a question of construction of document (Intelek).”. [42] The Federal Court went on to state: “[153] Where it is a question of fact, ‘The arbitrators (remain) the masters of the facts. On an appeal the court must decide any questions of law arising from the award on the basis of full and unqualified acceptance of the findings of fact of the Civil Appeal No. W-02(C)(A)-19-01/2018 21 arbitrators. It is irrelevant whether the court considers these findings to be right or wrong. It also does not matter how obvious a mistake by the arbitrators on issues of fact might be or what the scale of financial correspondences of the mistake of fact might be. That is, of course, an unsurprising position. After all, the very reason why parties conclude an arbitration agreement is because they do not wish to litigate in the courts. Parties who submit their disputes to arbitration bind themselves by agreement to honour the arbitrators’ award on the facts. The principle of party autonomy decrees that a court ought never to question the arbitrators’ findings of fact’ (The ‘Beleares’ at pg 228) ‘… on findings of facts an arbitrator is the sole judge. … … [157] The scope of the words ‘arising out of an award’ in s. 42 was first enunciated in Majlis Amanah Rakyat v Kausar Corp, citing Universal Petroleum Co v Handels und Transport GmbH [1987] 1 WLR 1178, where Mohamad Ariff J, as he then was, said that ‘A question of law must arise out of an award and not out of the arbitration’ (followed by Rmarine Engineering (M) Sdn Bhd v Bank Islam Malaysia Bhd [2012] 10 MLJ 453; [2012] 7 CLJ 540, Sanlaiman, and Tune Insurance; see also The Arbitration Act 2005 at pp 200-201).”. [43] Reverting to the instant appeal, and applying the principles as set out in Far East Holdings Bhd (supra), we found that all the questions referred are not questions of law arising out of the award on ‘the basis of full and unqualified acceptance of the findings of fact of the arbitrator’. The questions are of mixed fact and law which called upon the court to either re-examine or re-interpret the facts or application of the law by the arbitrator. [44] Question No. 1 pertained to the issue of who bears the responsibility of the NSCs. The plaintiff contended that the arbitrator’s decision in concluding that the determination of the contract by the defendant was valid Civil Appeal No. W-02(C)(A)-19-01/2018 22 by reason that the architect had failed to issue CNC to the NSCs in effect had rendered the plaintiff responsible for the NSCs. As a matter of fact, and consonant with clause 27.7 of the main contract which stipulates that the plaintiff shall not be liable for the NSCs, the arbitrator did not find that the plaintiff was responsible for the NSCs. That the plaintiff was found responsible for the NSCs was the conclusion made by the learned judge as evident by paragraph 54 of her grounds of judgment: “3rd Error of law – Question 1 [54] On this issue, the Arbitrator made a finding that the defendant was entitled to determine the Main Contract because he finds that the NSCs were also responsible for the delay. The Arbitrator has held that the defendant was justified in determining the Main Contract by relying on the NSCs’ delay and the non-issuance of the CNC by the Architect to the NSCs. This simply means that the plaintiff as the employer is held responsible for the delays of the NSCs.” (Emphasis added) [45] Question No. 1 did not therefore arise out of the arbitration award and it cannot form the basis of a question of law to be entertained by the court under section 42. [46] In any event, based on oral and documentary evidence, the arbitrator had made a specific finding of fact that the delay in the works were attributable to both the defendant and the NSCs. The arbitrator also found that it was not disputed that both the defendant and the NSCs contributed to the delays of the works. Flowing from this undisputed fact, the architect should have issued the CNC when asked to do so by the defendant. The arbitrator made a further finding of fact that the architect failed to comply with Civil Appeal No. W-02(C)(A)-19-01/2018 23 clause 27.5 of the main contract and that this failure by the architect interfered with the defendant’s right of recourse against the NSCs. [47] In respect of Question 2, the learned judge accepted the plaintiff’s contention that the defendant and the NSCs had expressly agreed that any contractual right to LAD in the event of delay for the completion of the works was rendered inoperative by the deletion or non-entry of any terms on LAD in the appendix in the nominated sub-contracts. Consequently, the architect is not obliged, as a matter of law, to issue a CNC in respect of the NSCs under the main contract, in view of the fact that it would be of no consequence. The arbitrator therefore fell into error in concluding that the defendant had lost its valid contractual right of recourse for loss and damage against the NSCs pursuant to clause 27.2(vi) of the main contract due to the non-issuance of the CNC by the architect. [48] On the issue of absence of the provision for LAD, we found that the arbitrator had specifically referred to clause 27.2(vi) of the main contract and clause 7 of the nominated sub-contracts, where both these clauses provide for loss and/or damage for non-completion. [49] It was not disputed that the defendant had to pay RM11,600,000.00 as compensation sum to the plaintiff for the extension of time. The arbitrator made a finding of fact that the compensation sum of RM11,600,000.00 was a consideration for the second revised completion date which was undertaken outside the contractual mechanism for extension of time. Based on the documentary evidence, the arbitrator had also made a finding of fact that the defendant had maintained its right to seek recourse against the Civil Appeal No. W-02(C)(A)-19-01/2018 24 NSCs in the form of apportionment of the compensation sum. There was no interpretation of the provision for LAD by the arbitrator. [50] In respect of Questions 3 and 4, the learned judge held that the arbitrator had made an error of law in failing to interpret that both supplemental agreements apply to the nominated sub-contract because both the main contract and the nominated sub-contract were designed to work together. Therefore, if the main works had been given extension, by necessary implication the extension must equally apply to the nominated sub-contracts. [51] Again, these were not questions of law arising out of the award, but arising out of the assumption of facts implied by the learned judge which facts were not found by the arbitrator. [52] Question 3 purports to state that the termination by the defendant was on the grounds that the architect was obliged in law to issue the CNC to the NSCs; that the defendant has a right of recourse against the NSCs and that the architect was wrong to issue the certificate of direct payment. It relates to the factual findings of the arbitrator that the architect’s failure to issue the CNC frustrated the defendant’s recourse against the NSCs as without the said CNC neither damages can be claimed nor amendments to the certificates, can be made. Be that as it may, the determination of the main contract by the defendant as can be seen from the award was made pursuant to clause 26.1 for non-payment and not on the grounds set out by the plaintiff in Question 3(d). Civil Appeal No. W-02(C)(A)-19-01/2018 25 [53] In so far as Question 4 is concerned, it was premised on a disputed interpretation of facts relating to the SAs and the understanding of the recourse that the defendant had against the NSCs. The question was framed premised on the necessary implication drawn by the plaintiff and accepted by the learned judge that the extension of time granted to the defendant must equally apply to the NSCs. [54] With respect, the learned judge, upon re-assessment of that disputed interpretation of facts, was not entitled to come to an opposite conclusion from what was reached by the arbitrator. Neither was the learned judge seized with the jurisdiction to draw her own inferences from the facts before the arbitrator nor can Her Ladyship find an implication that was factually rejected by the arbitrator. More so, when as highlighted by the affidavit evidence of the defendant in the High Court, the architect and the quantity surveyor (who had testified in the arbitration) had themselves recognised in the arbitration that the purchased extension of time under SA No. 2 did not automatically extend to the NSCs. [55] On Question 5, the learned judge held that the arbitrator erred in law in concluding that a CNC ought to have been issued by the architect against the NSCs pursuant to clause 27.2 (vi) when requested by the defendant as the architect could not have issued the CNC by reason that time for completion had not lapsed. [56] Question 5 likewise was not a question of law arising out of the award. It was a hypothetical question premised on the learned judge re-examining the effect of the SAs. With respect, it was not open to the learned judge to entertain questions grounded on disputed facts or varying legal interpretation Civil Appeal No. W-02(C)(A)-19-01/2018 26 that could be given to those facts. As stated by the Federal Court in Far East Holdings Bhd (supra), the plaintiff could not refer questions of law that were wholly reliant on a reversal of facts found by the arbitrator. It is also pertinent to note that clause 8 of the nominated sub-contract provides for extension of time but this clause, as the evidence revealed, was not availed by the NSC. [57] Question 6 was in relation to the issue of the architect’s impartiality and independence. The plaintiff contended that the arbitrator had erred in law in finding that the architect lacks impartiality and independence by reason inter alia that the architect’s professional services agreement contains a stipulation whereby the architect is required to refer to the plaintiff for comments on all contractual matters. [58] While the arbitrator took cognisance of the fact that the architect’s professional services agreement with the plaintiff contains a stipulation for the architect to refer to the plaintiff for comments on all contractual matters, it was the architect’s failure to comply with clause 27.5 of the main contract and how the main contract was administered by the architect that triggered the finding of partiality. The finding was made consequent upon the arbitrator’s finding that critical nominated sub-contract works had been delayed, thereby causing overall delay of the completion of the works. The architect having known that the NSCs had not obtained an extension of time and having known that the defendant would have recourse to recover from the NSCs the loss and damage suffered for the delay, ought to have acted on the defendant’s request for the issuance of CNC. [59] The arbitrator made a specific finding of fact that the architect was partial based on his assessment of both the oral and documentary evidence. Civil Appeal No. W-02(C)(A)-19-01/2018 27 Again we found that this was a mixed question of law and fact, requiring the court to re-examine the correctness of the architect’s actions and the consequence of those actions on the defendant’s right of recourse, which question did not fall under section 42 of the AA 2005. [60] On Question 7, the plaintiff argued that the arbitrator erred in law in holding that the plaintiff’s invocation of clause 27.4 of the main contract was invalid as no actual payment was made to the NSCs. In this regard, the plaintiff asserted that upon determination of the contract, the plaintiff could no longer validly proceed with the direct payment of sums due under IPC no. 32R to the NSCs. [61] As regards direct payment by the plaintiff, on 22.9.2010 the architect issued the certificate, followed by a letter dated 23.9.2010 where the architect advised the plaintiff to make direct payment to the NSCs. It was a fact that payment under IPC No. 32R was not made to the NSCs but was placed by the plaintiff into an escrow account. The arbitrator made a finding that by clause 27.4 of the main contract, actual payment had to be made and that without actual payment to either the defendant or the NSCs, the plaintiff had obviously not honoured the IPC No. 32R. Further, given his earlier determination that the architect had wrongly effected the direct payment mechanism, the defendant was entitled to full payment of IPC No. 32R. [62] We were of the view that Question 7 likewise was not a question arising out of the award. Civil Appeal No. W-02(C)(A)-19-01/2018 28 Conclusion [63] In light of all the above, we were unanimous in our decision that the learned judge erred in finding that this was a proper case under section 42. The questions posed do not fall under section 42. On the ground that the tests under section 42(1) of the AA 2005 have not been met, we allowed the appeal with costs. We set aside the order of the High Court and we reinstated the arbitrator’s award. Dated: 28th November 2018 signed (TENGKU MAIMUN BINTI TUAN MAT) Judge Court of Appeal Counsel/Solicitors : For the Appellant: Dato’ Cyrus Das (Logan Sabapathy, Felix Dorairaj and Alithea Wong with him) Messrs. Dorairaj Low & Teh For the Respondent: Rajendra Navaratnam (Mak Hon Pan and Sachpreetraj Singh Sohanpal with him) Messrs. Azman Davidson & Co.