TNB v. Rank Metal Sdn Bhd & Satu Lagi Kes [2014] 1 LNS 15 1776. [73] It is submitted that the fact that the loss of revenue claimed by the written statement under section 38(4) is “prima facie” evidence only of the loss of revenue, is the surest proof that the amount is an estimation of the 20 loss suffered by TNB which is open to the consumer to challenge. It is submitted that the realistic approach taken by the Court of Appeal in the Bright Rims and AWP Enterprise case be adopted. According to him 50 these cases held that in a case like this it is impossible for TNB to turn the clock back and re-meter the electricity supplied. As such, TNB’s calculation of its loss of revenue is necessarily an estimate and that estimate can only be rebutted if the consumer manages to show that there is a manifest error in the calculation or that the estimate is manifestly 5 unreasonable, excessive or wrong. [74] Learned counsel for TNB further submitted that it is well accepted in law that loss or damages need not be calculated to a point of mathematical certainty. In support, he referred to McGregor On Damages (19th 10 Edition) where at paragraph 10-002, under the chapter on ‘Certainty of Damages’ it is commented as follows: “On the other hand, where it is clear that some substantial loss has been incurred, the fact that an assessment is 15 difficult because of the nature of the damage is no reason for awarding no damages or merely nominal damages. As Vaughan Williams L.J. put it in Chaplin v. Hicks, the leading case on the issue of certainty. “The fact that damages cannot be assessed with certainty does not relieve the 20 wrong doer of the necessity of paying damages.” [75] Reference was also made to paragraph 10-012 of McGregor where it is commented as follows: 51 “A pecuniary loss may itself occasionally be difficult to assess although it is clear that it has been incurred. Thus in Biggin v Permanite, where in an action against a seller for delivering defective goods Devlin J held that the claimant was 5 entitled to claim damages in respect of the diminution in the market value of the goods, he further held that it was no bar to awarding substantial damages to the claimant that it was impossible to measure precisely the amount of the market diminution.” 10 [76] Thus, it was submitted that TNB’s calculation of its loss of revenue due to meter tampering may be based on an approximation or estimation of the loss caused by the tampered meter, as opposed to strict proof of damages to the last dollar as in the case of recovery of damages for 15 breach of contract. [77] The substance of the submission of learned counsel for Ichi-Ban Plastic is as follows. The general principles of law in this country must be equally applicable to the TNB, and TNB must discharge its burden to 20 prove its claim (in terms of liability and quantum) with no lesser burden than any plaintiff who commences an action in our Courts. Section 38(3) and (5) only gives some evidential advantages to TNB and does not relieve it of the legal burden to prove its claim when quantum as well as liability is challenged. TNB has to discharge the burden of proving both 25 52 the fact and the amount of damages before it could recover. If it fails to prove either the fact or the amount of damages, TNB will lose the action. If it proves the fact and damages but not its amount, TNB would be entitled to nominal damages only. Learned counsel relied on TNB v. Dunia Raya, TNB v. Ternakan Air Wui Kyee Sdn Bhd and TNB v. Ee-Lian Plastic 5 Industries (M) Sdn Bhd and Guan Soon Tin Mining Co v. Wong Fook Kum [1969] 1 MLJ 99, Taiwan Chief Precision Technology Sdn Bhd v. TNB [2014] 4 CLJ 23, Ong Ah Long v. Dr. S. Underwood [1983] CLJ (Rep) 300, Selva Kumar a/l Murugiah v. Thiagarajah a/l Retnasamy [1995] 1 MLJ 817 and Sumbang Projek Sdn Bhd v. Tenaga Nasional 10 Berhad [2014] 4 CLJ 323. In Sumbang Projek the Court of Appeal held that: “Considering that the plaintiff was claiming such a huge amount of money as back-charges, it was incumbent on the 15 plaintiff to adduce a more tangible, reliable and scientific method of calculation than a mere assumption based on some comparative graphs drawn by SP3 and one sudden drop in electricity usage/consumption on a particular date.” 20 [78] In the case of Bright Rims Manufacturing, its learned counsel submitted that the Court of Appeal misdirected itself when it held as follows: 53 “[14] …It is also obvious where a meter is tampered with, there is left no accurate metering of the electricity consumed. To require of the estimate to prove the amount claimed upon a balance of probabilities defeats the acceptance that it may be proved by an estimate. Herein lies the sting: to require too 5 high a standard of proof defeats the estimate and rewards the consumer who tampered with the meter. The wisdom of doing so is so questionable that justice cannot possibly require such a standard. The inequity is equally obvious, for such consumer comes not with clean hands. Justice must necessarily hold 10 that in the balance of justice, it must be the consumer who tampered with the meter who must bear the risk of having to pay more rather than the licensee to take a loss not because it was unable to prove the tampering but because it could not meet the high standard required from the estimate. 