Content
1 IN THE HIGH COURT IN MALAYA AT KUALA LUMPUR IN THE FEDERAL TERRITORY OF KUALA LUMPUR, MALAYSIA SUIT NO.: WA-22C-3-01/2020 BETWEEN SYARIKAT LETRIK CHEN GUAN SDN. BHD. [Company No.: 198201007046 (86803-T)] ... PLAINTIFF AND IMEJ TENGGARA SDN. BHD. [Company No.: 200701005227 (763226-V)] ... DEFENDANT GROUNDS OF JUDGMENT [1] This suit involves a claim by the Plaintiff, a company that provides services as an electrical and building contractor, against the Defendant who is the employer of a project known as “Cadangan Pembangunan Enterprise Komersial dan Perdagangan (Parcel B) Yang Mengandungi: - Budget Hotel (517 Unit) Di Tingkat 4 Hingga 12 Di Atas Sebahagian Lot 365, 262 dan 174, Seksyen 92, Jalan Loke Yew Dalam, Bandaraya Kuala Lumpur (Design and Build)” (‘Project’). [2] The main contractor for the Project is Bina Goodyear Berhad (‘BGB’). BGB was wound up on 10.9.2014. [3] The Plaintiff was selected as the Nominated Sub-Contractor (‘NSC’) for the “Design, Supply And Installation Of Mechanical & Electrical Works” (‘1st Sub-Contract Works’) for the Project. Subsequently, the Plaintiff was also appointed as the sub-contractor for the works relating to “Rainwater Down Pipe & Sanitary Wares & Fittings Installation” (‘2nd Sub-Contract Works’) and “To Supply and Fix: Table Lamp, Flexible Reading Light and Bedside Wall Lamp” (‘Supply and Installation Works’) under the Project. [4] Basically, the Plaintiff’s claim vide the Writ and Statement of Claim (‘SoC’), which were filed on 23.1.2020, was for the sum of monies allegedly due and payable by the Defendant for the 1st Sub-Contract Works, 2nd Sub-Contract Works and Supply and Installation Works in the total amount of RM1,070,417.60 with interest and costs, or in the alternative, for general damages to be assessed by the Court. [5] The Defendant pleaded that there was no amount due and owing to the Plaintiff and it initially counter-claimed for the sum of RM137,208.84 as the purported overpayment to the Plaintiff. However, this counterclaim was withdrawn on the first day of the trial. [6] The trial was held entirely via Zoom video conferencing for four days in the light of the Movement Control Order which was implemented as a preventive measure by the Federal Government in response to the Covid-19 pandemic which had besieged the country. Four witnesses testified for the Plaintiff whilst the Defendant called only one witness. [7] I had carefully considered the evidence given by these witnesses together with the pleadings, documentary evidence and submissions by the parties and thereupon pronounced that the Plaintiff had proven, on a balance of probabilities, its claim for only the 1st Sub-Contract Works in the sum of RM437,611.30 with interest at the rate of 5% per annum from the date of filing of the suit i.e. 23.1.2020 until full settlement. Costs of RM25,000.00 was ordered to be paid by the Defendant to the Plaintiff, subject to allocatur. [8] Both the Plaintiff and the Defendant are dissatisfied with the decision of the Court and I now provide my full grounds for the same. The Plaintiff’s Case [9] The Plaintiff is a private limited company incorporated in Malaysia and registered under the Companies Act 1965 [Act 125] and having both its registered and business address at Lot 1178, Jalan Subang 3, Taman Industri Sungai Penaga, 47610 Subang Jaya, Selangor. [10] The Defendant is similarly a private limited company incorporated in Malaysia and registered under Act 125 and having its registered address at Suite 23-05, 23rd Floor, Menara Zurich, No. 15, Jalan Dato Abdullah Tahir, 80300 Johor Bahru, Johor. The Defendant’s business address is at B-3-19, Block B, Pusat Komersial Bayu Tasik, Persiaran Southkey 1, Kota South Key, 80150 Johor Bahru, Johor. - 1st Sub-Contract Works [11] On 21.6.2010, the Plaintiff had submitted its “Quotation for Mechanical & Electrical Works” to the Defendant for the Project (‘Quotation’). [12] In the Letter of Award dated 10.9.2010 (‘1st Letter of Award’) issued by BGB to the Plaintiff, BGB stated that it was informed by the Defendant via the letter dated 1.9.2010 that the Plaintiff’s tender with a revised price of RM11,331,884.00 (‘1st Sub-Contract Sum’) has been accepted and that the Plaintiff has been selected to become BGB’s NSC for the 1st Sub-Contract Works. [13] According to the Plaintiff, the 1st Sub-Contract Works were duly completed. Hence, on 17.8.2012, the Plaintiff submitted its Penultimate Progress Claim for the sum of RM900,986.04 whereby the Adjusted Contract Sum was RM9,558,742.30 (‘Final 1st Sub-Contract Sum’). [14] Based on the Plaintiff’s calculation –