the architect’s letters do not state any opinion at all and merely state that there would be delays in the completion of the construction works. [29] As such, we are of the opinion that the architect’s letters do not qualify as valid certificates of extension of time which would justify the first respondent’s [developer’s] delay in delivering the vacant possession of the said properties to the appellant. [notes added] [34] Fifth, if the Engineer’s letter was to certify and approve a permissible delay, it is mandatory that the Engineer had to calculate and assess the period of the delay, and send the letter to both D and P, to inform them both. Instead, and in fact, the letter was issued only to D. The Page 11 of 15 letter was never issued to P and P was not informed about the letter. This further renders the Engineer’s letter even more remote from being considered as the requisite letter to certify and approve a permissible delay. [35] Sixth, the Engineer was D’s Engineer, which made the letter rather self-serving. Put differently, it was self-serving for D’s Engineer to issue this letter and send it only to D, but not contemporaneously sent to P, who was the party who should be informed about any permissible delay. The Engineer’s purported extension of time was not even notified to P, who was the party who would be adversely affected by the extension of time (if there was one). [36] Seventh, D has produced no affidavit evidence from the Engineer that may substantiate that his letter tantamounted to the requisite certification and approval for an extension of time under Clause 28. [37] Eighth, with the ultimate purpose of the completion of the SPAs in mind, D had the obligation to get the building plans approved and to construct the Properties on time. D’s failure to get the building plans approved, which is solely D’s obligation, cannot be attributed to or passed on to the authorities, just by a mere bare assertion, with no particulars setting out that the delay was the authorities’ fault, and not D’s fault. [38] D cannot be absolved from their obligation to complete and deliver vacant possession of the Properties on time by simply saying that the time required to obtain the approved building plans was beyond their control. D cannot be absolved from their obligation to deliver vacant possession within the agreed time by simply asserting that the obtaining of the Page 12 of 15 approved building plans was due to a cause beyond their control, or a circumstance beyond their control, or an event that cannot be reasonably foreseen and thus beyond their control—Mission Richmark Sdn Bhd v Capitol Avenue Development Sdn Bhd [2021] 8 MLJ 691 (HC); [2020] CLJU 977. [39] In Mission Richmark (supra), the High Court reasoned as follows— [12] In this instant case, the defendant is relying on the ground which is ‘beyond the developer’s control’ to justify the delay in the delivery of vacant possession of the said property. As provided in the defendant’s affidavit in opposition No 2 deposed by the developer’s architect, the defendant averred that it was the delay by SESB in, inter alia, connecting the electricity supply from the main supply line to the said property’s substation which caused the delay in the completion and delivery of vacant possession of the said property to the plaintiff… [13] The defendant submitted that as such connection of electricity rests solely within the domain of SESB, it is no longer within the control of the defendant as developer of the said property. [14] However, I am more inclined to agree with the plaintiff who submitted that the delay cannot be brought within the ambit of the proviso to cl 14.1.1 of the said agreements. The proviso which is also known as force majeure clause must not be construed liberally and widely enough to exclude the defendant of any liability of its contractors. [15] In the Court of Appeal case of Araprop Development Sdn Bhd v Leong Chee Kong & Anor [2008] 1 MLJ 783, the developer was held to remain liable to liquidated damages despite delay caused by the tardiness in laying of electrical and telephone cables by its subcontractors on the grounds that these subcontractors are under the control of the developer. [16] In the Singapore’s Court of Appeal case of Golden Bay Realty Pte Ltd v Orchard Twelve Investments Pte Ltd [1989] 2 MLJ 70, the developer was still found liable and was disallowed to rely on force majeure clause for failing to secure subsidiary title within the stipulated time provided in the agreement. It was held: We do not think a vendor is entitled to claim protection under the force majeure clause if he has under provided the time required to do the necessary things. Page 13 of 15 [17] In this present case, the defendant had covenanted to deliver vacant possession within 36 months from the date of obtaining the building plans as provided in the said agreements. Thus, it is incumbent on the defendant to ensure there are sufficient time to fulfill such obligation… [18] Therefore, it was the defendant who delayed completing the application for the installation of the permanent electricity supply from SESB. The defendant is not entitled to claim protection under cl 14.1.1 of the said agreements since it itself has under provided the time required to complete such installation. [emphases added] [40] Ninth, I find the argument that P knew, at the time the SPAs were signed, that the building plans for the Properties were not yet approved, and so constituted a triable issue—to be unconvincing and inconsequential. Even though they both knew about the fact that the building plans for the Properties were not yet approved—both parties nevertheless entered into the SPAs. D chose to take on the obligation under the SPAs. Hence it was D’s obligation to get the building plans approved, to complete the Properties, and to deliver vacant possession of the Properties to P on time. CONCLUSION [41] For these reasons, I find that D has fallen short in demonstrating that they have an arguable defence, or that there are triable issues that warrant a trial to determine them, or that there is some other reason that there should be a trial of the claim. [42] I find that D’s Defence and Affidavit In Reply, filed in the summary judgment application proceeding, do not disclose that D has a “fairly arguable defence” to the claim. Page 14 of 15 [43] I have no reasonable doubt that judgment should be entered summarily. [44] I am persuaded to by-pass a trial and summarily enter judgment against D. [45] And I find that there are no bona fide triable issues that warrant a trial to determine them i.e. there is no triable issue that defeats P’s summary judgment application under Order 14. [46] For these reasons, I dismiss D’s Appeal against the summary judgment. I uphold the Sessions Court’s decision in granting the order to enter judgment summarily against D. As for costs, I order D to pay P costs of RM7K by 19.4.2024. Costs are subject to the allocator. Dated: 15 May 2024 KENNETH ST JAMES Judicial Commissioner Penang High Court Page 15 of 15 Counsel/Solicitors: For the Appellant: Nicholas Lim [Messrs. Presgrave & Matthews (Pulau Pinang)] For the Respondent: Ong Yu Shin, Lim Wooi Ying [Messrs. The Chambers of Yu Shin Ong) (Pulau Pinang)] Legislation referred to: