Content
1 IN THE COURT OF APPEAL OF MALAYSIA (APPELLATE JURISDICTION) CIVIL APPEAL NO.:S-02(NCvC)(W)- 2545-12/2017 BETWEEN RICHALLENGE CORPORATION SDN BHD (COMPANY NO.: 257972-X) … APPELLANT AND POTECK ENTERPRISE SDN BHD (COMPANY NO.:111387-X) … RESPONDENT [In the High Court in Sabah and Sarawak at Kota Kinabalu Suit No. BKI- 22NCVC-75/7-2015 Between Richallenge Corporation Sdn Bhd (Company No.:257972-X) … Plaintiff And Poteck Enterprise Sdn Bhd (Company No.:111387-X) … Defendant] 2 CORAM: ABDUL RAHMAN SEBLI, JCA MARY LIM THIAM SUAN, JCA HASNAH DATO’ MOHAMMED HASHIM, JCA JUDGMENT OF THE COURT [1] This appeal by the Appellant is against of the decision of the learned Judicial Commissioner who had dismissed the Appellant’s claim for unlawful termination and for the damages to be assessed. The High Court allowed the Respondent’s counterclaim of RM1,537,226.00 for losses and damages. After having heard and considered the submission of the respective counsel for the parties, we had allowed the appeal and set aside the decision of the High Court. We remitted the case before the same High Court Judge for assessment of damages. We now give our reasons. [2] For the purpose of this judgment, the parties will be referred to as they were in the High Court. Material Facts [3] The Defendant is the main contractor of a project described as “Cadangan Pembangunan Projek Pendidikan Bagi SMK Tandek 2, Kota Marudu, Sabah” (‘the Project’) awarded by the Ministry of Education (MOE) (‘the Employer’). The contract sum for the Project is RM41,445,000.00 (‘the Contract Sum’). The Defendant appointed the Plaintiff as its sub-contractor on 28.7.2009. The expected completion date of the Project was 3 on 25.5.2011. However, the completion date was extended to 27.4.2012 (‘the 1st EOT’). By the terms of the Sub-Contract Agreement (‘SCA’) it was agreed by the parties that the Defendant’s entitlement was 15% of the total Contract Sum, which is RM 6,216,750.00. [4] The Plaintiff’s claim against the Defendant is for unlawful termination of the SCA. The Defendant, on the other hand, denied that it had unlawfully terminated the SCA. It had terminated the SCA due to the persistent failure of the Plaintiff to commence works as scheduled resulting in the delay of completion of the Project. Due to the Plaintiff’s breach the Plaintiff is estopped from relying strictly on the terms of the SCA. The Plaintiff, however, contended that it had duly commenced the works as scheduled but there were many factors beyond its control which consequently led to the delay in the completion of the Project as scheduled (such as inclement weather and other factors). [5] At the trial in the High Court the Plaintiff called two witnesses, the consulting architect (PW1) and the Plaintiff’s director, PW2. The Defendant called four witnesses, the director (DW1), the consultant quantity surveyor (DW2), a former officer of the MOE (DW3) and its General Manager (DW4). [6] It was highlighted by learned counsel for the Plaintiff that it was recorded in the minutes of meeting that as at 29.10.2013 the physical progress of the Project was 81% and that the Defendant has been paid approximately 50% of the Contract Sum. The Defendant in its defence pleaded that under the terms of the SCA the Defendant as the main contractor of the Project has the right to terminate the sub-contract. On 29.9.2014 the Defendant 4 terminated the SCA. On 20.10.2014 the Defendant through its solicitors notified the Plaintiff of its intention to invoke clause 11.3 and on 8.1.2015 the Defendant took over the Project. The Plaintiff argued that there was no express termination in writing given by the Defendant as clause 10 of the SCA does not allow the Defendant to terminate the sub-contract. Furthermore, the 2nd extension of time was subsequently granted by the Employer on 13.11.2014 extending the completion date to 6.9.2015 (‘the 2nd EOT’). The Plaintiff’s Arguments [7] The Plaintiff’s submission is that the learned Judicial Commissioner had erred in law by solely relying on the case of Tan Kok Siang v Kemuning Setia Sdn Bhd [2018] 8 CLJ 546 and concluding that there was a fundamental breach of contract by the Plaintiff. The learned Judicial Commissioner misapplied section 40 of the Contracts Act 1950 in determining that there was a total failure of consideration on the part of the Plaintiff. Learned counsel for the Plaintiff advanced several arguments in support of those submissions, contending that the finding by the High Court is fundamentally flawed. He argued that the Plaintiff could not be said to be behind schedule as not only had the Employer granted the 2nd EOT but the progress of works was 81% as confirmed by DW4 in evidence. In Tan Kok Siang’s case (supra) relied by the learned Judicial Commissioner, the Court referred to the Federal Court case of Berjaya Times Square Sdn Bhd v M Concept Sdn Bhd [2010] 1 MLJ 597 where it was held under section 40 Contracts Act 1950 the right of the non-defaulter to repudiate a contract only accrues when the defaulter refused to perform or disabled himself from performing the whole of his promise. If there is part performance the 5 innocent party may not put an end to the contract. In the light of the above and the facts before the Court there was no total failure of consideration. [8] Learned Counsel for the Defendant in response argued that the Plaintiff was incapable of completing the Project due to its financial woes at the material time. The Defendant alleged that the Plaintiff refused to commence works and instead gave all kinds of excuses and/or reasons for the failure to commence the works as scheduled. The Plaintiff did not have the financial capacity and means to complete the Project. Furthermore, there was an order to wind up the Plaintiff. The Plaintiff applied for a stay of that Order which was granted on 5.11.2014. In fact, the Plaintiff cannot complete the Project because the Official Receiver (‘OR’) was controlling the affairs of the Plaintiff. Sometime in March 2013, the Plaintiff abandoned the Project and this according to the Defendant tantamount to a fundamental breach of the SCA which entitled the Defendant to terminate the subcontract. [9] It was confirmed on 13.11.2014 that the Defendant obtained the 2nd EOT from the Employer extending the date of completion of the Project from 27.4.2012 to 6.9.2015. The 2nd EOT was granted due to inclement weather and factors beyond the control of the Defendant. With the 2nd EOT the Plaintiff would have more time to complete the Project. The Employer did not issue a certificate of non-completion nor did they claim Liquidated Ascertained Damages (‘LAD’). PW1 testified that the Defendant had obtained a third extension of time (‘3rd EOT’) further extending the completion date to 10.4.2017. It was therefore unconscionable for the Defendant to rely on the alleged delay to justify terminating the Plaintiff when the Defendant had obtained the 2nd EOT and applied for the 3rd EOT. 6 [10] In response, the Defendant contended that clause 11.3 of the SCA clearly provides that the Defendant may terminate the contract without prejudice to any right of action or other remedies it may have against the Plaintiff. According to the Defendant the Plaintiff did not disclose to the Defendant of the winding up order. [11] Learned Counsel for the Plaintiff argued that the Defendant should not be permitted to ignore the terms and conditions of the SCA to the detriment of the Plaintiff. The High Court [12] The Plaintiff appeals against the Judicial Commissioner’s decision on grounds which may be summarised as follows: