the summary judgment which was entered by the Plaintiff against the Defendant for profit and attendance fees for Stitec, ASC and Nova Nexus (see subpara 11(d) above). The Plaintiff benefitted from the arrangement, and it affirmed the same by applying for, and obtaining, the said summary judgment. As such, the Plaintiff cannot, through the testimony of PW4 and the Plaintiff’s Draft FA, contend that payment for any sum due under the nominated sub-contracts to these NSCs was never its responsibility, and that the Defendant’s sub-contract price was not reduced correspondingly by the value of the sub-contracts awarded to these NSCs and remained at the original sum of RM108,811,854.83. [78] The Plaintiff’s retort by way of its pleadings was, as outlined previously, a bare denial. Legally, the Plaintiff is not allowed to set up a positive case. In any event, the Plaintiff’s reliance on the second part of Clause A(iii) of the LoA in submitting that the scope of works remains under the Defendant’s responsibility and that the contract sum is not reduced S/N yrQ9pKi3j0eIe9E7JkAWjw by virtue of the NSCs’ contracts, is totally misconceived. The relevant part of Clause A(iii) of the LoA states as follows: “In the event of a default termination of any NSC’s employment, we will not be made responsible to complete the Works under any of the above NSC contracts and to bear extra costs incurred to complete the Works. You shall be responsible and bear all costs in completing the above Works in an orderly and timely manner to ensure completion of the Project. We reserve the rights to claim for any loss and/or extra expenses incurred due to any delay caused by this event.”. [79] By reading the clear words in the said part of Clause A(iii) of the LoA, it is obvious that it does not apply in the factual matrix of this case because there is no “default termination of any NSC’s employment”. In such situation, the sums due to the Defendant will be reduced corresponding to the amounts paid or payable to the NSCs. In effect, the Plaintiff does not have to pay the Defendant that part of the NSCs’ contract sum as it is the Plaintiff who will pay the NSCs. It is only in the event of default of any NSCs resulting in termination of the NSCs’ S/N yrQ9pKi3j0eIe9E7JkAWjw employment that the remaining scope of works which is left unfinished by the NSCs becomes the Defendant’s responsibility to complete. [80] Mr. Balbir Singh has rightfully articulated that the Plaintiff’s argument is circular, in that the net effect is still the same as what the Defendant is contending. Instead of saying that the Defendant’s contract sum has been reduced, it can be expressed that the amount due to the Defendant has been reduced. In both cases, the sums due to the NSCs must be paid. In the end, the monies will end up in the NSCs’ pockets, only by a different route. [81] Based on the oral and documentary evidence, the Court is satisfied that the Defendant has proven, on a balance of probabilities, that the contract sum has been reduced to RM63,018,535.83. S/N yrQ9pKi3j0eIe9E7JkAWjw - Whether the counterclaim is premature in view of Clause C.2 of the LoA [82] Proceeding next to the Plaintiff’s contention that the counterclaim is premature, this argument was premised on Clause C.2 of the LoA as quoted earlier, specifically the words “Payments for all works under Item A above including all differences between our contract sum to you and the contract sum to NSCs shall be made to you within 7 working days from the receipt of our claims subject to 3 (a), (b), (c) and (d) below …” (emphasis added). According to the Plaintiff, its obligation to pay the Defendant the amount due upon the issuance of the CPC does not arise until the Plaintiff and all the NSCs are paid first. PW4 had testified that up to the stage of the issuance of the CPC, the Plaintiff did not receive payment from KKP in the sum of RM25 million, inclusive of Goods and Services Tax. [83] The Defendant takes the position that Clause C.2 of the LoA is a “pay when paid” clause as opposed to a “pay if paid” clause. S/N yrQ9pKi3j0eIe9E7JkAWjw [84] In Globe Engineering Sdn Bhd v Bina Jati Sdn Bhd [2014] 5 MLJ 145, Jeffrey Tan FCJ, in delivering the judgment of the Federal Court, extensively discussed the approach of the courts within the country and beyond in determining whether a contractual provision is a “when” clause or an “if” clause and legal articles which have been written on this matter. The Court finally answered the first leave question that upon proper construction of the clause in question, it was a provision that merely fixed time for payment but did not absolve the respondent of liability to pay the amount certified and attributable to the work executed by the appellant. In the course of the analysis, the Court held: “[32] Time to honour payment to the appellant was contingent upon the time that the respondent would receive payment from the employer. That which was contingent was time for payment. But the fact that time for payment was so contingent could not reasonably extend to mean that even liability of the respondent was contingent, in the sense that the respondent would walk free MP the employer defaulted on the contract. For such a construction, there must be clear and unambiguous provisions to the effect that the liability of the respondent to pay the appellant, as opposed to time for payment, was S/N yrQ9pKi3j0eIe9E7JkAWjw contingent upon receipt of payment by the respondent from the employer. It must be universal truth that it need not even be said between contracting parties, that goods and services will naturally be paid by the receiving party. That is self-evident. ‘So when one is concerned with a building contract one starts with the presumption that each party is to be entitled to all those remedies for its breach as would arise by operation of law, including the remedy