(ii) Were the buildings constructed in a good and workmanlike manner in accordance with the building plans and specifications approved by the relevant authorities? [47] The CCC — Perakuan Siap dan Pematuhan (Borang F) — for the buildings constructed on the 11 subdivided lots of the land was issued by the consultant architect of the Project on 17.04.2014. [48] In the CCC, the architect certified that the buildings were constructed in accordance with the approved plans, the Act and the Undang-Undang Kecil Bangunan Seragam Selangor 1986. He also certified that the buildings were safe and fit for habitation. An excerpt of the architect’s certification on the CCC is reproduced below: Setelah berpuas hati bahawa bangunan/bangunan-bangunan itu telah siap menurut pelan yang diluluskan No. MDKS 280/3/11/2011-216 (42/2011) bertarikh 9 MEI 2011. Saya telah mengawai pembinaan dan penyiapan bangunan/bangunan-bangunan itu dan sepanjang pengetahuan dan keperpercayaan saya kerja / kerja-kerja itu adalah mengikut Akta, Undang-Undang Kecil Bangunan Seragam Selangor 1986 dan pelan-pelan yang diluluskan. Saya dengan ini memperakui bahawa bangunan/bangunan-bangunan itu adalah selamat dan layak untuk diduduki. [Emphasis added] [49] In Allan Kinsey & Anor v Sunway Rahman Putra Sdn Bhd & Anor, Dekon Sdn Bhd (Third Party) [2015] 4 CLJ 624; [2015] AMEJ 722 (“Allan Kinsey”), the first defendant had delivered vacant possession of the property the plaintiff with, inter alia, the support of a certificate of fitness and occupation (“CFO”) signed by the first defendant's architect certifying that the said property had been duly constructed and completed in accordance with all relevant acts, by-laws and regulations and all conditions imposed by the appropriate authority in respect of the issuance of the certificate of fitness for occupation had been duly complied with. Prasad Abraham J (as he then was) held that the issuance of the CFO points that the said property had been constructed in a good and workman-like manner in accordance with the relevant laws and regulations. He cited the case of Pentadel Sdn Bhd v. TPPT Sdn Bhd [2011] CLJU 1283; [2011] AMEJ 0524, where Hadhariah Syed Ismail J (as she then was) held: Under a construction contract, a certificate issued by the relevant authorities certifying the works had been completed prima facie proof that that the works had been completed. [50] The High Court in Pua Yu Len v Bandar Eco Setia Sdn Bhd [2018] MLJU 761; [2018] CLJU 821; [2018] AMEJ 0640 (“Pua Yu Len”), citing with approval the decision in Allan Kinsey, held that the CCC issued for a property is prima facie evidence that the property was in built in a good and workmanlike manner; that it had conformed with the approved building plans and that the property in safe for occupation. See Mee Chun J (as she then was) said in Pua Yu Len: [58] The meaning of the term 'good and workmanlike manner' in clause 13 was explained in the case of Hancock and others v. B W Brazier (Anerley) Ltd [1966] 2 All ER 1 at page 8 where it relates to "the way in which the work was carried out rather than to the materials, and that clause requires that the work shall be carried out with due skill, care and judgment." Hence the clause deals specifically with workmanship. [59] In Kiing Teck Hoon v. T-Phoon Aluminium Sdn Bhd & Ors [2007] CLJU 281; [2007] 1 LNS 281; [2007] MLJU 37, it was held that to establish a case under this clause, it must be shown that the building was not constructed in a workmanlike manner in accordance with the building plans, drawings and specifications. …………….. [61] CCC issued for the property on 22.5.2013 is prima facie evidence that the property was built in a good and workmanlike manner and has conformed with the approved building plans and the property is safe for occupation. In Allan Kinsey & Anor v. Sunway Rahman Putra Sdn Bhd & Anor, Dekon Sdn Bhd (Third Party) [2015] 4 CLJ 624, it was held at page 630 that the issuance of the certificate of fitness for occupation will point to compliance and satisfaction that the property is built in a good and workmanlike manner in accordance with the fourth schedule and approved plans. [Emphasis added] [51] Hence, in this instant case, for the plaintiff to prove its case that the defendant had failed to construct Premise 1 and Premise 2 in a good and workmanlike manner, it must show that both premises were not constructed in a good and workmanlike manner in accordance with the building plans and specifications approved by the relevant authorities. [52] However, there is nothing the evidence adduced before this Court that showed that the defendant’s workmanship