(ii) Samada Defendan berkewajipan dalam mendapatkan permit pasir dan batu-bata daripada Jabatan Tanah Langkawi (“permit tersebut”) yang merupakan satu syarat duluan sebelum kerja Projek tersebut dapat disempurnakan oleh Plaintiff. First Issue [11] Based on the contemporaneous documents adduced before this Court, the plaintiff had showed it had sent a total of five letters to the defendant pertaining to its claims for the work done (see exhibit B1, p.17 [dated 29.12.2015], p.18 [dated 27.11.2015], pp.19-20 [dated 27.11.2015], p.24 [dated 6.11.2015], pp.25-26 [5.11.2015]). [12] However, the defendant did not respond or refute the plaintiff‟s claim after it had received all the plaintiff‟s letters. [13] The defendant called only one witness, Mohd Niza Bin Abdul Mubin (DW1), who was the general manager of the defendant company at the material time, to give evidence for the defendant. He was charged with coordinating the said Project and daily operation of the company‟s affairs. [14] In cross-examination, DW1 agreed and admitted that the plaintiff had in fact carried out the works as claimed by the plaintiff. DW1 also admitted that the defendant did not reply to any of the plaintiff‟s letters. [15] DW1 further admitted that the plaintiff had in fact carried out the works as claimed. Based on DW1‟s admission alone, the plaintiff has Page 7 of 16 succeeded in proving its case. Although DW1 thinks that the plaintiff ought not to be paid because of the „back-to-back‟ clause in the LA, this does not preclude the plaintiff from discharging its onus in proving its claim on a balance of probabilities. Whether the „back-to-back‟ clause should prevail over the plaintiff‟s entitlement to immediate payment from the defendant is a separate issue which will be dealt with later in the judgment. [16] The plaintiff had made a positive assertion, i.e. that the defendant owned the plaintiff a sum, such positive assertion would compel the defendant to respond if the defendant denied such claim. Unfortunately, the defendant did not do so. This court is of the considered view that the defendant did not discharge its duty to reply the plaintiff‟s letters because when there is a duty to speak or act imposed on a party, and yet, the party keeps silent, this deliberate inaction or silence could be taken as representation to the other party as acceptance of such assertion. On these present facts, the inaction and silence on the defendant‟s part could be taken as representation to the plaintiff that the defendant was not denying the plaintiff‟s claim (see the proposition in the decision of the Federal Court in Public Textiles Berhad v Lembaga Letrik Negara [1976] 1 MLRA 70, p. 73). [17] The rates or prices quoted have to be agreed by the defendant/Employer before they were binding, this was stated in the LA, the defendant‟s counsel submitted. As explained in the preceding paragraph, the defendant did not refute the rates and prices provided by the plaintiff and that could be construed as a representation to the plaintiff that the defendant accepted the rates or prices quoted. Page 8 of 16 [18] The defendant‟s counsel also submitted that the plaintiff failed to prove its actual loss and expenses incurred, therefore, the plaintiff ought not to obtain judgment for the quantum as claimed even if the plaintiff succeeded in proving liability on the defendant‟s part (which was denied). This Court could not accept this submission because the plaintiff‟s claim was based on work done in the said Project. The plaintiff was not claiming for general or special damages, but for work done as stipulated in the LA and Bill of Quantities. All the plaintiff needs to satisfy the Court that it has executed his works, vis-a-vis work done as specified in its scope of works, (which was admitted by the defendant‟s own witness) for the plaintiff to be entitled to its claim. [19] Based on the above evidence before this Court, this Court will not hesitate to find the plaintiff has proved its claims on a balance of probabilities in that the defendant owes the plaintiff the sum as claimed. Hence, the first issue is answered in the affirmative. The Validity of the „back-to-back‟ Clause [20] I hold that the defendant cannot rely on the said back-to-back clause to defend the plaintiff‟s claim for the following reasons. [21] I am of the view that the LA or sub-subcontract would fall within the definition of a „construction work contract‟ in the Construction Industry Payment And Adjudication Act 2012 which came into force on 15.4.2014. The construction of the fringing reef and tidal gates involves construction of a structure or wall as defined as „construction work‟ in the Act. Hence, the Act would be applicable to the present LA. Page 9 of 16 [22] Section 35 of the Act renders a “conditional payment provision” in a construction contract void. [23] I find the said back-to-back clause is a “conditional payment provision” as provided in s.35 of the Act, and is therefore void. [24] The defendant did not refute the plaintiff‟s assertion that there was a previous agreement between the parties that the said back-to-back clause should not be applicable to the plaintiff‟s payments for work done. The counsel for the defendant submitted that the plaintiff should sue LADA for his work done instead of suing the defendant since the plaintiff insisted for a direct payment to be made from LADA to the plaintiff. [25] This is because following from the LA dated 16.7.2017, the plaintiff wrote a letter dated 20.7.2015 (see exhibit B1, p. 41) to the defendant and stated as follows: “2. It was previously agreed that payment to our company for the works done shall be directly assigned from Lembaga Pembangunan Langkawi (LADA) instead of from your good company as per stated in Cluase 3 of Letter of Appointment.” [26] The defendant‟s submission does not hold water. The sub-contract was entered into between the plaintiff and defendant, it is the defendant who owes a contractual obligation to pay the plaintiff for its works done, not LADA. When the plaintiff presented its claims to the defendant, the defendant did not in any occasion suggest that payment should be from Page 10 of 16 LADA or that it was not liable for the plaintiff‟s claim. The defendant could not now rely on the argument that the plaintiff should sue LADA. Second Issue – Who‟s duty to obtain the Permit? [27] It is in evidence that the plaintiff had written numerous letters to the defendant pertaining to the issue of obtaining the Permit (see exhibit B1, p. 27 [dated 14.9.2015], p.28 [dated 4.9.2015], p.29 [dated 28.8.2015], pp.31-32 [dated 24.8.2015], p.36 [dated 17.8.2015], and p.37 [dated 13.8.2015]). [28] The followings are the excerpts from the said letters concerning the enquiries and requests to the defendant to obtain the Permit: Letter dated 13.8.2015 (p. 37 – Exhibit B1) “Dengan segala hormatnya pihak kami merujuk kepada projek di atas dan mesyuarat LADA yang telah diadakan pada 11.08.2015 di mana pihak LADA telah maklumkan bahawa permit untuk pengangkutan pasir akan diselesaikan sebelum 16.08.2015 [emphasis added]” Letter dated 17.8.2015 (p. 37 – Exhibit B1) “2. Pihak kami ingin memaklumkan bahawa Permit Untuk Pengangkutan Pasir & Batu-bata masih belum diperolehi sehingga tarikh hari ini. Oleh itu, pihak kami tidak boleh menyiapkan kerja-kerja untuk Page 11 of 16 projek yang tersebut di atas pada 31.10.2015 seperti yang dicadangkan sebelum ini.