of setting up a breach of warranty in diminution or extinction of the price of material supplied or work executed under the contract. To rebut that presumption one must be able to find in the contract clear unequivocal words in which the parties have expressed their agreement that this remedy shall not be available in respect of breaches of that particular contract’ (Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd [1974] AC 689 at p 718 per Lord Diplock). The burden is on the party who proposes otherwise, to show that payment was on an NP basis. Hence, the burden was on the respondent to show that liability for payment was contingent. Since there were no such provisions to that effect or from which that could be so construed, it could not be so read into the subcontract where it was silent, that the liability of the respondent was contingent. Time for payment of the certificates was contingent. But under para 14 and cl 11(b), the liability of the respondent was not contingent. The respondent was liable even MP the employer defaulted on the S/N yrQ9pKi3j0eIe9E7JkAWjw contract (for an analogy, see Scobie & Mcintosh Ltd v Clayton Bowmore Ltd (1990) 23 ConLR 78, where it was held that with repudiation of the subcontract by the main contractor and which was accepted by the subcontractor, the primary obligations of the party in default which remained unperformed was substituted by a secondary obligation to compensate the subcontractor for loss sustained in consequence of the non-performance of the primary obligations).” (emphasis added). [85] Guided by the aforementioned case of high authority, I have considered the wordings in Clause C.2 of the LoA and in my view, it is undoubtedly a “pay when paid” clause as it speaks of the time for payment rather than of there being a condition precedent that the Plaintiff will only pay the Defendant if KKP pays the Plaintiff and if all NSCs are paid first. There are no words in Clause C.2 of the LoA which allows for it to be interpreted in the manner as urged by the Plaintiff upon this Court. The Plaintiff has clearly not discharged the burden of proving that payment to the Defendant is contingent on the Plaintiff receiving payment from KKP. S/N yrQ9pKi3j0eIe9E7JkAWjw [86] It follows from the above finding that the Defendant’s counterclaim is not premature because the Plaintiff’s liability to pay the Defendant is not contingent on the Plaintiff having received payment from KKP or on an outcome of the arbitration in the Plaintiff’s favor. And nor can the Plaintiff contend that “… payment can only be made to the Defendant after deducting out the Plaintiff’s payment to the NSCs” (see para 76 of the Plaintiff’s Written Submissions) as this Court has held that the obligation to pay the NSCs lies on the Plaintiff and the Plaintiff cannot take the benefit of its own wrong in not paying the NSCs to claim that the Defendant’s counterclaim is premature. [87] Moreover, by relying on PW4’s evidence and Clause C.2 of the LoA, the Plaintiff was attempting to prove the facts which have the effect of mounting a positive answer to the counterclaim. This the Plaintiff cannot do when all that it has pleaded is a negative defence. S/N yrQ9pKi3j0eIe9E7JkAWjw - Whether the total amount paid by the Plaintiff to the Defendant as progress payments is RM54,141,102.65 (Defendant’s version) or RM54,291,102.64 (Plaintiff’s version) resulting in the difference of RM149,999.00 [88] The Plaintiff asserted that it has paid RM149,999.00 (or RM150,000.00 as was stated by PW4 in her evidence) to the Defendant for project management fees under KKP’s LoA. This payment was made following correspondence from Datin Salmah. [89] The Defendant’s counsel drew the attention of the Court to PW4’s and DW2’s evidence and the documents showing the amount which was disbursed to the Defendant. Under Claim No. 1 for the Certificate of Payment dated 26.7.2013 for the amount of RM10,988,086.11 in the Annexure to WS-PW4, the payment received by the Defendant on 30.9.2013 is stated as the same amount as the Certificate of Payment. Although KKP, in the Form of Disbursement Notice dated 26.7.2013 issued to Malaysia Building Society Berhad (‘MBSB’), had requested that RM10,988,086.11 be disbursed to the Defendant, the Plaintiff’s General Ledger 1 for the entry on 31.12.2015 shows an adjustment of account for the Project in the sum of RM10,838,086.11. In the S/N yrQ9pKi3j0eIe9E7JkAWjw Statement of Account issued by MBSB to KKP, among the particulars for 4.9.2013 are the disbursement in the sum of RM10,838,086.11 to the Defendant and RM150,000.00 to the Plaintiff. [90] It can thus be safely concluded that the Defendant received RM10,838,086.11, and not RM10,988,086.11 as alleged by the Plaintiff. This means that the total amount paid by the Plaintiff to the Defendant as progress payments is as per the Defendant’s version, namely RM54,141,102.65. [91] At this juncture, it would be appropriate to mention that the Plaintiff did attempt to convince the Court to disregard DW2’s evidence on the ground of bias as DW2 had previously represented the Defendant in this suit and he admitted that he wants to assist the Defendant. It was also contended that DW2’s evidence is replicated by DW3 as both had produced a statement of account laying out the quantum that is owed by the Plaintiff to the Defendant. [92] The Plaintiff submitted that the statement of account is the only evidence that the Defendant has provided to support its claim and S/N yrQ9pKi3j0eIe9E7JkAWjw hence, by virtue of s 34 EA 1950 and the decisions in Sim Siok Eng & Anor v. Poh Hua Transport and Contractor Sdn Bhd [1980] 1 MLRA 618 and Tey Por Yee & Anor v. Protasco Bhd [2020] MLRAU 69 this evidence on its own is insufficient as proof of the Plaintiff’s liability for the counterclaim. Section 34 EA 1950 provides that: “Entries in books of account when relevant