The Letter of Acceptance of 27 March 2014 was signed by the Defendant on 31 March 2014. 23 [27] Based on the facts submitted, the events leading to this appeal can be unfolded into a chronology order. There was a LOI from the Defendant to the Plaintiff based on JKR’s LOI to the Defendant (exhibit P-10A). The JKR’s Letter of Intent clearly stated that the Government of Malaysia through JKR is desirous to appoint the Defendant on the condition to the acceptance of the tender that no change can be made to the price, value and additional cost or losses. [28] Paragraph 3 of the LOI exhibit P10A specifically stated that the Defendant is to return the letter accompanying the LOI which bears the same reference number and date in accepting the offer and non-returning of the letter will be assumed as non-acceptance. The letter was returned to JKR, filled and signed on 15 January 2014 (exhibit P10B, at page 185 of the Appeal Record Jilid 2 Bahagian C) by the Defendant. [29] The letter to accept the offer as returned again provides the statement that the Defendant will not make any changes to the contract sum, the scope and any claims for additional cost and losses: “Pihak kami juga tidak akan membuat sebarang perubahan harga, skop dan sebarang tuntutan perbelanjaan tambahan dan kerugian.” 24 [30] In comparison to the Defendant’s LOI (exhibit P-11) received by the Plaintiff, my careful perusal finds that it is almost a perfect replica of the Letter of Intent exhibit P-10A. The exact words of no change to the contract value and that the letter of intent is not intended to be binding, is expressly provided. The standard notice to accept the LOI (at page 190 of Appeal Record Jilid 2 Bahagian C) accompanying the LOI is of similar format to JKR’s. [31] The LOI exhibit P-11 between Defendant and the Plaintiff clearly stated that the Defendant is desirous to appoint the Plaintiff as the sub-contractor for the contract value of RM22,689,187.00. The remaining words at paragraph 2 of exhibit P-11 informing Plaintiff that the tender acceptance is subjected to the Plaintiff’s agreement to the condition that the Plaintiff cannot make any changes to the price, scope (works) and is not qualified to make a claim for additional cost and losses in the event the offer is accepted by the Plaintiff. [32] The letter of intent is at the very early stage of negotiation where the tender has yet to be agreed upon and approved by JKR. The contractual relationship between the main contractor and its subcontractors as simply 25 explained by Sundra Rajoo & Harbans Singh KS, ‘Construction Law in Malaysia’, 2012, unless expressly prohibited under the construction contract, the main contractor is free to sublet portions of works to other parties to carry them out for and on his behalf and may consist of various types of works depending on their particular method of appointment and the ultimate contractual arrangement entered into. [33] In most building contracts, it is a normal practice to see a fair amount of negotiation taking place over the terms of contract. The case of Hock Chuan Ann Construction Pte Ltd v Kimta Electric Pte Ltd [2000] 2 SLR 519 is instructive as the court was invited to make sense out of a mass of facts concerning the negotiations carried out by the parties with a view of determining whether a subcontract is formed as prescribed by the legal principles. [34] So much so, the elements pertinent to contract value or the price, the supply of construction materials and contractor’s responsibilities during contract period may take time to be finalized particularly involving government procurement within an approved budget before the offer or proposal can be extended to a party by the other. 26 [35] At this juncture, if this line of argument by Plaintiff is to be followed that there was a contract, I cannot disregard the fact that the negotiation has yet to be finalized for the contract to be effectively implemented and operationalized by both parties. More particularly, the offer between Defendant and Plaintiff has to be certain as it must be in accordance with the terms specified by JKR before an acceptance can be communicated. [36] This is important as the offer is the first element in the chain of events leading to a construction contract. The offer must consist of a definite proposal in clear terms capable of resulting in a binding agreement once it is accepted as decided in the Federal Court in Preston Corp Sdn Bhd v Edward Leong [1982] 2 MLJ 22. In that case, the wording of the quotation issued to the customer and printing orders were studied in determining the formation of the contract. It was held that the printing order constituted an offer and its confirmation by the respondents constituted acceptance which concluded a contract. [37] Therefore the effect of a letter of intent depends upon the objective meaning of the words used. Based on the Defendant’s LOI to the Plaintiff, the construction of the words are clearly in plain language that it has no 27 binding effect. The LOI by Defendant to the Plaintiff was based on JKR’s Letter of Intent which is subjected to the acceptance of tender and other conditions. [38] Invitations to tender are not offers but are invitations to treat. This tender process was aptly put by Bingham LJ in the case of Blackpool and Fylde Aero Club Ltd v Blackpool Borough Council [1990] 1 WLR 1195 at page 1202, “A tendering procedure of this kind is, in many respects, heavily weighted in favour of the invitor. He can invite tenders from as many or as few parties as he chooses. He need not tell any of them who else, or