44.3 If the Contractor fails to comply with clauses 44.1 and 44.2, he shall not be entitled to such claim and the Government shall be discharged from all liability in connection with the claim.”. However, the learned SFC did not elaborate as to how these contractual provisions operate to bar the Plaintiff from claiming this amount. The Defendant further submitted, on one hand, that the claim concerns preliminary works, which should be borne by the Plaintiff, and on the other hand, that it pertains to additional works and requirements by MOH which were not related to the Plaintiff’s scope of work and done under a separate contract. S/N RV6xtFhtqkumMTPJbtnjQ To the Plaintiff, the claim was due to JKR’s failure to timely obtain MOH’s consent to construct the additional works as required by MOH after the issuance of the CPC. As the Plaintiff had issued the notice of intention to claim for this item to JKR and there being no response or rebuttal from the Defendant, and in view of the oral and documentary evidence adduced at the trial, I allowed this claim. ii. losses arising from the S.O.’s failure of refusal or negligence to remove MS Time amounting to RM106,730.00; I found that the Plaintiff was not entitled to this claim on the grounds as submitted by the Defendant, mainly that the Plaintiff has not established which provision in the Contract that allows for these purported losses to be claimed from the Defendant. The Plaintiff is not appealing against this part of the decision. iii. balance variation works that was duly completed, amounting to RM2,181,913.75; S/N RV6xtFhtqkumMTPJbtnjQ This pertains to the Plaintiff’s claim for the following six items for variation works [see PW2’s evidence in WS-PW2 and the Plaintiff’s reference to the supporting documents therein and in the Written Submission and Revised Scott Schedule (Quantum)]. Essentially, I allowed the Plaintiff’s claim for the reason that the S.O.’s representative had instructed the Plaintiff to re-submit these claims with the supporting documents to the new S.O. on 20.6.2022 and the Plaintiff accordingly did so. JKR or the new S.O. did not respond to the Plaintiff’s submission by refuting the claim or stating that the Defendant had paid for these claims. • Steel Column The Defendant alleged that the steel column works were not Variation Works but were part of Bill of Quantities (‘BQ’) in the Contract (see the words “steel structure support” in the Bills at pp 38 - 43, B8 and the construction drawing at pp 31 - 37, B8). Payment was said to have been made (see pp 62 - 63, B48 under item nos. 3, 4, 5, 6 and 9). S/N RV6xtFhtqkumMTPJbtnjQ However, as submitted by the Plaintiff, the description of works in the Contract is itemised and not on a lump sum basis. The 300mm x 300mm rectangular hollow section was shown in the construction drawing but not in the BQ in the Contract. As the specifications according to the construction drawing are not part of the BQ, this item is deemed as a variation and no payment has been made by the Defendant despite the notice of claim having been served by the Plaintiff to the Defendant. There was no contemporaneous denial by the Defendant on this claim at the material time and specifically, the Defendant did not refute on the Plaintiff’s value engineering. Accordingly, the sum of RM69,197.07 for Steel Column was allowed. • Support Fire Rated Ceiling Similarly, the Defendant submitted that these works were not Variation Works but were part of the BQ in the Contract. Payment was said to have been made (see pp 62 - 63, B48 under item nos. 3, 4, 5, 6 and 7). S/N RV6xtFhtqkumMTPJbtnjQ I was persuaded by the Plaintiff’s submission to allow the sum of RM247,680.00 for Support Fire Rated Ceiling for the same reason that all supporting documents were submitted to JKR which then requested its consultant to evaluate the Plaintiff’s claim. The Defendant did not refute this claim at the material time. Moreover, akin to the Steel Column, the reference to pp 62 - 63, B48 under item nos. 3, 4, 5, 6 and 7 do not show anything on Support Fire Rated Ceiling. • Galvanised Double Cover The Defendant claimed that it has evaluated and made full payment under IPC No. 72, which includes both the original and additional scope (APK 49). The Plaintiff drew my attention to “Laporan Penilaian Tuntutan Kepada Jawatankuasa Tuntutan: Tuntutan No. 7 – Kerja-Kerja Penambahan Galvanised Double Cover Untuk Menutup Bahagian Atas Inspection Chamber, Sump Dan Gulley Trap” at p 23, B55 wherein Perunding QS commented that “Tuntutan pihak kontraktor ini telah di proses di bawah … (KPK) No. 46 berjumlah RM 85,002.00. Pihak perunding telah menolak bagi kerja-kerja inspection chamber. Walaubagaimana pun S/N RV6xtFhtqkumMTPJbtnjQ Kerja tersebut telah dilaksanakan oleh kontraktor di tapak. Oleh yang demikian, nilai tersebut perlu ditambah semula kepada pihak kontraktor.”. In “Lampiran 1”, “Jumlah Bersih Tambahan” was stated as RM47,000.00. Therefore, the sum of RM47,000.00 for Galvanised Double Cover was allowed. • Bullnose The same defence was raised i.e. this item was not Variation Works and payment has been made as seen at p 92, B48 under item nos. 3, 4, 5, 6, 9 and 11. However, a scrutiny of the page in B48 does not support the Defendant’s contention. The notice of claim and supporting documents were served to JKR and there was no contemporaneous denial on this variation claim at the material time. Thus, the sum of RM616,284.10 for Bullnose was allowed. • Cold Water & Sanitary Plumbing The Defendant alleged that it has evaluated and made full payment under IPC No. 72 (APK 49). S/N RV6xtFhtqkumMTPJbtnjQ However, I agreed with the Plaintiff’s submission that JKR agreed on the final cold water & sanitary works in the sum of RM2,654,000.00. After taking consideration the original contract sum of RM1,028,090.00, APK 25 (RM939,061.80) and APK 29 (RM20,344.00) which were approved and paid by JKR, the balance of claim on this Variation Order was RM666,504.20. This amount was accordingly allowed. • Built-In Furniture The Defendant alleged that it has evaluated and made full payment under IPC No. 72 (APK 71). The Plaintiff accepted the final revised contract sum for this item as offered by JKR for RM5,173,546.00. After taking consideration the original contract sum of RM4,397,150.00 and APK 71 of RM481,396.00, the balance amount for this variation claim was RM295,000.00 and was accordingly allowed. iv. idling costs amounting to RM1,312,348.91; S/N RV6xtFhtqkumMTPJbtnjQ This claim was in respect of three distinct blocks of the hospital [see PW2’s evidence in WS-PW2 and the Plaintiff’s reference to the supporting documents therein and in the Written Submission and Revised Scott Schedule (Quantum)]. • Idling cost for electrical block - RM 211,922.46 • Idling cost for catering & engineering block (for 22.8.2014 - 31.3.2015) • Idling costs for main building (for 11.11.2014 -