in constructing the premises was not in accordance with the building plans and/or the specifications approved by the relevant authorities and the applicable laws and regulations. [53] The plaintiff also did not adduce any evidence to prove that at the time delivery of vacant possession, Premise 1 and Premise 2 were not safe for occupation. In fact, the plaintiff in QA17 of his witness statement stated that since the delivery of vacant possession of the premises, he had rented both Premise 1 and Premise 2. The ground floor of Premise 1 and both floors of Premise 2 were rented to PW2. [54] Furthermore, the plaintiff pleaded in paragraph 15(a) of his Amended Reply and Defence to Counterclaim, that PW2 had demolished the common wall between Premise 1 and Premise 2 in August 2015. [55] As held in Allan Kinsey and Pua Yu Len, the CCC issued is prima facie evidence that the buildings were built in compliance with clause 5 of the JVA; that they were constructed in a good and workmanlike manner in accordance with laws; and the property is safe for occupation. [56] The prima facie evidence provided by the CCC was supported by DW1’s testimony and the documents produced by the defendant during the trial. [57] The evidence showed that the defendant commenced the construction of the premises commence after the building plan was approved by MDKS. The defendant’s architect received the “Kelulusan Pelan Bangunan” from MDKS on 09.05.2011 and the architect gave the Notice to Commence Construction to MDKS on 22.06.2011. [58] The evidence further showed that after the earth works were completed, the defendant had appointed a licensed land surveyor to prepare the “as built filled up earth plan”. Also, that the defendant had engaged a full-time site supervisor on site during the entire construction period. [59] As regards the piling works, the evidence showed that the piling works were carried out on the pile points marked by the surveyor, that a pile dynamic load test was conducted to confirm the pile length and capacity and that during the piling works, a blow count record was recorded for every pile. In addition, an as built pile survey was done to verify the pile position after the completion of the piling works. [60] The plaintiff, on the other hand, did not provide any evidence to disprove the prima facie evidence provided by the CCC that the premises were built in a good and workmanlike manner. He also did not adduce any evidence to show that either Premise 1 or Premise 2 was not constructed in accordance with the building plans and specifications approved by the relevant authorities. Findings on sub-issue (b)(ii) [61] This Court finds that, for the above reasons, the plaintiff failed to disprove and/or rebut the prima facie evidence in the CCC that the buildings and Premise 1 and Premise 2 had been (i) duly constructed and completed (a) in a good and workmanlike manner; (b) in accordance with all relevant acts, by-laws and regulations and all conditions imposed by the appropriate authority; and (ii) is safe for occupation. Finding on issue (b): [62] Based on the findings in sub-issues (b)(i) and (ii), this Court finds that the plaintiff had failed to discharge his burden of proof that the defendant had breached the JVA or its duty of care to the plaintiff as particularised in the statement of claim. Issue (c): Whether the Plaintiff has proven that the defects to Premise 1 and 2 were caused by poor construction quality or settlement of the foundation? Plaintiff’s Case [63] The plaintiff’s case is that the settlement of the foundation had occurred since the joint inspection in May 2014. He claims that the defects in Premise 1 and Premise 2 were caused by the poor construction quality and the settlement on the building foundation, which amounted to a total failure of consideration by the defendant, and that entitles him to rescind the transfer of both Premise 1 and Premise 2 to him and claim damages based on the current price of both premises from the defendant. [64] The plaintiff appointed AMAS FM Consultant Sdn Bhd (“AMAS”) to inspect Premise 1 and Premise 2. AMAS inspected both properties twice: the first time from 12 to 20 September 2017 and the second time on 2 October 2017. [65] The plaintiff pleaded in para. 21 of the statement of claim that the inspection by AMAS identified that the cause of damages and the defects is poor construction quality. [66] In October 2018, the plaintiff appointed Greenex Consultant (“Greenex”), a consultant engineering firm, to investigate Premise 1 and Premise 2. In its report dated 29.10.2018, Greenex stated that based on its visual inspection on 27.11.2018 of seven units of the double-storey building in Jalan Ria 2, Tanjong Karang, Kuala Selangor concluded that the cracks on the building were due to the settlement of the foundation of the building. [67] The plaintiff pleaded in para. 26 of the statement of claim that the investigation by Greenex confirmed that the settlement in the foundation of Premise 1 and 2 is substantial and that the cracks in the building was caused by settlement in the foundation. [68] He also pleaded in para. 27 of the statement of claim that on 29.01.2019 the Jabatan Kawalan Bangunan Majlis Daerah Kuala Selangor had issued a Notis Mengosongkan Bangunan (Notice to Vacate) for Premise 1 and Premise 2 because the building was unsafe. Defendant’s Case [69] The defendant’s case is that the AMAS inspection was conducted three years after the delivery of vacant possession. And that it was a visual inspection only. [70] As regards the inspection by Greenex, the defendant submits that it was conducted four years after delivery of vacant possession. Also, the inspection was limited to a visual inspection only and had relied mainly on the earlier report by AMAS. [71] Tan Kuan Leong (PW5) the principal of Greenex, had conducted the inspection and prepared Greenex’s expert report (marked as “P4”). PW5 concluded in the said report that the excessive cracks to the buildings were due to the settlement of the foundation: see para. 8.0 of P4. [72] During the trial PW5 confirmed that his conclusion was reached based on his visual inspection of the shop lots. PW5 said that he conducted a visual inspection only. [73] Additionally, PW5 confirmed that he did not determine the root cause of the foundation failure. This is because another investigation needs to be to be done to find out why the foundation failed. PW5 said that he did not conduct the further investigation to determine the cause of the foundation failure because it was not within his scope of work. [74] In fact, PW5 stated that his report was not to find out what was the root cause of the foundation failure: Enc. 105 / NOP / p.186 lines 1-7 But we don’t know why the ….. as what you asked, why the ….. what cause the foundation failed, we need to do another investigation. Defendant’s Counsel: Exactly. That’s what I want to hear. This, this is not my scope of work. Enc. 105 / NOP / p.216 lines 29-34; p. 217 lines 2-8 I’m finding root cause for the excessive cracking and the settlement for the building, why the building so excessively cracked. This is my term and reference for my report. My report is not find out what are the root cause of the foundation failure. Defendant’s Counsel: So …. Because the …. they engaged me to get why the building crack, so excessive cracked. So, I find the root cause of the excessive cracked not the root cause of the foundation failure. That one is second stage. It’s good as what you say … advisable to go further to investigate the foundation failure. [75] Learned counsel for the defendant submits that on this basis alone, i.e. the fact that PW5 did not investigate the cause of the foundation failure, PW5’s expert opinion is not necessary and is of no evidential value at all. He cites the case of Sim Ah Song & Anor v R [1951] 1 MLJ 150; [1951] CLJU 83, where Brown Ag CJ said the following with respect to expert evidence: The business of an expert witness is to draw upon the store of his knowledge and experience in order to explain some matter which his experience should qualify him to understand. He is quite entitled to express his opinion, which indeed is the natural corollary of his explanation. But a bare expression of his opinion has no evidential value at all. Unless he gives an explanation which supplies the understanding of the subject which the Court lacks, the Court is in no better position than it was before to determine the question which it is its duty to determine, and if the Court acts upon a bare expression of the expert's opinion the determination of the question becomes that of the expert and not of the Court. [Emphasis added] [76] Here, PW5 did not investigate the cause of the foundation failure in the building because “it was not in his scope of work”. Also, his expert report was a bare expression of his opinion — as he told this Court he did not conduct any test to determine the cause of the failure of the foundation. He made his determination based solely on his visual inspection of the building. [77] The defendant further submits that Greenex’s expert report (P4) also does not comply with the procedural requirements of expert’s report in Order 40A rule 3(2) of the Rules of Court 2012 (“ROC 2012”), which states: