16 ALR 363, the Privy Council helpfully set out the principles upon which the court will act in implying terms to the contract. i.e. 1)The term must be reasonable and equitable. 2) It must be necessary to give business efficacy to the contract so that no term will be implied if the contract is effective without it. 10 3) It must be so obvious that is goes without saying. 4) It must be capable of clear expression. 5) It must not contradict any express terms of the contract. See Yap Nyo Nyok v Bath Pharmacy Sdn Bhd [1993] 2 MLJ 250 and the Federal Court case of Sababumi (Sandakan) Sdn Bhd v Datuk Yap Pak Leong [1998] 3 MLJ 151 where the Federal Court applied both the “officious bystander test” and the “business efficacy test”. [27] Learned counsel for the Plaintiff had cited the above cases to justify importing implied terms that the Defendant as contractor would properly carry out the works with proper workmanship and materials. That is already a given and in fact the cases cited would be more relevant to importing and imposing an implied term of extension of time if additional Variation works are instructed, in this case by the M&E Consultant. [28] Time is generally not of the essence in a construction contract and if the Plaintiff had wanted to declare the Defendant in default after 30.11.2009, one would have expected a Notice of default given to the Defendant. As no Notice was given time becomes at large and the Defendant as contractor should complete the works within a reasonable time. 11 [29] The Defendant handed over the building with the works duly completed on 6.1.2010. In the circumstances I do not think that the Defendant could be said to be in default since 1.12.2009 till 6.1.2010. [30] This is also a case where the Plaintiff had agreed to a scheduled monthly payments to the Defendant but had defaulted in the payments. The final Contract Sum after negotiation and with a 3% discount given from the Quoted Sum was RM9,780,726.00 with a fixed payment schedule in the following manner: Gross Retention Net-Sept’ 09. 3,000,000. 150,000. 2,850,000 -Oct’ 09. 1,000,000. 50,000. 950,000 -Nov’ 09. 1,000,000. 50,000. 950,000 -Dec’ 09. 1,000,000. 50,000. 950,000 -Jan’ 10. 1,000,000. 50,000. 950,000 -Feb’ 10. 500,000. 50,000. 500,000 -Mar’ 10. Balance [31] The Plaintiff paid the initial first few payments according to the agreed payment schedule in the Contract. However the Plaintiff defaulted in November 2009 at a crucial time when the Defendant had a balance one month to complete the Works. 12 [32] The Plaintiff tried to make it up for the month of December 2009 in the sum of RM1,057,863.00 though this still fell short of the combined sum of November and December 2009 of RM1,900,000.00. [33] The fact that the Hotel commenced operation on 16.1.2010 was admitted by the Plaintiff’s own witness PW 1, Mr Tan Wee Lee, the Manager of the Plaintiff as follows at page 50 NOE: “113) S: When did the Hotel commence operation, isn’t it 16.1.2010? J: Yes, we announced it to the public on that date. 114) S: And it’s also posted on your website that the Hotel commenced business on 16/1/2010? J: Yes, it was” [34] In a case like this where there is no Notice of default, no Certificate of Non-Completion and delay in the agreed schedule of payment by the Plaintiff, it can hardly be said that the Defendant as contractor was in default from 1.12.2009 to 6.1.2010. [35] Assuming for a moment that there was breach on the part of the Defendant in failure to complete the works by 30.11.2009 and only completed by 6.1.2010, has the Plaintiff proved their loss in the Room Charges for the year 2010 from January to December based on total of 13 non-saleable rooms amounting to RM 3,823,960.00 as claimed in the Amended Statement of Claim? [36] To begin with the damages has to be strictly proved. In Popular Industries Limited v. Eastern Garment Manufacturing Sdn Bhd [1989] 3 MLJ 360 it was highlighted as follows at pages 367-369: “It is axiomatic that a plaintiff seeking substantial damages has the burden of proving both the fact and the amount of damages before he can recover. If he proves neither, the action will fail or he may be awarded only nominal damages upon proof of the contravention of a right. Thus nominal damages may be awarded in all cases of breach of contract. And, where damage is shown but its amount is not proved sufficiently or at all, the court usually decree nominal damages. When, as here, the claim is for the difference between the contract price and a clear and undoubted market price, absolute certainty in proving damages is possible and therefore the court will expect precise evidence to be given. … In all the circumstances, reason and justice pointed to inevitable conclusion that although the plaintiffs had shown the fact of damage, 14 no evidence or no sufficient evidence had been adduced as to its amount with the perhaps unfortunate result that it is virtually impossible to assess damages. Accordingly, all I can do is to make an award of nominal damages of US500, that being the currency of the contract.” [37] There is no basis for the Plaintiff to claim the gross Room Charges because if at all there is loss suffered by the Plaintiff it must be confined to the loss of profit attributed to the Rooms Charges that could not be charged because the guests have to be turned away as a result of the rooms not being ready. [38] However there is no evidence led as to the costs in running the Hotel when divided by the number of rooms. The damage suffered must be limited to the loss of profit and not loss of Room Charges or loss of revenue. To charge loss of Room Charges to the Defendant would mean there is no costs element at all in the running of the Hotel! That cannot be right. Costs in running a Hotel would cover staff costs, food and beverage costs, utilities, marketing and promotion costs and the like. [39] From the documents prepared by the Plaintiff to substantiate and support their claim for loss of Room Charges there is clearly a case where going by rooms available for the various months from January to December 15 2010 there is not full occupancy of the rooms available. See pages 733-745 Tab O of Plaintiff’s Core Bundle of Documents. [40] From the evidence of PW 2, Miss Laura Daniel, who worked as a secretary in TCY Century Management Sdn Bhd, the company that manages the Hotel, we learned that the occupancy rate of the Hotel even based on the rooms available, according to her, was 20.44% in January 2010 andincreases to 53.05% by December 2010. As she only started work in August 2010 she had no personal knowledge of the so-called loss of Room Charges from January to July 2010. When asked why the rooms were not let out she was candid to admit that technically she did not know. [41] That being the case, there is no basis for charging the so-called Rooms not available to the Defendant when the Plaintiff themselves could not fully let out the available rooms. It is of course not unusual and indeed quite common for a new hotel not to have full occupancy during the initial years of business. To charge the Defendant based on a 100% occupancy when that was not achieved throughout 2010 would be to require the Defendant to pay for what the Plaintiff could not achieve on their own and that would amount to a windfall and be against all known principles of assessment of damages! 16 [42] Learned counsel for the Defendant advanced yet another ground as to why the Plaintiff is not entitled to a claim of RM3,823,960.00. The Plaintiff has entered into a management agreement whereby one of its subsidiaries TCY Century Management Sdn Bhd (“TCY”) shall manage the Hotel and pay to the Plaintiff 30% of the net revenue as provided for in Clause 4.2. The agreement is at Tab V of the Plaintiff’s Core Bundle of Documents. [43] It is trite law that even wholly owned subsidiaries are separate legal entities from its parent company. To make it even clearer it was provided in Clause 4.5 that TCY was not operating the Hotel as an agent of the Plaintiff; in other words TCY was a separate and distinct entity operating the Hotel in its own right. [44] If authority is needed one can cite the case of Mackt Logistics (M) Sdn Bhd v. Malaysian Airline System Bhd [2014] 2 MLJ 518 where it was observed that: “[24] In Malaysia, the Salomon principle was applied in Abdul Aziz bin