- Court
- High Court of Malaysia
- Decision date
- 12 Mar 2025
- Case number
- BA-22C-16-05/2024
- Coram
- YA Puan Sumathi a/p Murugiah
- Practice area
- -the Defendant had failed to pay the Plaintiff for the works done in the project upon completion. -no evidence produced to this court to show that there has been any dispute or even query raised by the Defendant at any stage of the project or even after the completion of the same to the Plaintiff or to the Project Architect. -the sum owed to the Plaintiff is clearly admitted by the Defendant at that material time -This is a plain case of non-payment of sums owed for works already carried out and completed by the Plaintiff. The Defendant’s defences raised in this case is nothing more than a mere afterthought and a bare denial
- Version
- Alasan Penghakiman 1
- Published
- 13 May 2025
- Source ID
- 82c8e8e0-698f-46a9-85f3-680799305f26