15 [15] The reasoning that the respondent had proved a manifest error upon a balance of probabilities is equally flawed. It is the amount claimed that has to be proved upon a balance of probabilities. A claim for backbilled sums due to 20 meter tampering is necessarily based upon an estimate. That estimate is accepted unless it is demonstrated that there is manifest error. It is a question of whether there is or there is not a manifest error. That there is upon a balance of probabilities a manifest error is insufficient to elevate 25 conjecture to a demonstration of manifest error. [16] We examined why the High Court considered that manifest error was proved upon a balance of probabilities. We 54 concluded it came from the fact that the document D2 referred to in para. 67 of the grounds was produced at the trial by the witness, without the appellant having had an opportunity to check and verify it as to its accuracy. It purported to be prepared from the respondent's records of its operations. Its 5 production was objected to. In a contest between the appellant licensee's estimate and the document generated by the consumer who tampered with the meter, the balance must favour the licensee. 10 [17] A further consideration is this. In para. 67 of the grounds, the High Court referred to a reply by PW3 and stated that the answer could not be understood and was of no assistance to the court. The issue raised with PW3 was his failure to make adjustments on various holidays and days when night shift 15 was not working. The cross-examination merely elicited the shortcomings but did not go on to establish how much that shortcoming amounted to. But the High Court, ignoring that except for the shortcomings where on certain days the estimates erred, the whole estimated sum of RM2,031,328.60 20 was rejected in toto. There was a failure to appreciate not only that the major part of the estimate was not shown to be incorrect, but also the alleged inaccuracy was not quantified so that the estimate can be further adjusted to arrive at the amount that can be claimed. We accept it is not for the court 25 to calculate the correct amount for an order, but it is equally true it is not for the appellant and respondent to establish by how much the estimate is to be corrected. The respondent not having elicited from PW3 what the adjustment should be for 55 those days where the factory was not working full time or night shifts, there was no reason to deny an order for the RM2,031,328.60 as claimed. This is particularly so when D2 was produced only at the defence stage of the case.” 5 [79] It was contended that the Court of Appeal’s finding as aforesaid was not supported by authority and departed from the cardinal rule in civil proceedings, namely, that it is for the plaintiff to prove its loses, and in the event that the presumption applies, the burden shifts onto the defendant to rebut the same on the balance of probabilities. 10 [80] In Nikmat Maju Development Sdn Bhd, in respect of the first question, its learned counsel submitted that the loss of revenue under section 38(4) should be based on strict proof damages as construed by the Court of Appeal. 15 [81] In Dunia Raya Enterprise Sdn Bhd, its learned counsel submitted that there is no necessity or purpose for this Court to answer the question posed, because the questions merely relate to the sets of facts in this appeal. Specifically on the first question posed, learned counsel 20 submitted that this question need not be answered by this Court as TNB failed to satisfy the requirements under section 38(4) to enable it to rely on the prima facie evidence. In any event, he contended that the answer 56 to the question should be in the negative as TNB must also discharge its evidential burden of proof on the quantum of its claim. He added that there must be corroboration on the accuracy in TNB’s calculation and it was incumbent on TNB to adduce a more tangible, reliable and scientific method of calculating the quantum. 5 [82] In Kepala Batas Bihun Sdn Bhd, in respect of the second question, its learned counsel submitted that the method of calculation used by TNB was in itself “manifestly unreasonable, excessive and wrong”. He argued that if this method of calculation was considered sufficient evidence, then 10 there would be no safeguard for the consumer. TNB will always choose the period of consistent and high usage of electricity to calculate its loss of revenue. 15 [83] The first question raised the issue as to the nature and extent of the evidence necessary to establish a claim under section 38 of the Act. Given the nature of the claim for the loss of revenue in this case, the question raises the issue of certainty or otherwise of the loss and how to 20 measure it. Although pecuniary loss have been incurred, it may be difficult to assess it. However, the fact that assessment is difficult due to the 57 nature of the damage is no reason of awarding no damages or nominal damages. In Biggin & Co. Ltd. and Another v. Permanite Ltd Berry Wiggin & Co. Ltd. (Third Parties) [1951] 1 KB 422, in action against a seller for delivering defective goods the Court held that claimant was entitled to claim damages in respect of the dimunation in the market value 5 of the goods. It was also held that where the market value was the measure of damages, the absence of precise evidence of it was no ground for awarding nominal damages only. The Court must determine the damages as best as it could. In his judgment Devlin J said at page 433- 439: 10 “It seems to me that one can very rarely arrive at an accurate figure of unsound value. Where the breach is non-delivery, there is often a market price which can be quoted, or evidence can be given of the price at which at the relevant date similar 15 goods were changing hands, but there is rarely any market price for damaged goods, since their value depends on the extent of the damage. If the actual damaged goods are sold with all faults, good evidence can be obtained of the difference in value, but such a sale is not always possible, and a claim 20 for substantial damages cannot be limited to goods which have been sold. Moreover, damage may arise from two sources. Suppose that goods are delivered which are inherently defective in breach of the contract of sale and that they are further damaged by negligent handling in breach of 25 the contract of carriage, and that in their damaged condition 58 they fetch 70 per cent of their sound value. Is the plaintiff to recover nominal damages only because he cannot prove against either defendant what part of the depreciation in value was due to his acts? It is one thing to say, as I have said, that this is the sort of situation which parties in contemplating the 5 measure of damage would be glad to avoid, and it is another thing to say that it is one which must necessarily result in an injured plaintiff obtaining no satisfaction. I think that in such a situation the court is bound to do the best that it can. It is no more difficult to estimate a plaintiff's loss in such 10 circumstances than it is to estimate the loss of earning power caused by physical disablement. The third parties submit that the latter case is entirely different. I do not think the fundamental principle on which damages are awarded for breach of warranty of quality, namely, that it "is the estimated 15 loss directly and naturally resulting in the ordinary course of events from the breach of warranty", is any different in principle. It is only that where precise evidence is obtainable, the court naturally expects to have it. Where it is not, the court must do the best it can. In Chaplin v. 20 Hicks (15), Vaughan Williams L.J., said: "In the case of a breach of a contract for the delivery of goods the damages are usually supplied by the fact of there being a market in 25 which similar goods can be immediately bought, and the difference between the contract price and the price given for the substituted goods in the open market is the measure of damages; that rule 59 has been always recognized. Sometimes, however, there is no market for the particular class of goods; but no one has ever suggested that, because there is no market, there are no damages. In such a case the jury must do the 5 best they can, and it may be that the amount of their verdict will really be a matter of guesswork. But the fact that damages cannot be assessed with certainty does not relieve the wrong-doer of the necessity of paying 10 damages for his breach of contract.” Fletcher Moulton, L.J., said much the same thing in his judgment.” 15 [84] The approach in Chaplin v. Hicks [1911] 2 KB 786, the leading case on the issue of certainty, and Biggin v. Permanite (supra) were applied by the Court in Zabihi and Janzemini & Ors [2009] EWCA Civ