14.7.2013 [38] The Defendant submitted that the Plaintiff has requested an extension of time for Roselle 1 Project (BDO 81) and Roselle 2 Project (BDO 86) from the Defendant, but the Defendant never granted any extension to the Plaintiff. However, since JLB gave the Defendant extension of time to complete the Works and for the sake of fairness to the Plaintiff, the Defendant did not refer to the days of delay as submitted above but referred to the days of delay calculated by JLB to claim LAD as follows: Project Extension of time given by the Employer Actual Compeletion Date Delay (day) Roselle 1 (BDO 81) Project 19.3.2015 11.6.2015 84 Roselle 2 (BDO 86) Project 19.3.2015 26.5.2015 68 Lovage (PG144) Project – Parcel 1 29.8.2015 20.9.2015 23 Lovage (PG 144) Project – Parcel 2 30.10.2015 3.12.2015 35 [39] Therefore, the total LAD ought to be paid by the Plaintiff to the Defendant is RM92,424.00 as specified below: Project Delay (day) LAD per day (RM) Total LAD (RM) Roselle 1 Project (BDO 81) 84 487.00 40,908.00 Roselle 2 Project (BDO 86) 68 535.00 36,380.00 Lovage Project (PG144) – Parcel 1 23 442.00 10,166.00 Lovage Project (PG 144) – Parcel 2 35 142.00 4,970.00 Total 92,424.00 [40] Hence, the Defendant submitted that SCJ was right in law and/or fact in dismissing the Plaintiff’s claim against the Defendant with cost of RM10,000.00 and allowing the Defendant’s counter claim against the Plaintiff with cost of RM10,000.00. The Respondent therefore prays that the Plaintiff’s appeal dismissed with cost. Court analysis and findings [41] By the following LOAs, the Defendant as the main contractor for the Project has appointed the Plaintiff to be a subcontractor to carry out the supply, delivery, lay and install complete with (c/w) testing and commissioning for electrical works system, telephone and street lighting infrastructure system for the Project (the “Works”): i. LOA dated 26 April 2013 (see page 275 of Appeal Records) for construction of 81 units of Terrace House Type Roselle 1 at Neighbourhood 12 Bandar Dato’ Onn, Johor Bahru, Johor; ii. LOA dated 26 April 2013 (see page 286 of Appeal Records) for construction of 86 units of Terrace House Type Roselle 2 at Neighbourhood 12 Bandar Dato’ Onn, Johor Bahru, Johor; iii. LOA dated 11 May 2013 (see page 272 of Appeal Records) for the construction of 4 units of show houses comprising of 2 units type Amber 1 and 2 Units Type Amber 2 At Bandar Tiram 1, Johor Bahru; and iv. LOA dated 20 July 2013 (see page 298 of Appeal Records) for the construction of 144 units of Terrace House Type Loverage at Taman Bukit Dahlia, Pasir Gudang, Johor. [42] In the present case, the court finds that the Plaintiff failed to call the relevant and material witnesses, namely Sim Sian Lye and Trevor Sim who was in charge of the Works and signed the documents marked as exhibits P5, P6, P7, P8, P9, P10, P11 and P12 to prove their claims againt the Defendant. PW1 informed that his younger brother named Trevor Sim and another person named Sim Sian Lye were the project managers who handled the Works for the Plaintiff and both of them were not called as witnesses at trial. [43] PW1 was not able to give affirmative answer when he was questioned on the matter of the Works. It shown that PW1 did not have full knowledge to the Works. PW1 could not produce any document to prove that the Plaintiff has completed Amber Project on 14.7.2013, Lovage (PG 144) Project on 16.4.2015, Roselle 1 (BDO 81) Project on 6.5.2015, and Roselle 2 (BDO 86) Project on 5.8.2015. [44] The Plaintiff has submitted progress claim vide the following letters to the Defendant: dated 10.4.2014 as in exhibit P10; House Type Roselle 1 dated 20.6.2016 as in exhibit P11; House Type Roselle 2 dated 20.6.2016 as in exhibit P12. [45] However, the Defendant did not pay to the Plaintiff the sum claimed by them. The Defendant argues that the amount claim is provisional and subject to be certified by the Defendant pursuant to clause 2. The Plainitff on the other hand contended failure of the Defendant to inform them the issuance of CPC has caused the Plaintiff could not submit their claims. [46] Clause 2 of the LOAs, inter alia, provide that— “The total subcontract works sum are provisional and the amount shall be…Final quantity shall be determined to actual work done on site or to refer as-built drawings….”. [Emphasis added] [47] Upon perusal of clause 2 of the LOAs, the court is of the view that there is no requirement of the issuance of CPC to enable the Plaintiff to submit their claims and therefore their arguments are completely devoid of merits. In this regards, the court agrees with the contention of the Defendant that the total contract sum for each project is subject to the certification by the Defendant based on the actual work done on site or to refer to as built drawings. The Plaintiff did not request for final measurement to be done by the Defendant pursuant to clause 2 of the LOAs. The Plaintiff has submitted the progress claim vide the letters dated 10.4.2014 and 20.6.2016 respectively. However, the amount claimed by the Plaintiff included the Works omitted by the Plaintiff which rendered their claims incorrect. Since the Plaintiff's claim for Works done is closely related to the total value of the Works to be certified by the Defendant, therefore the Plaintiff failed to prove their claims. [48] According to clause 6 of the LOAs, the Plaintiff was required to hand over all public utilities and services of the Works to the relevant authorities and obtain from these authorities the letter of acceptance pertaining to such hand over. The Plaintiff is also required to arrange for the submission of the meter installation application form to the relevant authorities. Clause 6 of the LOAs provide that— “for building works, the Plaintiff shall ensure that the submission for electrical meter shall remain valid until the end of defect liability period. Retention of RM80.00 shall be made until these meters are fixed. For the installation of these meters, the Plaintiff shall liase with the relevant authority and arrange for the submission of application form, setting account number, extension of validity of submission form, inspection, testing and finality fixing the meters. The subcontractor shall be required to hand over all the public utilities and sevices to the relevant authorities and obtain from these authorities the letter of acceptance pertaining to such handling over.”. [Emphasis added] [49] There is no dispute that the Plaintiff has obtained CFO for the street lighting infrastructure works for the Roselle 1 Project (BDO 81) & Roselle 2 Project (BDO 86). However, the Plaintiff has failed to complete the hand over job for street lighting to MBJB and obtain the street lighting acceptance certificate from MBJB. DW3 and DW4 have been appointed by the Defendant to carry out the work of handing over the street lights to TNB and MBJB and their testimonials are supported by TNB's letter dated 25.1.2018 which is marked as exhibit D23. The handing over of street lights to MBJB was done by DW3 and DW4 and supported by the street light acceptance certificate issued by the Bahagian Pengangkutan Bandar, Jabatan Kejuruteraan Majlis Bandaraya Johor Bahru and “sokongan pengeluaran sijil penerimaan lampu jalan” as in exhibit D26. Their evidence were never challenged by the Plaintiff during cross examination and therefore their evidence are deemed admitted. [50] Further, pursuant to clause 7 of the LOAs, the Plaintiff shall carry out and complete the Works diligently and in a good and workmanlike manner and using reasonable skill and care including the selection of any specifications for the materials and goods and workmanship to be used in the Works. However, the Works carried out by the Plaintiff were full of defects and even caused a fire incident occurred at the Fire Affected Premises on 21.7.2018. [51] According DW1, the cause of the fire involved a main switch in the store room at the ground floor of the Fire Affected Premises and there was no sign of renovation or electrical modification found at the Fire Affected Premises and the main switch box/distribution board at the Fire Affected Premises was still in its original condition. DW1 has prepared the report on the cause of the fire dated 14.8.2019 as in exhibit D13 and fire investigation report under paragraph 5(1)(b), Fire Services Act 1988 as in exhibit D14. Therefore, the court is of the view that the Plaintiff is responsible for the poor connection in the main switch box which is the cause of the fire incident as the main switch box/distribution board at the Fire Affected Premises was installed by the Plaintiff and the main switch box/distribution board at the Fire Affected Premises was still in its original condition. [52] The Plaintiff has failed to rectify the defects despite numerous demands by the Defendant, including the issuance of the letters as in exhibit D18 and exhibit D19 to the Plaintiff, however no action was taken by the Plaintiff. The Defendant has appointed DW3 and DW4 to complete the Works that were omitted by the Plaintiff and to rectify the defects. Therefore, the Defendant has to incur additional costs which include rectification costs, administrative costs at the rate of 15% and additional operating costs. The Defendant has imposed LAD against the Plaintiff for delay in completing the Works according to the completion date. The claim of LAD by the Defendant is based on the LAD imposed by JLB and not based on the clause 4 of each LOAs. The sum of LAD is summarised as in paragraphs 37 to 38 above. [53] Hence, the court is of the view that since the Plaintiff bears the burden of prove under section 103 Act 50 to prove their claims, and on the balance of probabilities, they have failed to do it. The Defendant has, on the balance of probabilities, proven their counter claims through the evidence and exhibits addced in court. Therefore, the court ruled that the findings of SCJ to dismiss the claim of the Plaintiff and allow the Defendant’s counter claim, with costs is upheld. [54] However, the court rules that the retention sum of RM136,926.15 (reduction sum) based on the documents produced by the Plaintiff, exhibits P1, P10, P11, and P12, to be returned by the Defendant and not the sum claimed by the Plaintiff. Clause 5 of the LOAs provide that— “All payments are subject to retention at the rate of 5% of the amount certified for each claim up to a maximum of 5% of the contract value… The retention sum of 5% shall be released within thirty (30) months upon issuance of the Certificate of Practical Completion and can be extended to another three (3) months.”. [Emphasis added] [55] In the present case, according to DW2, the CPC for the Amber Show House project had already been issued to the Defendant in 2014