17.4, and 20.2 of the Letter of Award are clear and unequivocal. The Plaintiff’s reliance on visual pegging without as-built verification or coordinate checks constitutes a serious omission and a breach of its contractual obligations. The evidence of SP1, read together with the testimonies of SD1 and SD2, confirms that the Plaintiff failed to ensure compliance with the approved plan. The deviation, though latent, was a non-conformity attributable to the Plaintiff. On Issue (b), the Court accepts the evidence of SD1 (TNB) and SD2 (Defendant) that the immediate cause of the 4 June 2015 failure was mechanical damage by a third-party contractor engaged in drainage works. However, the root cause of the damage was the cable’s deviation from the approved alignment, which placed it within the drainage reserve. This deviation rendered the cable vulnerable to interference and constituted a latent defect under the contract. The absence of complaint prior to the incident does not exonerate the Plaintiff, as the defect was not discoverable without excavation. On Issue (c), the Court finds that the Plaintiff remained bound under the Letter of Award to rectify any deviation or defect discovered during the Defects Liability Period (“DLP”). The 4 June 2015 incident occurred well within the DLP and the Plaintiff’s obligation to make good such defects was active and enforceable at that time. The Plaintiff’s attempt to characterise the rectification as “new work” or “extra-contractual” is inconsistent with the plain terms of the contract and settled principles of law. The works were corrective in nature and part of the Plaintiff’s continuing obligations. Accordingly, the Plaintiff was contractually liable to bear the cost of rectification. On Issue (d), the Plaintiff’s reliance on quantum meruit under Section 71 of the Contracts Act 1950 is misplaced. The post-incident diversion and reinstatement works were not voluntary or independent of the contract but carried out in discharge of the Plaintiff’s continuing contractual duty. Section 71 does not apply to acts done pursuant to an existing contract. Further, a party who caused the defect cannot invoke equity to seek restitution for remedying its own breach. The Plaintiff’s quantum meruit claim is therefore dismissed. On Issue (e), the Court finds that the Plaintiff has not proven the quantum of its claim. The quantification does not comply with the contractual pricing mechanism under Clause 2.5 and the claimed sum of RM1,620,546.02 (identical to the entire original contract price) is mathematically implausible for partial rectification works. Moreover, the Defendant was entitled under Clause 23.4 of the Letter of Award to retain and set off sums to cover costs incurred due to the Plaintiff's deviation. The retention was lawful and justified