Setiakon’s AIR affirmed by the same deponent on 17.10.2023 (encl. 9). Background Facts [8] Setiakon is a private limited company incorporated under the laws of Malaysia and having its registered address at Unit 30-01, Level 30, Tower A Vertical Business Suite, Avenue 3, Bangsar South, No. 8 Jalan Kerinchi, 59200 Kuala Lumpur. Its business address is 13, Jalan Cempaka SD12/1, Bandar Sri Damansara, 52200 Kuala Lumpur. [9] Bellworth is a private limited company incorporated under the laws of Malaysia with its registered and business address at No. 28, Jalan Wan Kadir 1, Taman Tun Dr. Ismail, 60000 Kuala Lumpur. [10] By way of the Letter of Award dated 17.12.2012 (‘LoA’), Bellworth engaged Setiakon as its main contractor for the execution and completion of the “Super-structure Works for Cadangan Pembangunan 2 Blok Pangsapuri Servis 27 Tingkat Yang Mengandungi Blok A (60 Unit) dan Block B (105 Unit) Di atas 5 Tingkat Podium (6 Unit Perdagangan, 4 Tingkat Tempat Letak Kereta dan 1 Tingkat Kemudahan Penduduk), Serta 1 Tingkat Separa Basement Tempat Letak Kereta di Atas Lot 50973, Lot 53610 dan Lot 53611, Jalan Wan Kadir, Taman Tun Dr.Ismail dalam Bandaraya Kuala Lumpur” (‘Project’). The original contract sum is RM168,300,000.00. [11] According to Clause 1.0 of the LoA, Setiakon’s scope of work is to supply labour, materials, plant, machineries, and tools including equipment, services and supervision to construct and complete the super-structure works for the Project (‘Works’). [12] On 2.6.2014, which is after Works had commenced, the parties executed the Agreement and Conditions of PAM Contract 2006 (With Quantities) (‘PAM Contract’) containing the terms and conditions governing the appointment of Setiakon as the main contractor for the Project, including the Addendum to the Articles of Agreement and Schedule of Conditions of PAM Contract 2006 (With Quantities) (‘Addendum’) (hereinafter collectively referred to as the ‘Contract’). [13] Clause 3.0 of the LoA provides that the total contract period is 25 months from the site possession dated 26.12.2012 and the date of completion is 25.1.2015. However, Setiakon contended that the LoA was only issued on 31.12.2012 and site possession was given on or about 9.1.2013. [14] During the course of the Project, Setiakon had submitted the following applications for extension of time (‘EoT’) to Bellworth or the Architect for assessment: EoT No. Date EoT Applied EoT No. 1 17.7.2014 75 days EoT No. 2 3.12.2014 187 days EoT No. 2 Appeal 6.7.2015 29 days EoT No. 3 19.5.2015 68 days EoT No. 3 Appeal 1.4.2016 253 days [15] EoT No. 1 and EoT No. 2 were partially allowed by the Architect. By way of Certificate of EoT No.1 dated 10.9.2014 and Certificate of EoT No. 2 dated 20.1.2015, Bellworth granted Setiakon 162 days of EoT. The original date of completion was therefore extended to 6.7.2015. [16] On 6.7.2015, Setiakon submitted an appeal with regards to EoT No. 2 but this was rejected by the Architect on 9.7.2015. [17] In respect of EoT No. 3, the Architect notified Setiakon through the letter dated 1.6.2015 that he was unable to assess the application due to insufficient particulars and requested Setiakon to furnish better particulars within 28 days. [18] On 9.6.2015, Setiakon replied by submitting what Bellworth alleged are 40 new events which are unrelated to EoT No. 3. This was rejected by the Architect on 19.6.2015 and he reiterated his request for further particulars. [19] Bellworth issued a Certificate of Non-Compliance (‘CNC’) on 7.7.2015 stating that Setiakon had failed to complete the Works by the extended date of completion. On the same date, the Architect issued a Notice to Contractor for Deduction of Liquidated Damages (‘LD’) to inform Setiakon of its intention to impose LD at the rate of RM50,000.00 per day. [20] By the letter dated 17.12.2015, Bellworth informed Setiakon of its intention to deduct LD from 7.7.2015 to 3.11.2015 in the sum of RM6,000,000.00 and indicated that Bellworth will deduct the sum of RM1,500,000.00 from Certificate No. 34. [21] Setiakon claimed that it had completed the Works around the end of October 2015. Hence, by the letter dated 26.10.2015, Setiakon requested for an inspection for purposes of the Certificate of Practical Completion (‘CPC’). The Architect was of the view that the Works have not achieved practical completion. [22] Setiakon further alleged that Bellworth had started to take over the Residential Blocks (save for the Penthouse) since 10.1.2016. In addition, the Certificate of Completion and Compliance (‘CCC’) for the Project was obtained on 26.1.2016. [23] Oon 28.1.2016, the Architect issued a Certificate of Partial Completion for Occupied Part (‘CPCOP’) certifying that all the works on Level 6 to Level 26, which represented 85.38% of the total value of the Works, had been completed and taken possession by Bellworth. [24] The CPC was issued on 15.3.2016. [25] On 1.4.2016, Setiakon submitted its appeal against EoT No. 3 on the ground that the reasons which it had submitted previously entitled it to an EoT until 15.3.2016. The Architect responded on 28.4.2016 denying that his assessment of EoT No. 3 was unfair and maintaining that no further EoT would be given. [26] Disputes arose between the parties and Setiakon proceeded to refer the same to arbitration for final determination in accordance with Clause 34.5 of the PAM Contract. [27] Pursuant to the Notice of Arbitration dated 6.8.2019, Setiakon claimed against Bellworth for, among others, the following: “51. …