how many others, he has invited. …. The invitation to tender may itself, in a complex case, although again not here, involve time and expense to prepare, but the invitor does not commit himself to proceed with the project, whatever it is;….” Therefore this Court finds that the LOI which is subjected to the tender to be accepted by JKR could not be a concluded contract as yet. [39] A letter of intent which provides the statement “subject to contract” had been decided where in the words of Lord Denning in the case of Tiverton Estates Ltd v Wearwell [1975] Ch 146 at 159, 28 “.. for over a hundred years, the courts have held that the effect of the words “subject to contract” is that the matter remains in negotiation until a formal contract is executed….” [40] I stand to be guided by the decision of the Supreme Court in the case of Ayer Hitam Tin Dreging Malaysia Bhd v YC Chin Enterprises Sdn Bhd [1994] 2 MLJ 7544 which had decided on the status of a letter of intent. In that case, YC Chin entered into negotiations with Malaysia Mining Corp Bhd, a majority shareholder of Ayer Hitam, to develop and construct low cost houses and shophouses for Ayer Hitam’s workers. On 19 September 1984, Ayer Hitam wrote to YC Chin accepting YC Chin’s proposals in undertaking the project but subject to certain terms and conditions stipulated in the letter. One of the terms was that there be a formal agreement in writing entered into between the parties incorporating all the terms proposed by Ayer Hitam. [41] The Supreme Court held that essential matters referred to the letter still remained to be settled between the parties and the condition that a formal written agreement be executed was yet to be fulfilled, the letter did not constitute a contract binding in law but was only a record of terms upon which they were agreed upon as a basis for the negotiation of a contract. 29 [42] Interestingly the Counsel for the Plaintiff said that the law tends to lean in favour of upholding bargains and relied on two authorities to support her argument. However what the Counsel for the Plaintiff did not do was to make reference to the Supreme Court decision in Ayer Hitam Tin Dredging Malaysia Sdn Bhd v YC Chin Enterprise Sdn Bhd [1994] 3 CLJ 133 that was referred in the case submitted to this Court, JNA Ikhtisas Sdn Bhd v Kerajaan Malaysia [2015] 3 CLJ 1100. [43] Based on Ayer Hitam Tin Dredging (supra) case, it is settled law that when an arrangement is made “subject to contract” or “subject to the preparation and approval of a formal contract” and similar expressions, it will generally be construed to mean that the parties are still in a state of negotiation and do not intend to be bound unless and until a formal contract is entered into. [44] There is a striking difference between the case of JNA Ikhtisas Sdn Bhd (supra) and Ayer Hitam Tin Dredging (supra) case where in the former, the defendant clearly intended the plaintiff to render services under a direct negotiated contract. 30 [45] Although the case of RS & L Marine Sdn Bhd v Bras Ventures Bhd & Anor [2016] 9 CLJ 56 was referred by the counsel for the Plaintiff, this Court takes the stand that the case must be read as a whole and not in extraction. The RS & L Marine Sdn Bhd (supra) case was about the defendant, Bras Ventures who were trying to secure a project with TNB expressed the desire to award a portion of the works known as ‘Kerja-Kerja HDD merentasi Sungai Manjung, Perak’ to the plaintiff, RS & L Marine as the sub-contractor. The plaintiff has the experience and equipment to carry out the works in particular the use of Horizontal Directional Drilling (HDD). While the terms of payment of the contract price were being negotiated, the defendant conveyed their intention not to proceed with the subcontract with the Plaintiff. [46] The Court of Appeal stated that when the defendant informed TNB that they had appointed the plaintiff as the subcontractor, it was nothing more than that and it does not tantamount to prove that all the fundamental elements of a valid contract had been established consensus ad idem on the terms of payment of the contract price. In that regard, the Court of Appeal held that there was no concluded subcontract reached between Bras Ventures and the plaintiff. 31 [47] It is for the Plaintiff to prove that there was communication in accepting the LOI of the Defendant in order not to treat the negotiation between the parties as still open to process of bargaining. Based on the submission by the Defendant’s Counsel on proof of no contract, this Court finds that it is corroborated by the Plaintiff’s witness (see page 112 of the Appeal Record Jilid 1 Bahagian A & B) whom agreed that the LOI was only an expression of desire to appoint and not a contract. [48] Reverting to the evidence given by the Plaintiff’s witness, he admitted upon questioning, “Q: Maksudnya surat ini ditulis “Surat Niat” tetapi Encik Zahari baca tiba-tiba menjadi Surat Tawaran pula. Setuju? A: Surat Niat tetap surat niat. Q: Setuju atau tidak, Surat ini menyatakan bahawa Seroja Anggerik hanya berhasrat untuk melantik dan bukan melantik pihak Plaintiff. Setuju atau tidak?” A: Ya (witness nod his head).” 32 [49] It is of the Court’s view that it is for the Plaintiff to prove on the balance of probabilities that the contract exist before this Court can delve into the second and third grounds of appeal. [50] Reverting to the dispute, the Plaintiff claimed that the Defendant offered to the Plaintiff via letter of 29.1.2014 for the price of RM22,689,187.00 and the Plaintiff claimed that it had accepted the offer. However the Plaintiff could not produce any evidence that the acceptance letter to the LOI was returned to the Defendant. [51] In the Defendant’s defence, it was stated that a meeting took place between the Defendant and the Plaintiff on 12.2.2014 where the contract value was discussed and Plaintiff was offered with a new contract price of RM21, 680,114.45. The Defendant had issued the offer letter of 12.3.2014 with the new contract price of RM21, 680,114.45. The Defendant claimed that there was still no acceptance from the Plaintiff. [52] Based on the facts and the evidence tendered, the letter 12.3.2014 (exhibit P-12 at page 195 of the Appeal Record Jilid 2 Bahagian C) was an offer letter to the Plaintiff for the subcontract work at the price of RM21, 33 680,114.45. It specifically stated that the Bills of Quantity (BQ) is based on provisional sum which is subjected to the offer letter of JKR, the payment to the Plaintiff will be by way of Deed of Assignment and the other conditions will be discussed at a later stage upon receiving the offer letter from JKR. [53] The Defendant’s counsel submitted that the Defendant had wrote to the Plaintiff on 4 April 2014 in reply to the Plaintiff’s letter of 25 March 2014 denying the preliminary works of RM450,000.00 as the Defendant has yet to be appointed by JKR (exhibit P-18 at page 210 of the Appeal Record Jilid 2 Bahagian C). The Defendant also submitted that the Plaintiff did not reply to the offer letter of the Defendant which is as shown in Defendant’s letter of 29 April 2014 (at page 213 of the Appeal Record Jilid 2 Bahagian C), the Plaintiff was given 3 days to reply to the offer made by the Defendant. [54] Based on the foregoing, the evidence produced proved that the Plaintiff did not accept the new offered price for the subcontract works. In addition, this Court is of the view that the Plaintiff in disagreeing initially to the contract value offered by the Defendant at RM22,689,187.00 may amount to a rejection of the Defendant’s offer. 34 [55] If the Plaintiff disagreed and had introduced a new contract value or had insisted on the original price, he would then be making a counter-offer. A counter-offer not only fails as an acceptance but it also amounts to a rejection of the original offer: Malayan Flour Mills Bhd v Saw Eng Chee (Administrator of the Estate of Saw Cheng Chor, Deceased) & Anor [1997] 1 MLJ 763 at page 773. This Court finds that the Plaintiff had never accepted the new offer by the Defendant. [56] Generally a contract is formed when there is an offer that has been accepted and the terms agreed to must enable the parties to perform the contract. The acceptance of the offer should be absolute and unqualified to be effective in order to satisfy the need to achieve the consensus ad idem criteria following section 7(a) of the Contracts Act 1950. This point of law had been decided in the case of Rajeswari Thedshanamurthy v Kin Nam Realty Development Sdn Bhd [1993] 1 MLJ 88. [57] The case of RS & L Marine Sdn Bhd (supra) case is similar with the instant case with regards to the fact that the contract value and other vital terms of the contract particularly the site possession to commence with the works have yet to be finalized between Plaintiff and Defendant. JKR’s 35 approved tender and the Letter of Acceptance of 27 March 2014 proved to show that no prior contract or agreement could exist as the site possession was given after the date of JKR’s Letter of Acceptance to the Defendant which is 28.04.2014. [58] In this regard, counsel for the Plaintiff’s submission of the case Sinar Wang Sdn Bhd v Ng Kee Seng (supra) cannot be relied upon as there was an offer made in this case after the issuance of LOI from the Defendant. The fact still remain that the Plaintiff could not prove acceptance of the offer and thus commencement of the preliminary works. Alternatively, the Plaintiff may have jumpstart the construction which is illegal but this matter was not pleaded on the Defendant’s part. [59] Given that the wordings in the LOI are clear and free from any ambiguity and that the acceptance was never communicated to the offer made, it must follow that there was no contract. The existence of a contract has yet to be proven by the Plaintiff. This translates to what is simply the fact that there was no judicial appreciation of the law by the learned Session Judge in deciding that the burden is on the Defendant when it was 36 the Plaintiff who brought the suit claiming that a contract exist. In her first part of her decision she stated that, “Berdasarkan dari keterangan semua saksi dan eksibit-eksibit yang telah dikemukakan di dalam Mahkamah, Mahkamah mendapati bahawa Plaintiff mempunyai tuntutan yang kukuh dan gagal dicabar oleh Defendan di dalam tuntutan. Atas asas demikian, Mahkamah telah membenarkan tuntutan Plaintiff terhadap Defendan bersama-sama dengan kos.” [60] The initial onus of proving the case is always on the plaintiff. The plaintiff, at the start of the plaintiff’s case, has the legal burden of proving the existence of any relevant fact and the evidential burden of some evidence of the existence of such fact. The law on the burden of proof can be found in a plethora of cases and the decision of the Federal Court in Letchumanan Chettiar Alagappan @ L. Allagapan, M. Venkatachalam S/O Venkatachalam Chettiar v Secure Plantation Sdn Bhd No. 02-78- 10/2014 had extensively discussed the burden of proof with sections 101 – 103 of the Evidence Act 1950 and made reference to an earlier Federal Court case of International Times & Ors v Leong Ho Yuen [1980] 2 MLJ