim dated 31.8.2018, the Plaintiff’s pleaded position was that the Defendant was in breach of its express and/ or implied terms of the contract when the Defendant failed to, among others, provide adequate material to the Plaintiff, make prompt payments, and properly administer the contract. This is evident from paragraphs 21, 24 and 37 of the Points of Defence. In this sense, the Arbitrator correctly observed in paragraph 72 of the Award that “The Respondent in its Defence and Amended Counterclaim is more explicit.”. [54] Pertinently, and as submitted by the Defendant’s counsel, nowhere in the Points of Defence and Written Submissions did the Plaintiff contend that the Defendant did not plead breach of contract in the Points of Claim and as such, none of the Defendant’s witnesses were S/N Xdi4ypbnsEGDUtsYlczQTA cross-examined on this point. It was only in the instant application that the Plaintiff attempted to persuade this Court to set aside the Award on the ground that the Arbitrator had decided on a “new difference” which was not relevant to the determination of the dispute and was not an issue in dispute between the parties. [55] Although in the AIS, the Plaintiff had highlighted paragraphs 71, 75, 80 and 81 of the Award, the decision on whether the Award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration and/ or the Award contains decisions on matters beyond the scope of the submission to arbitration entails a reading of the entire section in the Award on the issue of whether there was a breach of the contract i.e. from paragraphs 71 to 82. [56] Having read the said paragraphs, suffice for present purposes to re-produce the following passages from the Award to accentuate the findings and conclusions of the Arbitrator: “77. Although the Claimant does not refer specifically to breach or breaches of contract by the Respondent, it is fairly obvious that a reading of pleadings and submission that the Claimant alleges that there was substantial delay by the Respondent in meeting with the contractual key dates and as well as recovery plan. This in essence was the breach. …