10.02.2022 • Maybank Statement dated 28.02.2022. Transfer on 10.02.2022. Exh. A-1 Encl. 16. • 12th line of Table 2, Amended Annexure A. [10] Prior to making the payment on 6.01.2022 (as stated in item 10 above), the Defendant via his letter dated 5.01.2022 informed the Plaintiff that in respect of the balance Principal Loan Sum amounting to RM4,500,000.00 (due and payable under 12th Instalment on 11.04.2022 upon having paid RM500,0000 on 24.11.2021) it would be paid in 3 instalments before the due date of 11.04.2022 and that all interest and repayment will remain, and be paid in full as per the Agreement. [11] Thereafter, the Defendant failed to pay the following: i) the Contractual Interest in the sum of RM62,500.00 due payable on 11.03.2022 under the 11th Instalment; ii) the Contractual Interest in the sum of RM62,500.00 due payable on 11.04.2022 under the 12th Instalment; and iii) the balance Principal Loan in the sum of RM4 million due payable on 11.04.2022 under the 12th Instalment. [12] By way of the Plaintiff’s then solicitors’ (Messrs Mah-Kamariyah & Philip Koh’s) letter dated 29.9.2022, the Plaintiff demanded from the S/N RipRodWb/kmioZkADyNdgQ Defendant that the sum of RM4,280,027.40 (consisting of balance Principal Loan Sum and the Contractual Interest of RM4,125,000.00 together with the Late Payment Interest of RM155,027.40) due and payable as at 29.9.2022 to be paid within 14 days from the date of the said letter, failing which the Plaintiff shall be entitled to deem the Agreement as terminated and commence legal proceeding against the Defendant. [13] However, the Defendant failed to adhere to the Plaintiff’s demand and rectify the breach. [14] On 26.10.2023, the Plaintiff filed the suit herein. [15] On 10.01.2024, the Plaintiff filed Encl. 10 for summary judgment. Triable Issues [16] The Defendant claims that the Plaintiff has failed to take into account the sum of RM1 million paid towards the principal loan sum and thus failed to reduce the interest accordingly. The Defendant has also alleged that the interest calculation is wrong and the Plaintiff has failed to show the calculations. Court’s Considerations [17] The Plaintiff claim is for RM4,634,438.37 as at 26.10.2023 consisting of: